Rec-ID | Code | Recommendation |
---|---|---|
REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2496 | 10 - Infrastructure | To enhance shared capacity and collaboratively manage risk, the Chair of the Bundaberg LDMG use the Queensland Emergency Risk Management Framework (QERMF) process to determine if dam failure for Paradise Dam should be reported as a residual risk to the Bundaberg DDMG in this instance due to known changes in the risk profile. |
REC311-2495 | 10 - Infrastructure | To increase understanding of hazards and manage risks, dam failure for Paradise Dam be included as a separate risk within the Bundaberg LDMP. |
REC311-2491 | 10 - Infrastructure | To enable a shared understanding of the risk, changes in the risk profile of referable dams be clearly communicated by entities that own dams to stakeholders and the community likely to be affected. The communication process starts immediately after the change is identified, is tailored to its audience, makes clear the scale of the change, and is documented so that stakeholders and the community can make informed decisions for managing risks. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
REC308-2459 | 14 - Incident Mgt Teams | Significant effort should be invested to provide disaster decision-makers at every level with a shared understanding of risks, the situation, and capability, so that they can agree on the best decisions for the communities they serve. |