Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4017 | 15 - Inter-service cooperation | The working group (Rec 1) should include relevant stakeholders deciding collectively what the declaration might mean for such things as sub and supporting plans and the relevant community messages and calls to action. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4034 | 15 - Inter-service cooperation | Efforts be increased to build trust, confidence and a common operating picture across PCS and RFS and seek mechanisms that identifies RFS and PCS as equitable partners in delivery of fire management across the territory. |
REC316-4048 | 37 - Funding | Government consider adopting a similar model to NSW for the management of emergency costs and reimbursements within ACT Government agencies. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4047 | 37 - Funding | Government consider an alternative funding arrangement for extraordinary costs borne by Government agencies in combating emergencies such as bushfires. |
REC316-4019 | 15 - Inter-service cooperation | In collaboration with other jurisdictions the ACT share the learnings for this bushfire event and work to officially embedded values officers and RRATs as key elements of bushfire response. |
REC316-4043 | 15 - Inter-service cooperation | NDIA be engaged in regard to information sharing in emergencies as part of the above actions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC307-2433 | 24 - Govt responsibility | To make planned burning and land clearing easier to understand and implement for landholders, a single point of contact for all bushfire mitigation inquiries and permits should be established. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1035 | 37 - Funding | That the State Government contribution towards the purchase of operational vehicles is to be retained at 80 percent but that the District Inspector can recommend full Government subsidy of vehicles for Brigades experiencing financial hardship. |
REC241-1001 | 24 - Govt responsibility | That the extent of forest and plantation fuel load fire risk in South East Queensland requires a designated government resources fire team to manage this risk and proactively conduct fuel mitigation burning; and provide a wildfire response to government land. |
REC241-1034 | 37 - Funding | That the State Government contribution towards the construction of Brigade sheds be changed from $10,000 to a maximum of 25 percent, subject to the approval of the Deputy Chief Officer, Rural Fire Service Queensland. |
REC241-0979 | 24 - Govt responsibility | That the Queensland Government liaise with the Federal Government with a view to securing incentives for employers that recognise loss of income and employee time for emergency operations. |
REC241-1033 | 37 - Funding | When a local Rural Fire Brigade requests an equipment and maintenance levy from a local government authority, that authority will either supply the brigade’s equipment and maintenance costs or raise the requested levy. The amount to be collected is to be agreed between the local Brigade and the local government authority. |
REC241-0954 | 24 - Govt responsibility | That a Ministerial Advisory Council be established to inform the Minister of matters relating to Rural Fire Service and SES volunteers. |
REC241-1032 | 37 - Funding | That the current Urban Fire Levy be changed to the Queensland Fire Levy. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-1004 | 15 - Inter-service cooperation | That a memorandum of understanding be developed between RFSQ and other organisations with fire fighting capacity at state level, to establish operational procedures when these organisations may be required for a joint response roles. Specifically, the intent will be: Vegetation Fire in a Rural Area: The Rural Fire Brigade in that area (boundary) is in charge and is the first Brigade called by Firecom. Structural Fire in a Rural Area: Firecom calls the Urban Brigade first and they control the incident. Local Rural Fire Brigade must also be notified by Firecom at the same time. Vegetation Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. At their discretion they may call Rural Fire Brigades for assistance. Structural Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC228-1616 | 37 - Funding | The Territory and Municipal Services Directorate should enhance internal monitoring of its implementation of bushfire management activities and spending under the Bushfire Operations Plan by routinely reconciling figures in this plan with those in the Directorate’s corporate financial system. |
REC228-1623 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should develop and routinely review a strategic bushfire capability for the ACT. The contribution of ACT Fire and Rescue (including the Community Fire Units) and the ACT Rural Fire Service (including Parks Brigade) should be explicitly stated. |
REC228-1614 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the ACT Bushfire Council, should conduct a review of the ACT Bushfire Council against its recently developed terms of reference (July 2013) within two years. |
REC228-1622 | 15 - Inter-service cooperation | The Emergency Services Agency and the Territory and Municipal Services Directorate should continue to improve working arrangements between the ACT Rural Fire Service Parks Brigade and the ACT Rural Fire Service headquarters, by: |
REC228-1610 | 24 - Govt responsibility | The Emergency Services Agency should annually review fire management zones and the Territory and Municipal Services Directorate should subsequently update the Regional Fire Management Plans. |
REC228-1620 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency, in consultation with the Territory and Municipal Services Directorate, should review the Farm FireWise Program, including: |
REC228-1609 | 25 - Inquiry, audit, lessons management and after action review | The Emergency Services Agency should undertake audits to meet the requirements in the Strategic Bushfire Management Plan for the preparation, sharing and publication of annual progress reports. Annual progress reports should be made available to the ACT Bushfire Council. |
REC228-1618 | 24 - Govt responsibility | The Emergency Services Agency, the Environment and Sustainable Development Directorate and the Territory and Municipal Services Directorate should strengthen across-Government delivery of major projects in the Strategic Bushfire Management Plan and Regional Fire Management Plans by collectively: |
REC228-1605 | 24 - Govt responsibility | The Justice and Community Safety Directorate should continue to review its strategic and accountability indicators and the Territory and Municipal Services Directorate should commence a review of its strategic and accountability indicators. The directorates should consult to develop complementary measures which better assess their bushfire management activities. |
REC228-1617 | 37 - Funding | The Territory and Municipal Services Directorate should annually (and on a cumulative basis) track and report on funds allocated for, and spent on, its Bushfire Operations Plan to the Minister for Police and Emergency Services. |
Rec-ID | Code | Recommendation |
---|---|---|
REC191-0273 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services implement system of fire levies for landholders situated in urban, iZone and village brigade areas. |
REC191-0266 | 37 - Funding | that QFRS cover the cost of annual vehicle inspection certificates for rural fire brigade registered vehicles. |
REC191-0275 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services ensure that the formula for distribution of funding as recommended above allows rural fire brigades to control any donation or sponsorship funding raised by individual brigades. |
REC191-0274 | 37 - Funding | that the for Minister for Police, Corrective Services and Emergency Services undertake a thorough review, including consultation with rural fire brigades, regarding the proposed formula for distribution of funding. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1956 | 15 - Inter-service cooperation | That courses and programs be conducted to increase the level of Incident Control System training and augment the expertise of people who are likely to perform functions in an incident management team |
REC126-1981 | 15 - Inter-service cooperation | That senior officers in the Australian Federal Police and the Emergency Services Agency maintain regular and meaningful contact during fire emergencies, to ensure full dissemination of information and thus facilitate the making of good operational decisions |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
REC126-1954 | 15 - Inter-service cooperation | That senior officers of the Emergency Services Agency give greater recognition to the skills, knowledge and experience of people from other agencies – particularly the land management agencies – as well as rural residents and private individuals and use these people in roles commensurate with their skills and experience |
REC126-1979 | 24 - Govt responsibility | That the policy and practice just recommended be the subject of a memorandum of understanding between the Emergency Services Agency and the Department of Territory and Municipal Services (previously the Department of Urban Services) or other relevant department or agency, so as to ensure that the land management agency on whose land a fire starts has responsibility to respond immediately to that fire in accordance with the applicable standards for weight of response. Further, the land management agency should be responsible for efforts to suppress fire until such time as it becomes clear that the suppression task is beyond capacity of the agency, at which point the ACT Rural Fire Service should assume direct responsibility for coordinating the ongoing response |
REC126-2009 | 24 - Govt responsibility | That a taskforce be established to give effect to the recommendations in this report |
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
REC126-1976 | 24 - Govt responsibility | That the Emergency Services Agency have authority over the land management agencies and other landholders in order to implement preparedness and prevention measures – including fuel-reduction works where there are failures in compliance |
REC126-2006 | 24 - Govt responsibility | I recommend that, as appropriate, the ACT cooperate with the Commonwealth in the implementation of the committee's recommendations and, in particular, give careful consideration to adoption of the following recommendations: |
REC126-1948 | 24 - Govt responsibility | That the Emergency Services Agency be removed from the Department of Justice and Community Safety and transformed into an independent statutory authority reporting directly to the responsible Minister. Note in this regard that Mr McLeod made a similar recommendation, and I endorse it unequivocally. Placing the agency within a government department puts unnecessary layers of bureaucracy between the agency and the responsible Minister, and the bureaucrats concerned usually have no special knowledge of or experience in emergency management, regardless of their seniority in the bureaucracy |
REC126-1962 | 24 - Govt responsibility | That, because of the small jurisdiction of the ACT (equivalent to one fire district in NSW) the ACT Government consider all possible options for the provision of fire services to the ACT, among them: |
REC126-1985 | 24 - Govt responsibility | That the Emergency Services Agency, with the suport of the ACT Government, seek to establish with the NSW Department of Environment and Conservation and the NSW Rural Fire Service a protocol that will provide for the establishment of a joint incident management team as part of unified control arrangements based on adoption of the following principles: |
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-2012 | 24 - Govt responsibility | If they are willing and available to participate, that the taskforce's membership include Mr Phil Cheney, Mr Tony Bartlett, Mr Val Jeffery and Mr John Lowe |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-1984 | 24 - Govt responsibility | That the Emergency Services Agency, with the support of the ACT Government, develop a single, new memorandum of understanding with the NSW Department of Environment and Conservation and the NSW Rural Fire Service, providing for liaison and joint operations as soon as it becomes apparent to whichever jurisdiction is managing a fire that the fire will probably affect the other jurisdiction. Joint operations should not be limited to when an incident occurs on both sides of the border, as is the current arrangement |
REC126-1942 | 24 - Govt responsibility | That the ACT Attorney-General and the ACT Government - in consulation with the Chief Justice of the ACT and the ACT Chief Magistrate - take legislative action that would have the effect of funds being directly appropriated annually to the courts, preferable along the lines of the Commonwealth model as it applies to the High Court of Australia, the Federal Court of Australia, the Family Court of Australia and the Federal Magistrates Court. Alternatively, the funds could be appropriated in accordance with the South Australian model, which has a seperate Courts Administartion Authority. |
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |