REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1269 | 35 - Business and Industry in relation to industry | That Government engages with non-government organisations that may provide services during emergency events to clarify the terms and conditions for support through a written arrangement (MOU or similar). |
REC297-1257 | 35 - Business and Industry in relation to industry | That in the event that Hydro Tasmania decides to start cloud seeding again, water managers, represented by DPIPWE, work with Hydro Tasmania to ensure appropriate, best practice application of the guidelines issued by the Agricultural and Resource Management Council of Australia and New Zealand. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1256 | 9 - Community education | That SES and Tasmania Fire Service share resources and align their community education programs and adopt an all-hazards approach to awareness. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
REC297-1251 | 9 - Community education | That all councils include an easily identifiable website link for the public to locate their Municipal Emergency Management Plan and community safety information. |
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |