Rec-ID | Code | Recommendation |
---|---|---|
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
REC210-0696 | 21 - Role of Commonwealth Government | Carriers, councils and the Australian Communications and Media Authority should take into account the risk of flooding when considering the placement of telecommunications facilities. |
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |