Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
REC258-2555 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority changes the current two-tier regulatory framework (act and regulations) to a three-tier structure (act, regulations and standards), with: |
REC258-2531 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority’s Board exercises full governance control. The nonexecutive directors should possess a range of appropriate skills and backgrounds in aviation, safety, management, risk, regulation, governance and government. |
REC258-2538 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development and Department of Defence (and appropriate agencies) establish an agreed policy position on safety oversight of civil operations into joint user and military airports. |
REC258-2554 | 32 - Doctrine, standards, and reform | Recreational Aviation Administration Organisations, in coordination with the Civil Aviation Safety Authority, develop mechanisms to ensure all aircraft to be regulated under CASR Part 149 are registered. |
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
REC258-2562 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority amends the current Terms of Reference of the Industry Complaints Commissioner so that: |
REC258-2537 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority delegates responsibility for the day-to-day operational management of airspace to Airservices Australia, including the designation of air routes, short term designations of temporary Restricted Areas, and temporary changes to the classification of airspace for operational reasons. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2529 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority utilise the provision in their bilateral Memorandum of Understanding to accredit CASA observers to ATSB investigations. |
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
REC258-2536 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority amend the wording of their existing Memorandum of Understanding to make it more definitive about interaction, coordination, and cooperation. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2560 | 29 - Operational Health and Safety | The Civil Aviation Safety Authority devolve to Designated Aviation Medical Examiners the ability to renew aviation medical certificates (for Classes 1, 2, and 3) where the applicant meets the required standard at the time of the medical examination. |
REC258-2535 | 32 - Doctrine, standards, and reform | Airservices Australia, in conjunction with the Department of Infrastructure and Regional Development and the Civil Aviation Safety Authority, reconsiders the policy on ‘Assessment of Priorities’ that stipulates that air traffic controllers sequence arriving aircraft based on category of operation, rather than on the accepted international practice of ‘first come, first served’. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2527 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development plays a stronger policy role in the State Safety Program. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2533 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority: |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2912 | 29 - Operational Health and Safety | The review team recommend that the safety case system be strengthened by including provisions for a design notification scheme along the lines of that under the British Offshore Safety Case Regulations. |
REC189-2906 | 21 - Role of Commonwealth Government | In order to improve the effectiveness of National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA), with similar benefits for State or Territory regulators, attention should be given to the following actions. |
REC189-2911 | 29 - Operational Health and Safety | The review team recommend that: |
REC189-2910 | 21 - Role of Commonwealth Government | NOPSA should: |
REC189-2909 | 32 - Doctrine, standards, and reform | Equipping the regulator with a wider range of compliance tools under the legislation should continue to be a policy priority. The aim should be to enhance the regulator’s capacity to secure compliance in an appropriately graduated way. The opportunity should be taken to ensure that the regulator and inspectors can, in appropriate cases, bring proceedings that do not require referral to the Commonwealth Director of Public Prosecutions, such as actions for civil penalties or injunctions. |
REC189-2914 | 32 - Doctrine, standards, and reform | The review team recommend that: |
REC189-2908 | 21 - Role of Commonwealth Government | To ensure that NOPSEMA is in a strong position to perform its functions effectively: |
REC189-2913 | 21 - Role of Commonwealth Government | In developing and improving its policies and practices for stakeholder engagement, NOPSA should ensure that: |
REC189-2907 | 29 - Operational Health and Safety | a) For the purposes of designing and implementing its regulatory activities, National Offshore Petroleum Safety Authority (NOPSA) should continue to identify priority hazards and risks and their underlying causes, in consultation with the NOPSA Advisory Board and stakeholders (see Theme 9, Stakeholder engagement). |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3298 | 32 - Doctrine, standards, and reform | Reliance upon one barrier against a blowout must not take place except with the prior written approval of the relevant regulator and then only in a true emergency situation (see below). |
REC177-3316 | 32 - Doctrine, standards, and reform | Wells should be re‐entered with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3339 | 32 - Doctrine, standards, and reform | The Inquiry supports the objective (rather than prescriptive) approach to regulation now followed in Australia. However, the pendulum has swung too far away from prescriptive standards. In some areas relating to well integrity there needs to be minimum standards. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3375 | 21 - Role of Commonwealth Government | For the purposes of that review, the Minister should issue a ‘show cause’ notice to PTTEPAA under s 276 of the OPGGS Act. |
REC177-3287 | 38 - Agency/Department Reporting | Licensees should be subject to an express obligation to inform regulators of problems which arise in the course of installing barriers, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3361 | 32 - Doctrine, standards, and reform | The National Plan should be revised to ensure that it fully comprehends environmental matters and that it recognises the importance of the prompt implementation of Scientific Monitoring to facilitate the assessment of the environmental impacts of an incident. |
REC177-3276 | 32 - Doctrine, standards, and reform | WOMPs should be comprehensive and freestanding, rather than an overarching document cross‐referencing many other documents (although the Inquiry also recommends a freestanding well control manual; this should be a guide to rig and onshore personnel on good oilfield practice). |
REC177-3292 | 32 - Doctrine, standards, and reform | Licensees should be subject to an express obligation to inform regulators of the proposed removal of a barrier, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. Removal of a barrier should not take place without prior written approval of the relevant regulator(s). |
REC177-3309 | 32 - Doctrine, standards, and reform | If performance of barrier installation is outsourced by a licensee, the contractor (for example, the cementing company) should be engaged on terms which clearly require the provision of expert advisory services by the contractor with respect to barrier integrity. |
REC177-3326 | 32 - Doctrine, standards, and reform | Prior to commencement of drilling operations, senior representatives of the licensee and rig operator should exchange certificates to the effect that their respective key personnel and contractors have been informed in writing of agreed well control arrangements. |
REC177-3350 | 32 - Doctrine, standards, and reform | The recommendations of the Inquiry in relation to suitable ways of achieving well integrity contained in Chapter 3 be included in a guidance manual that is issued for the assistance of industry and regulators. |
REC177-3368 | 32 - Doctrine, standards, and reform | The regulatory framework should provide that in respect of all activities in Commonwealth waters: |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3297 | 32 - Doctrine, standards, and reform | A minimum of two barriers should be in place at all times (including during batched operations) whenever it is reasonably practicable to do so. |
REC177-3315 | 32 - Doctrine, standards, and reform | PCCCs should be installed in a timely manner (for example, to prevent corrosion in the MLS apparatus). Non‐installation in order to park a BOP is not acceptable. |
REC177-3335 | 32 - Doctrine, standards, and reform | Licensees, rig operators and relevant third party contractors should develop well control competency standards for key personnel in other entities involved in well control operations. |
REC177-3355 | 32 - Doctrine, standards, and reform | The Inquiry also supports Bills and Agostini’s recommendation: ‘…in relation to safety case development and compliance overall, that NOPSA revise its approach to interacting with operators prior to the safety case assessment process and subsequently direct more resources into its advisory functions. We further recommend that NOPSA develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on the latest information, including the interaction with the operator’. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3302 | 32 - Doctrine, standards, and reform | Industry, regulators, and training/research institutions should develop standards that address best practices for cementing operations (including liaising, as appropriate, with overseas regulators) with a view to overcoming problems which can effect the integrity of cemented casing shoes, annulus and cement plugs. |
REC177-3320 | 32 - Doctrine, standards, and reform | Any pro‐formas used by licensees, rig operators and contractors for recording information about installation of barriers should explicitly provide for ‘exception reporting’, that is, the form should include provision for recording any unforseen or untoward events which occur in the course of installation. |
REC177-3343 | 32 - Doctrine, standards, and reform | The OPGGS Act should be amended to allow for a power to suspend a petroleum production licence (in addition to the current power to cancel a licence or suspend its conditions). |
REC177-3360 | 42 - Culture and Heritage | DEWHA should participate in training programs and exercises relevant to an oil spill in the marine environment. |
REC177-3275 | 32 - Doctrine, standards, and reform | Well Operations Management Plan (WOMPs) submitted by licensees to the regulator(s) should continue to be the primary framework document for achieving well integrity. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3308 | 32 - Doctrine, standards, and reform | Volumes of cement used in connection with barrier installation should be calculated with the assistance of a pro‐forma which records all relevant baseline data, which should be verified by onshore personnel. |
REC177-3325 | 32 - Doctrine, standards, and reform | Relevant personnel from licensees and rig operators should meet face to face to agree on, and document, well control issues/arrangements prior to commencement of drilling operations. Well control should be regarded as a so‐called SIMOP to signify its critical importance to both licensees and rig operators, and to ensure that they each take responsibility for achievement and maintenance of well control. |
REC177-3349 | 21 - Role of Commonwealth Government | In the meantime, the Minister should: |
REC177-3367 | 32 - Doctrine, standards, and reform | Procedures and accountabilities should be established to ensure, in the event of a future incident, that: |
REC177-3280 | 32 - Doctrine, standards, and reform | Well construction and management plans should include provision for an independent compliance review of well integrity (i) in the event of stipulated triggers; and (ii) at least once in the period between perceived achievement of well integrity and production. The independent compliance review should be undertaken by an expert who is not involved in the day‐to‐day drilling operations. Reviews should be completed in sufficient time to enable results to be implemented in a meaningful manner. |
REC177-3296 | 32 - Doctrine, standards, and reform | Use of single strings of intermediate casing to penetrate hydrocarbon bearing zones should be carefully risk assessed. Multiple strings of intermediate casing have the advantage of isolating lost circulation zones and sealing off anomalous pressure zones. If intermediate casing is set in a hydrocarbon zone it should be treated as production casing. |
REC177-3314 | 32 - Doctrine, standards, and reform | Secondary barriers (including PCCCs) should only be installed, tested, and removed with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3334 | 32 - Doctrine, standards, and reform | Licensees, rig operators, and relevant third party contractors should develop well control competency standards for their key personnel. Wherever possible, the competencies of key personnel should be benchmarked against their roles and responsibilities. |
REC177-3354 | 32 - Doctrine, standards, and reform | NOPSA develop a policy of engagement with operators so as to enable experts (including safety experts) to canvas all available options for well control in the event of a blowout. |
REC177-3373 | 32 - Doctrine, standards, and reform | Arrangements should be developed to minimise duplication between the EPBC Act and the OPGSS Act Environment Regulation. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3301 | 32 - Doctrine, standards, and reform | The industry standard of two barriers should be replaced with the concept of ‘two or more barriers’ as a minimum standard. A minimum standard when operations proceed normally should never be regarded as a sufficient standard in other circumstances. |
REC177-3319 | 32 - Doctrine, standards, and reform | Drilling programs dealing with barrier installation should incorporate relevant aspects of manufacturer’s instructions. |
REC177-3342 | 32 - Doctrine, standards, and reform | Written (rather than verbal) approval from the DA (or new regulator) should be obtained before the commencement of well activities that lead to a physical change of a wellbore, other than in a true emergency situation (requiring amendment to regulation 17 of the Management of Well Operations Regulations). |
REC177-3359 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed to clarify the arrangements to apply in Commonwealth waters regarding key roles and responsibilities, including in relation to the ESC, in the event of an oil spill. This should also address any necessary training required. |
REC177-3274 | 21 - Role of Commonwealth Government | The Minister should appoint a senior policy adviser to investigate and report on the best means to implement the recommendations contained in this Chapter 3 of this report. |
REC177-3290 | 38 - Agency/Department Reporting | The successful installation of every barrier should be the subject of written verification within and between licensees and rig operators; and should be the subject of explicit reporting to the relevant regulator(s). |
REC177-3307 | 32 - Doctrine, standards, and reform | Any indication of a compromised cemented shoe which cannot be resolved with a high measure of confidence should result in the installation of additional well control barrier(s). |
REC177-3324 | 32 - Doctrine, standards, and reform | The mere fact that the rig is over the platform should not be regarded by licensees or regulators as sufficient justification for reliance on only one barrier. The default position should be that producible wells are shut‐in when a rig is moved on and off a platform, or when a drilling unit is moved between wells on a platform. |
REC177-3348 | 21 - Role of Commonwealth Government | Responsibility for well integrity should be moved to NOPSA (as also proposed by the Productivity Commission). |
REC177-3366 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed: |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3313 | 32 - Doctrine, standards, and reform | Barriers should not be installed or removed off‐line. The derrick should be located over a well at the time of removal and installation of any barrier. This will enable more decisive action to be taken in the event a problem arises. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3353 | 32 - Doctrine, standards, and reform | The regulatory regime should also impose an obligation on an operator to ascertain the availability, and provide details to the regulator, of any potential relief well rigs, prior to the commencement of drilling operations (including prior to each phase of a drilling operation where applicable). |
REC177-3372 | 21 - Role of Commonwealth Government | OSCPs should be endorsed by AMSA prior to regulatory approval to ensure that they align with the National Plan. Once field operations commence, the capability of operators should be assessed against their plans, and exercises conducted to ensure the plans remain effective. |
REC177-3377 | 32 - Doctrine, standards, and reform | The Minister consider legislative amendments to the OPGGS Act which make clear that |
REC177-3284 | 32 - Doctrine, standards, and reform | Memoranda of Agreement should be entered into between operators in relation to provision of emergency assistance in the event of blowouts. |
REC177-3300 | 32 - Doctrine, standards, and reform | Licensees and rig operators should install an additional barrier whenever (i) there is any real doubt as to the integrity of any barrier; (ii) whenever the risk of flow from a reservoir increases materially in the course of operations; and (iii) where the consequences of a blowout are grave (for example, for reef systems or shorelines). |
REC177-3318 | 32 - Doctrine, standards, and reform | Manufacturers should be consulted about how to address non‐routine operational problems affecting their well control equipment. |
REC177-3341 | 32 - Doctrine, standards, and reform | The definition of ‘good oilfield practice’ in the OPGGS Act is unduly narrow. The current definition is incapable of application except where things ‘are generally accepted as good and safe’. The definition should be amended such that ‘good oilfield practice includes…’. |
REC177-3358 | 21 - Role of Commonwealth Government | The body established to undertake a central coordination and facilitation role in the event of any future blowout in Commonwealth waters should undertake to make all relevant information publically available from one, authoritative and easy to access source. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3306 | 32 - Doctrine, standards, and reform | It should be standard industry practice to re‐test a cemented casing shoe (that is, after WOC) whenever the plugs do not bump or the float valves apparently fail. Standard industry practice should require consideration of other tests in addition to a repeat pressure test. |
REC177-3323 | 32 - Doctrine, standards, and reform | Where multiple wells are drilled, operations and occurrences at one well must be carefully assessed for any implications with respect to well control at other wells. |
REC177-3347 | 21 - Role of Commonwealth Government | The proposal of the Productivity Commission’s Research Report (Review of Regulatory Burden on the Upstream Petroleum (Oil and Gas) Sector, April 2009) to establish a NOPR should be pursued at a minimum. |
REC177-3363 | 32 - Doctrine, standards, and reform | DEWHA, in concert with AMSA and with expert input, should develop ‘off the shelf’ monitoring programs that can be speedily implemented following incidents in Commonwealth waters. In this context, the utility of the current Scientific Monitoring program should be peer reviewed to inform future policy. |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3312 | 32 - Doctrine, standards, and reform | The BOP and rig should not move from a well until barrier integrity has been verified. |
REC177-3328 | 32 - Doctrine, standards, and reform | All communications between on‐rig and onshore personnel relating to well control should be documented in a timely manner. |
REC177-3352 | 32 - Doctrine, standards, and reform | The regulator, rather than the responsible Minister, should be given the power to direct an operator to use a particular rig for the purpose of well control operations, if appropriate in the circumstances, and the power should be used in the future if that rig is the best option available. This would necessarily involve the operator fully compensating for the use of the rig and any other associated costs. The Inquiry suggests that this power could be invoked and given effect as a condition of an operator’s licence. |
REC177-3371 | 21 - Role of Commonwealth Government | The Government should examine the scope for a single environment plan to meet the regulatory requirements of both the OPGGS Act and the EPBC Act. This could possibly be achieved by way of bilateral agreements and accreditation arrangements and/or legislative amendment. |
REC177-3376 | 21 - Role of Commonwealth Government | In carrying out a review of PTTEPAA’s permit and licence, the Minister should have regard to this Report, particularly (i) the adverse findings set out in this Chapter; and (ii) the extent to which PTTEPAA has implemented the Action Plan submitted to the Inquiry, or otherwise addressed the matters canvassed in this Report. |
REC177-3283 | 32 - Doctrine, standards, and reform | A separate, identifiable barrier manual should be agreed upon and used by licensees, rig operators, and cementing contractors. These manuals should set out best industry practice in relation to achieving and maintaining well integrity. They should describe barrier types, barrier standards, general principles of well integrity, testing and verification methods and technologies, standard operating procedures (including procedures for the capture and communication of relevant information within and between relevant stakeholder entities). Barrier manuals should address blowout control during drilling, completion, re‐entry, tie‐back of casing strings and so on. Barrier manuals should be the subject of expert external review, and should be regularly updated. |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3317 | 32 - Doctrine, standards, and reform | Any equipment (including PCCCs) used as, or to install, a barrier should be manufactured for that purpose and be generally recognised as fit for purpose. If equipment is designed in‐house by a licensee or rig operator it should not be approved for use unless and until it is subjected to expert external analysis. |
REC177-3340 | 32 - Doctrine, standards, and reform | To better ensure that ‘risks’ are identified and managed in accordance with sound engineering principles and good oilfield practice, it is recommended that regulation 25(1)(a)(i) and (2)(a)(i) of the Management of Well Operations Regulations, be reworded as follows: ‘A titleholder must not commence / continue a well activity if…a well integrity hazard exists in relation to the well’. |
REC177-3357 | 21 - Role of Commonwealth Government | In any future similar blowout or offshore emergency situation, the Minister appoint (through either a NOPR or the relevant Department) a senior public servant to establish and oversight a central coordinating body that will facilitate interaction between regulators, industry, AMSA and the owner/operator. Primary responsibility for stopping a blowout should remain with the owner/operator but should be subject to direction from the central coordinating body in consultation with stakeholders (including the owner/operator). |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3305 | 32 - Doctrine, standards, and reform | Cement integrity should be evaluated wherever practicable by way of cement evaluation tests, rather than relying on pre‐operational calculations of cement and displacement fluid volumes. |
REC177-3322 | 32 - Doctrine, standards, and reform | Batched drilling operations should only be undertaken after careful assessment of the special risks which such operations give rise to; well control must be maintained during the course of batched drilling operations. |
REC177-3346 | 21 - Role of Commonwealth Government | A single, independent regulatory body should be created, looking after safety as a primary objective, well integrity and environmental approvals. Industry policy and resource development and promotion activities should reside in government departments and not with the regulatory agency. The regulatory agency should be empowered (if that is necessary) to pass relevant petroleum information to government departments to assist them to perform the policy roles. |
REC177-3362 | 32 - Doctrine, standards, and reform | Procedures for the approval of development projects should ensure that conditions of approval are comprehensive and clearly set out the obligations of their proponents in relation to environmental matters (including expected monitoring and remediation obligations). |
REC177-3277 | 32 - Doctrine, standards, and reform | The concept of ‘good oilfield practice’ should be supplemented by the requirement to incorporate into WOMPs non‐exhaustive minimum compliance standards in relation to well control: for example, stipulations as to when BOPs and/or well control systems must be in place and when they can be removed and minimum barrier requirements (a number of other factors that should be stipulated are outlined in other recommendations below). |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3311 | 32 - Doctrine, standards, and reform | Horizontal or high angle penetration of a reservoir should be avoided wherever practicable until such time as the apparent problems associated with the cementing of a casing shoe in these situations are satisfactorily overcome. If a casing string does penetrate a well horizontally or at a high angle, standard practice should be to install two secondary barriers in addition to the cemented casing shoe. |
REC177-3327 | 32 - Doctrine, standards, and reform | Information relevant to well control must be captured and communicated within and between licensees and rig operators (and relevant third party contractors), in a manner which ensures it comes to the attention of relevant personnel. In particular, protocols should be developed to ensure that changes in shift and hitch do not operate as communication barriers. |
REC177-3351 | 21 - Role of Commonwealth Government | In the future, and in the interests of ensuring that all possible well control options are comprehensively pursued to exhaustion, decisions as to well control response options should be the result of collaboration between the regulator and the operator rather than leaving one party to make unilateral judgements as to the appropriateness of various well control operations. The regulator should provide transparent and contemporaneous explanations to the public of all well control options under consideration at any particular time. |
REC177-3370 | 32 - Doctrine, standards, and reform | Environment plans and OSCPs should be made publicly available as a condition of approval of proposals under the OPGGS Act, and should clearly set out Scientific Monitoring requirements in the event of an oil spill. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3143 | 21 - Role of Commonwealth Government | The role of the advisory Board, namely to give advice to Ministers and NOPSA when asked, should be made clear to Board members and all stakeholders. The Board and NOPSA should consider the need for a clear description of who does what based on the legislated responsibilities of the NOPSA CEO. |
REC149-3130 | 32 - Doctrine, standards, and reform | The regulations pertaining to vessels of opportunity or their interpretation should be changed to facilitate a risk based approach to regulation. This approach will be consistent with the approach taken in other jurisdictions. |
REC149-3135 | 29 - Operational Health and Safety | The initial acceptance of a new facility Safety Case should be in conjunction with inspection of a facility upon commencement of operations. |
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
REC149-3129 | 32 - Doctrine, standards, and reform | The consequences of the disapplication of the Navigation Act 1912 should be analysed, the actual consequences identified and unintended consequences addressed. |
REC149-3147 | 29 - Operational Health and Safety | As all stakeholders have responsibility for safe outcomes, decisions regarding target subjects for safety promotion need to have the support of all stakeholders including NOPSA and the workforce. Industry, which ultimately has the responsibility for managing risk as well as funding the promotion, should take a leadership role in implementation. |
REC149-3134 | 32 - Doctrine, standards, and reform | Improved and agreed guidelines for Safety Case application and assessment, including suggested structure and content, would alleviate many current problems related to Safety Case processes. |
REC149-3141 | 32 - Doctrine, standards, and reform | NOPSA should complete the next revision of Safety Case guidelines in consultation and agreement with stakeholders and continue its program to achieve consistency with a firmer hand from the CEO and management. |
REC149-3128 | 29 - Operational Health and Safety | National Offshore Petroleum Safety Authority (NOPSA) should develop guidelines in consultation with stakeholders to provide clarity and consistency to the process which ultimately will result in better safety outcomes. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3140 | 32 - Doctrine, standards, and reform | The industry should provide advice to NOPSA on where the regulations do not provide sufficient clarity and consider developing broad policy/process guidelines in consultation with the regulator to provide clarity and consistency. Regulators should not take personal views or preferences. |
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3144 | 29 - Operational Health and Safety | The Safety Case proponent should be allowed some flexibility to involve appropriate experience matched with the proposed workforce competencies to enable the Safety Case to be developed with value adding processes. Subsequent to the hiring of the workforce Final Government Response Offshore Petroleum Safety Regulation Inquiry and 2008 Review of NOPSA Operational Activities and preferably before the commencement of operations a review of the Safety Case should take place with the new workforce to ensure they understand the accepted Safety Case, its risks and Safety Management Plan. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3138 | 38 - Agency/Department Reporting | The current KPI measures used by the Regulator and industry need to be reassessed and the performance indicators need to be related to the risk profiles of the industry. The industry needs to develop the indicators, which need to be agreed and measured by the industry in discussion with other stakeholders. The KPI's selected should be published in comparison with the worldwide offshore industry and with other industries. NOPSA should continue discussions with Australian Safety and Compensation Council (ASCC) with a view to adopting their goals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3671 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include a requirement for the debriefing of all senior rail and emergency response personnel involved in any rail accident, so as to determine the way or ways in which emergency response arrangements for rail accidents can be continually improved, and thereafter implement such improvements. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3736 | 32 - Doctrine, standards, and reform | The RailCorp passenger containment policy must be abandoned. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3680 | 29 - Operational Health and Safety | All trains must be fitted with a minimum of two independent engineering defences to minimise the risk of derailment or collision in the event of train driver incapacitation. |
REC121-3699 | 32 - Doctrine, standards, and reform | All reported train defects should be certified by a person in a supervisory position in RailCorp as having been rectified. |
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
REC121-3741 | 29 - Operational Health and Safety | The operation of the train doors should have an override facility whereby the train driver or the guard can override an internal passenger emergency door release system if the door release is interfered with when there is no emergency. There should be an alarm, together with an intercom, in the train guard’s compartment so that, if a passenger attempts to initiate an emergency door release, there is an appropriate delay during which time an alarm sounds in the train guard’s compartment and the guard can then, after first attempting to speak via the intercom to the person concerned, if necessary, override the door release, and make an appropriate announcement over the intercom system in the train. |
REC121-3763 | 32 - Doctrine, standards, and reform | The ITSRR should publish guidelines to be followed by accredited organisations. |
REC121-3662 | 32 - Doctrine, standards, and reform | The rail displan should provide for the site controller to have complete control of the site, with other agencies co-ordinating with and supporting him or her, until the rescue phase of the emergency response has been completed. |
REC121-3685 | 32 - Doctrine, standards, and reform | The ITSRR should impose a standard in relation to the collection and use of data from data loggers. |
REC121-3705 | 32 - Doctrine, standards, and reform | The ITSRR should develop standards for periodic medical examinations which include the following: |
REC121-3730 | 32 - Doctrine, standards, and reform | Legislation should be enacted and any necessary arrangements made, to enable the ATSB to review any reports of any investigation by a rail organisation or the OTSI into any serious incident or accident in New South Wales. |
REC121-3749 | 29 - Operational Health and Safety | All new rolling stock must be designed with an area of the roof through which emergency services personnel can access a rail car without encountering wiring or other equipment. That access point must be clearly marked with words such as “emergency services cut here”. |
REC121-3769 | 32 - Doctrine, standards, and reform | The ITSRR should continue to participate in the development of a national system for rail safety regulation, provided that any ultimate agreement between the States and Territories and the Australian Government does not produce a safety outcome for New South Wales that is less than would be achieved by the implementation of all the recommendations contained in this report. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3668 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include action checklists of the steps that each employee is required to take, and the order for specific employees to follow in case of emergency. |
REC121-3692 | 32 - Doctrine, standards, and reform | Communications protocols and procedures should be standardised and mandated by regulations making them a condition of accreditation. |
REC121-3711 | 29 - Operational Health and Safety | The ITSRR should establish an electronic document control system to enable effective and reliable information to be gathered for monitoring the safety of the New South Wales rail system. |
REC121-3735 | 29 - Operational Health and Safety | Risk assessments of occupational health and safety issues by RailCorp should include an analysis of broader public safety risks and not be confined to narrow occupational health and safety issues. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3679 | 32 - Doctrine, standards, and reform | The rail safety regulator should set standards for the design, manufacture, testing and commissioning of rolling stock to ensure that the rolling stock is fit for its purpose. |
REC121-3698 | 32 - Doctrine, standards, and reform | No RailCorp train should enter into revenue service or remain in service if, in the opinion of the driver in charge of that train, any defect in it creates a risk of injury. |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3740 | 29 - Operational Health and Safety | The internal passenger emergency door release should be fitted with a facility which prevents it from operating unless the train is stationary. |
REC121-3762 | 32 - Doctrine, standards, and reform | The Chief Executive of ITSRR should have sole accountability and responsibility for the regulation of rail safety in New South Wales. |
REC121-3661 | 32 - Doctrine, standards, and reform | The rail displan should include provision for the appointment of a rail emergency management co-ordinator at the RMC, and an on-site rail commander with the sole function of assisting and supporting the emergency services during the rescue phase of the emergency response. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3748 | 29 - Operational Health and Safety | All new rail cars must have appropriate signage and lighting identifying escape routes in the case of emergency. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3773 | 32 - Doctrine, standards, and reform | The ITSRR should ensure that RailCorp establishes a safety management system containing the 29 elements identified in the SMSEP report, and ensure the ongoing monitoring and improvement of the safety management system established. |
REC121-3667 | 32 - Doctrine, standards, and reform | RailCorp should develop and implement an emergency response plan for management of all rail accidents. Such a plan should be subsumed by the rail displan in the case of serious accidents or incidents. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3734 | 29 - Operational Health and Safety | RailCorp should integrate its management of occupational health and safety into its overall safety management. |
REC121-3755 | 29 - Operational Health and Safety | The RailCorp Board should require a full review of the safety competence of RailCorp managers to ensure that each has the ability to bring about those safety reforms recommended in this report which are applicable to his or her position. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3739 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must be fitted with external emergency door releases which do not require any special key or other equipment to operate. |
REC121-3761 | 32 - Doctrine, standards, and reform | Legislative changes should be enacted to ensure the complete independence of ITSRR from the Minister for Transport Services. |
REC121-3660 | 32 - Doctrine, standards, and reform | The rail displan should include the use by all emergency response personnel of a uniform incident command system, involving procedures for such matters as the establishment of inner and outer perimeters, control of access to the site, orderly evacuation of injured passengers and the establishment of a staging area remote from the accident site, in a unified command structure with the site controller co-ordinating the various emergency services through representatives of each service. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3702 | 29 - Operational Health and Safety | Random alcohol testing should be continued. |
REC121-3728 | 32 - Doctrine, standards, and reform | Any barriers to communication between OTSI and ITSRR should be removed, so as to ensure that any findings made by OTSI in relation to any investigation it conducts are reported immediately to ITSRR. |
REC121-3747 | 29 - Operational Health and Safety | All trains should have windows available through which passengers can escape. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3690 | 32 - Doctrine, standards, and reform | All communications protocols must be strictly enforced by all accredited rail organisations. |
REC121-3709 | 29 - Operational Health and Safety | RailCorp should provide access to electronic versions of safety documentation for all operational staff at their workplace. |
REC121-3733 | 29 - Operational Health and Safety | RailCorp’s approach to occupational health and safety should be proactive and involve the systematic analysis of all current hazards, risks and controls and an assessment of their adequacy to reduce the risk of injury to, or death of, employees to an acceptable level. |
REC121-3754 | 29 - Operational Health and Safety | The RailCorp Board should ensure that RailCorp has an adequate and integrated safety management system, including adequate systems for risk assessment, clearly defined safety responsibilities and accountabilities for persons holding management positions, and specific performance criteria against which evaluations can be made of safety performance and accountability for safety performance of all managers. |
