Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2821 | 26 - Research | The National Health and Medical Research Council, in conjunction with key stakeholders, work collaboratively to provide more support for initiatives to increase international infectious disease research collaborations and build research capacity, particularly with neighbouring countries in the Asia-Pacific region. |
REC232-2819 | 9 - Community education | The Australian Government, coordinated by the Department of Health and Ageing and in consultation with the wider Australian community, develop a national public awareness campaign to better inform and engage the travelling public about infectious disease issues. This campaign should cover the risks associated with travelling overseas, preventative measures that can be undertaken to minimise these risks, and screening measures used at the border to prevent the importation of infectious disease. |
REC232-2818 | 16 - Training and behaviour | The Royal Australian College of General Practitioners provide resources and training to general practitioners on the complex health needs of migrants and refugees, with a focus on identifying infectious diseases which are notifiable in Australia, or diseases which are of specific concern to refugee and migrant communities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3364 | 37 - Funding | The funding arrangements that support the National Plan should be reviewed to ensure that the costs associated with both preparedness and response capability are equitably shared between the shipping and offshore petroleum industries. |
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
REC148-3169 | 37 - Funding | That the budgets for airport reception of horses and government controlled and operated quarantine stations be determined so as to be sufficient to fund the operations of the Quarantine Stations in accordance with these recommendations and any further procedures and requirements that are laid down from time to time. |
REC148-3185 | 37 - Funding | That, until the review of those fees has been completed, the fee charged by the government controlled and operated quarantine stations for thoroughbred stallions temporarily imported into Australia be not be less than $165.00 plus GST a day and the fee for all other horses be not less than $65.00 plus GST a day. No discount is to be allowed for the number of horses in a consignment. |
REC148-3184 | 37 - Funding | That the fees charged in relation to the importation and quarantining of horses be reviewed and fixed without delay having regard to the following factors: |