REC325-4321 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General of Emergency Management recommends this report be returned to the Office of the Inspector-General of Emergency Management to monitor, evaluate, and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC322-4246 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the Interagency Protocol for Fire Management be reviewed by all relevant entities, including representatives of the Butchulla people, and be updated as a matter of priority. Entities responsible for the protocol should implement a process for regular review and evaluation of its effectiveness. This review process should be conducted after a major bushfire event, or to reflect any material change to applicable legislation and policy. It should also consider pre-arranged approvals and a range of agreed fiscal protocols between the agencies. |
REC322-4252 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services regularly review and evaluate the effectiveness of the Queensland Bushfire Plan with land managers and stakeholders, including disaster management groups. A review should occur in line with any material change to the Queensland State Disaster Management Plan, the Disaster Management Act 2003, the Prevention Preparedness Response and Recovery Guideline, or after major bushfire events, to ensure appropriate alignment and currency. |
REC322-4218 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends this report be returned to the IGEM to monitor, evaluate and report on progress and implementation of the recommendations that are accepted in whole or in part by government. |
REC322-4219 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends should a Queensland Government Action Plan be considered, clarity about the intent of the recommendations be sought from the Inspector-General Emergency Management to assist in informing this process. |
REC322-4220 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends Queensland Fire and Emergency Services and the Department of Environment and Science monitor the progress of relevant improvement activities resulting from the K’gari (Fraser Island) Bushfire Review, through their respective lessons management programs. |
REC322-4240 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General Emergency Management recommends the next review of the Queensland State Disaster Management Plan examines and provides guidance in respect to the application of Queensland’s disaster management arrangements to support hazard specific events such as bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4178 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – in collaboration with the Country Fire Authority and local government – undertake a review of the current residual risk target to ensure that it remains contemporary in terms of its designated percentage value. The review should: |
REC318-4171 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that the State review (and where necessary amend) legislation including but not limited to the Country Fire Authority Act 1958, Forest Act 1958 and Local Government Act 2020 to: |
REC318-4176 | 26 - Research | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) lead the development and distribution of evidence-based land and fuel management tools for use by all legislated fuel management organisations to ensure a common approach to fuel management. |
REC318-4172 | 26 - Research | The Inspector-General for Emergency Management recommends that the State support the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) and its partners to expand the Safer Together program to: |
REC318-4182 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in partnership with agencies engaged in state, regional and incident control centres: |
REC318-4181 | 25 - Inquiry, audit, lessons management and after action review | The Inspector-General for Emergency Management recommends that Emergency Management Victoria – in collaboration with the emergency management sector and as part of the emergency management planning reforms: |
Rec-ID | Code | Recommendation |
---|---|---|
REC311-2504 | 25 - Inquiry, audit, lessons management and after action review | To enable entities in the sector to proactively work to achieve better results for the community, the recommendations and lessons of this review should be evaluated through the lessons management processes of entities involved in dam safety for their value and relevance. |
REC311-2494 | 22 - Role of local Gvt | To increase shared understanding of risks, enable coordinated plans and collaboratively engage with downstream community members, residents listed within a dam EAP be identified by the Local Government Area (LGA) they reside in. |
REC311-2505 | 25 - Inquiry, audit, lessons management and after action review | This report be returned to the InspectorGeneral Emergency Management to monitor, evaluate and report on progress and implementation of the recommendation(s) that are accepted in whole or in part by government. |
Rec-ID | Code | Recommendation |
---|---|---|
REC310-2481 | 22 - Role of local Gvt | Greater clarity about responsibilities for recovery at the community, local, and district levels should be considered in any future review of the Disaster Management Act (2003). |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2456 | 22 - Role of local Gvt | A Local Government Association of Queensland representative should be included on the Crisis Communications Network to enhance the delivery of consistent information across and between levels of government. |
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2369 | 26 - Research | I recommend that the New South Wales Police Force evaluate whether the use of noise-attenuation devices should be mandated when explosive distraction devices are used. |
REC292-2370 | 25 - Inquiry, audit, lessons management and after action review | I recommend that the New South Wales Police Force undertake a formal assessment of alternatives to the TOU’s current soft-point ammunition to determine whether a more appropriate form of ammunition is reasonably available. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1201 | 25 - Inquiry, audit, lessons management and after action review | Preventing Flood Related Fatalities: The NSW Government consider the recommendations from the Preventing Flood Related Fatalities Report when it is released. |
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1102 | 25 - Inquiry, audit, lessons management and after action review | SEMC Secretariat Community Emergency Management Officers should work with the Shire to document the Shire of Mundaring’s learnings from the Parkerville Stoneville Mt Helena fire with a view to sharing this with other local authorities particularly those facing similar situations in order to extend the range of tools available to assist local governments to understand their roles and responsibilities in future emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0804 | 26 - Research | Clarify roles, responsibilities and consider funding options for post-event collection of data and flood intelligence. |
REC238-0802 | 25 - Inquiry, audit, lessons management and after action review | Review the NSW state-wide governance arrangements for flood risk management so that broader issues identified by this Review can be most effectively addressed. |
REC238-0813 | 26 - Research | Develop and maintain a comprehensive flood model and flood modelling framework for the Hawkesbury-Nepean Valley. |
REC238-0807 | 26 - Research | Develop a comprehensive road evacuation network model for floods in the Hawkesbury-Nepean floodplain to inform evacuation capacity assessments and strategic transport and land use planning, and to assist with the real-time operational management of evacuation during floods. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1590 | 25 - Inquiry, audit, lessons management and after action review | Department of Broadband, Communications and the Digital Economy seek regular updates from Telstra on the implementation of the recommendations of its inquiry into the Warrnambool exchange fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0559 | 22 - Role of local Gvt | Early contact with the LG A is critical. |
REC226-0545 | 26 - Research | Improved understanding of fire behaviour in coastal heathlands would support sound risk management through the southwest of W |
REC226-0597 | 22 - Role of local Gvt | Given the prominent role played by the Shire in the management of welfare aspects in this emergency, there may be a need for state sponsored training for shire staff who are involved in implementing state emergency management policies and plans including how to deal with traumatised individuals. |
REC226-0593 | 22 - Role of local Gvt | Good Local Government planning and management facilitates community resilience. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0540 | 25 - Inquiry, audit, lessons management and after action review | : In due course, acts of bravery are considered and recommendations for awards are submitted, including commendations for the delivery of First Aid. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2871 | 22 - Role of local Gvt | Efficient and effective supporting tools and processes: high-quality local/municipal planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
Rec-ID | Code | Recommendation |
---|---|---|
REC200-1693 | 22 - Role of local Gvt | The Fire and Emergency Services Authority and local governments ensure that the ability to: |
REC209-1677 | 37 - Funding | A specialist investigation be conducted, using expertise from NT Treasury, to identify more appropriate ways to optimise the use of available funding for bushfire management. |
REC209-1643 | 25 - Inquiry, audit, lessons management and after action review | An evaluation be conducted into the integration of the appropriate elements of the South Australian Country Fire Service “Crimson” networking system into Bushfires NT ICT. |
REC209-1662 | 37 - Funding | Identify where Australian Government funding is available and apply for funding for integrating weed management, controlled burning, bushfire management and carbon farming initiatives. |
REC209-1642 | 37 - Funding | That a cost benefit analysis of an integrated ICT desktop and portable capability including iPads and iPhones for all operational personnel be conducted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3009 | 25 - Inquiry, audit, lessons management and after action review | That the Tasmania Fire Service conduct an audit of all shopping centres to ensure that there exists within those centres adequate fire protection and evacuation systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3451 | 37 - Funding | That port/channel managers should be able, within the general context of the pricing/cost recovery arrangements established under the Port Services Act 1995 and pricing determinations made by the Essential Services Commission, to recover the reasonable costs of meeting their statutory obligations (as per recommendation 26) through charges for prescribed service applied to port users. |
REC158-3450 | 37 - Funding | That emergency services are responsible for funding the development of the emergency services marine emergency response capacity/capability to meet their statutory obligations. |
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
REC158-3449 | 37 - Funding | That port/channel managers are responsible for funding the preparation of marine emergency risk assessments and marine emergency response arrangements and ensuring the availability of identified marine resources in support of response to a marine emergency, to meet their statutory obligations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3492 | 22 - Role of local Gvt | The review of the municipal emergency management planning guidelines being led by the Office of the Emergency Services Commissioner clarify local governments’ role in community information about emergencies. |
REC156-3506 | 26 - Research | The Office of the Emergency Services Commissioner facilitate further research into technologies that will reduce the need for the public to speak to an operator during an emergency as a component of the proposed emergency warning and alert system and Victorian Emergency Information Line. |
Rec-ID | Code | Recommendation |
---|---|---|
REC153-1776 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to establish means by which risk of bushfires, as created by continuous cropping, minimum tillage, direct drilling seeding practices and the retention of cropping stubble across the landscape, can be minimised. |
REC153-1775 | 26 - Research | That the Minister for Emergency Services cause independent scientific or other research to be undertaken to identify the effects of continuous cropping, minimum tillage, direct drilling seeding practices and of the retention of cropping stubble, in respect of bushfire risk and prevention. |
REC153-1780 | 22 - Role of local Gvt | That the Minister for Local Government cause rural councils to appoint an Officer whose duties consist entirely of bushfire prevention, such Officer being required to become a trained, operative member of the South Australian Country Fire Service during the currency of his or her appointment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-1958 | 37 - Funding | That the ACT Government allocate sufficient funds to enable full-time and volunteer firefighters to participate in relevant courses and programs |
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2241 | 37 - Funding | That the financial models incorporate changes in public land use, particularly ‘Our Forests Our Future’, and the subsequent changes in fire management priorities. |
REC104-2281 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA work cooperatively to review the management and application of bulldozers in fire suppression operations to ensure that they are used effectively, appropriately and are adequately supervised. |
REC104-2308 | 37 - Funding | That Government funding for Community Development Officers engaged in community support and rebuilding incorporates flexible resources to enable the purchase of services from a range of providers to ensure choice for those requiring support. |
REC104-2332 | 25 - Inquiry, audit, lessons management and after action review | That the Review of emergency operations centres by the Departments of Premier and Cabinet and Treasury and Finance and the Office of the Emergency Services Commissioner: |
REC104-2240 | 37 - Funding | That Government supports the immediate development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2201 | 26 - Research | That DSE undertake a formal study of the level of prescribed burning in south western Australia for its possible application in Victoria by comparing respective fuel arrays, terrain, weather, ground access, staff, prescribed burning days, areas conducive to prescribed burning and fire response systems. |
REC104-2277 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review methods of gathering and processing fire information to ensure all methods are pursued to greatest effect. |
REC104-2245 | 37 - Funding | That DSE includes the cost of tracks, as above, in the development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2293 | 25 - Inquiry, audit, lessons management and after action review | That aviation contractors be required to submit a copy of their annual independent regulatory compliance audit prepared for Civil Aviation Safety Authority to the State Aircraft Unit. |
REC104-2228 | 25 - Inquiry, audit, lessons management and after action review | That the Government identifies an appropriate body, or bodies, to undertake the audit of the Municipal Fire Management Plans. |
REC104-2244 | 37 - Funding | That DSE assesses the environmental and monetary cost of establishment and rehabilitation of temporary tracks, per 100 km, constructed during firefighting operations, and compare this with the recurrent costs of a program of maintaining existing tracks. |
REC104-2292 | 25 - Inquiry, audit, lessons management and after action review | That a systematic performance audit of State Aircraft Fleet contractors be conducted jointly by agency and SAU personnel. |
REC104-2304 | 22 - Role of local Gvt | That Municipal Emergency Resource Officers develop registers of volunteers willing and available to provide assistance and support during the response to, and recovery from, emergency incidents. |
REC104-2197 | 25 - Inquiry, audit, lessons management and after action review | That a review of the fuel management zones be implemented with a view to reducing the number of zones so as to focus clearly on (i) asset protection (especially at the Public/Private land interface), and (ii) ecological burns. |
REC104-2243 | 37 - Funding | That Government reviews the funding for DSE for the 2004-2005 fire season to ensure that appropriate resources are available for fire prevention planning and preparedness. |
REC104-2284 | 25 - Inquiry, audit, lessons management and after action review | That DSE and CFA review the management of personnel deployed ensuring that: |
REC104-2222 | 22 - Role of local Gvt | That Municipal Councils: |
REC104-2242 | 37 - Funding | That the financial arrangements incorporate full cost recovery for prescribed burning to be undertaken over a number of weekends utilising Project Firefighters, CFA volunteers and MFESB members. |
REC104-2282 | 25 - Inquiry, audit, lessons management and after action review | That quality control or performance assessments are routinely completed post fire season, to ensure that contractors who have not performed to an agreed standard are not re-engaged for the consequential rehabilitation works. |
REC104-2318 | 37 - Funding | When the research into prescribed burning and optimum fire protection described in Chapter 11, and the financial analysis of appropriate funding levels for prevention and suppression recommended in Chapter 15, are completed, DSE should develop a business case with Department of Treasury and Finance for assured funding to an agreed level over a three-year rolling cycle. |
REC104-2333 | 25 - Inquiry, audit, lessons management and after action review | That in doing so, this Review must consult with the agencies mentioned above, and others such as VICSES and the Departments of Human Services and Primary Industries. |