REC121-3772 | 32 - Doctrine, standards, and reform | RailCorp should establish a safety management system containing the 29 elements identified in the SMSEP report which is in volume 2 of this report. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3696 | 32 - Doctrine, standards, and reform | Defects reporting, recording and rectification should be integrated with the RailCorp regimes for train maintenance. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3738 | 29 - Operational Health and Safety | All passenger trains must be fitted with an internal passenger emergency door release. |
REC121-3760 | 32 - Doctrine, standards, and reform | The Advisory Board established under the Transport Legislation Amendment (Safety and Reliability) Act 2003 must be abolished. |
REC121-3659 | 32 - Doctrine, standards, and reform | A railway disaster plan, or rail displan, should be developed by RailCorp and the emergency services to ensure co-ordinated inter-agency response to rail accidents and incidents on the RailCorp network. |
REC121-3682 | 29 - Operational Health and Safety | All new rolling stock should be designed to be compatible with at least level 2 automatic train protection discussed in chapter 7 of this report. |
REC121-3701 | 32 - Doctrine, standards, and reform | Train inspections should be carried out at the time of stabling RailCorp trains, as well as a part of train preparation prior to entering service. |
REC121-3727 | 32 - Doctrine, standards, and reform | The relevant legislation should be amended to provide expressly that OTSI and the Chief Investigator have the power to initiate a rail accident or incident investigation. |
REC121-3743 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must have the external emergency door release clearly marked with the words “Emergency Door Release”. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3688 | 32 - Doctrine, standards, and reform | Communications procedures must be standardised throughout the rail network, so that all railway employees describe the same subject matter in an identical way. |
REC121-3707 | 29 - Operational Health and Safety | The safety document management system should provide for the distribution of electronic versions of safety documentation to relevant staff. |
REC121-3732 | 29 - Operational Health and Safety | If ITSRR accepts such a plan as an appropriate response to the existing weak safety culture, ITSRR should approve it and monitor the effectiveness of the plan. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3771 | 32 - Doctrine, standards, and reform | RailCorp should establish an integrated safety management system which includes the following: |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
REC121-3674 | 32 - Doctrine, standards, and reform | Uniform verbal descriptions identifying that power has been isolated should be developed by RailCorp and utilised by all railway personnel, electrical service providers and all emergency response personnel. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3737 | 29 - Operational Health and Safety | There must be a minimum of two independent methods of self-initiated emergency escape for passengers from all trains at all times. |
REC121-3759 | 29 - Operational Health and Safety | A Safety Reform Program Director (hereafter referred to as SRPD), reporting directly to the Chief Executive of RailCorp, should be retained to manage, as head of a Safety Reform Program Office, any safety reform program being undertaken by RailCorp. The SRPD should work with the Chief Executive and senior management to ensure the implementation of an integrated safety management system and the cultural change required. The SRPD must have qualifications suitable for recognition by the Australian Institute of Project Management as a master program director. He or she should report to and be under the control of the Chief Executive, to ensure that the accountability of the Chief Executive is not reduced. The SRPD should co-ordinate and integrate any existing rail safety reform programs and, in consultation with and with the authority of the Chief Executive he or she should: |
REC121-3655 | 32 - Doctrine, standards, and reform | Procedures should be put in place by RailCorp to ensure that electrical power supply to the area of an accident can be immediately isolated, if necessary, in the event of a rail accident, so as to reduce any risk of exposure of emergency response personnel to injury or harm. |
REC121-3681 | 29 - Operational Health and Safety | RailCorp should progressively implement, within a reasonable time, level 2 automatic train protection with the features identified in chapter 8 of this report. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3764 | 29 - Operational Health and Safety | The ITSRR should not grant accreditation to any rail organisation unless it has an integrated safety management system in accordance with any safety management system regulation and the guidelines published from time to time by ITSRR. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3686 | 32 - Doctrine, standards, and reform | The standard in relation to the collection and use of data from data loggers should provide that such information must be accessed in the circumstances of any accident or incident and can be accessed to monitor driver performance generally. |
REC121-3706 | 29 - Operational Health and Safety | RailCorp should establish a comprehensive safety document management system. |
REC121-3731 | 29 - Operational Health and Safety | RailCorp should develop a plan to be submitted to ITSRR to address the deficiencies in the safety culture of RailCorp, including: |
REC121-3750 | 32 - Doctrine, standards, and reform | ITSRR should initiate and/or participate in the development of a national standard for crashworthiness of all passenger trains. |
REC121-3770 | 32 - Doctrine, standards, and reform | A safety management system regulation should be promulgated, specifying the requirements of safety management systems in all accredited organisations, using Annexure I to this report as a guide |