Rec-ID | Code | Recommendation |
---|---|---|
REC002-4007 | 40 - Equipment and consumables | A measure of safety may be found in the use of high explosives combined with wet tamping, or, still better, water cartridges, instead of powder under any of its modifications. Encouragement ought also to be given to the use of patent multiple wedges and applicances of a like nature, for supplanting the use of explosives. Under all circumstances and conditions some provision should be adopted for compelling workmen to thoroughly undercut, shear, or nick, and generally to work the coal as directed by the Manager. |
REC002-4005 | 40 - Equipment and consumables | Where safety-lamps are used the lock should be of such a character as to prevent any workman opening it. If the "Protector" type of lamp be employed the necessity for a lock is the less necessary, as the unscrewing of this type of lamp extinguishes the light. |
REC002-4004 | 35 - Business and Industry in relation to industry | Where safety-lamps are used, and the obligation is laid upon the men to cleanse the same, all examinations, tests, and repairs to these should be done by the owners. |
REC002-4011 | 32 - Doctrine, standards, and reform | The Commission feel that the 4th clause in the present Act, relating to the spacing of cut-throughs, should be amended to admit of any convenient or safe system of mining being pursued. This is a matter of detail that would be better out of the Act. The Commission would advise that the word should not occur at all, and that, if bratticing be used, or the air by some other satisfactory device be conveyed to the face, scope would be given to Managers to introduce systems of mining adapted to the circumstance of each particular coal-seam, with advantage to all concerned. |
REC002-4003 | 35 - Business and Industry in relation to industry | Where gas exists, and no provisions are made for its constant removal, no shots should be fired, and, where permitted in a gassy mine, shots should be fired only by a man specially appointed, and at such hours when the miners are not within the mine. All shots should be tamped by stone well damped, and only copper or wooden tools should be employed. As far as possible the use of explosives should be discouraged, and skilful mining encouraged. Danger-boards should be placed further from the faces whence gas issues (say), where practicable, 50 yards. |
REC002-4010 | 35 - Business and Industry in relation to industry | The Commission do not approve of removing any responsibility from the management by increasing the power or number of the Inspectors. The visits of these officials should, so far as possible, be visits of surprise. |
REC002-4001 | 35 - Business and Industry in relation to industry | The Commission consider that in all mines where gas exists the course of the air should be directed to sweep along the working-faces; in mines worked by Pillar and Stall, bratticing must be resorted to to carry the gas from the face as it issues, and so prevent any accumulation of explosive gases or of gases inimical to life. In cases where gas exists it would be better that no bords should be broken off the back or return heading or supplied with air fouled by dangerous gases. The panel system of working by confining and localising districts, or some modification thereof, might be pursued with advantage. |
REC002-4008 | 35 - Business and Industry in relation to industry | Where dust exists in quantity, and under conditions favourable for ignition, it should be periodically and sufficiently dampened by water |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1287 | 32 - Doctrine, standards, and reform | That the glossary of terms in the State Emergency Management Plan be reviewed to ensure all relevant language is included. All agencies need to ensure the use of clear communication and accurate use of terminology, including in describing the status of critical services e.g. Triple Zero (000), SA Government Radio Network, electrical and water supplies and infrastructure. |
REC295-1301 | 32 - Doctrine, standards, and reform | Establish an ‘Interstate Deployment Support Plan’ for incoming interstate resources. The plan should outline responsibilities and arrangements for this function. Consider including this plan into the State emergency management arrangements. |
REC295-1277 | 32 - Doctrine, standards, and reform | That the Department of Planning, Transport and Infrastructure review their Business Continuity Plan to: |
REC295-1323 | 32 - Doctrine, standards, and reform | Review and update the role, function, workload and focus of the groups/committees that contribute to incident management and emergency management capabilities including the State Emergency Management Training Committee, Interagency Incident Management Sub-Committee and the Central Exercise Writing Team. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1333 | 32 - Doctrine, standards, and reform | Develop a State Relief and Recovery Plan as a distinct part of the State Emergency Management Plan which should include: a) potential locations for suitable facilities for relief and recovery centres which: are in locations safe from hazards such as flooding and bushfire; and, have appropriate access and suitable ablutions. b) formalisation of roles and capabilities of non-government organisations such as Red Cross |
REC295-1295 | 32 - Doctrine, standards, and reform | That resources be provided to support the implementation of recommendations in the South Australian Levee Bank Management Issues Paper (DEWNR, 2015) including: a) development of relevant policy; and b) identification of responsibilities in relation to levee management and flood mitigation |
REC295-1274 | 35 - Business and Industry in relation to industry | That relevant agencies, such as the Department of State Development, SA Police and emergency services, collaborate to establish an education campaign to encourage businesses in South Australia to develop Business Continuity Plans which, among other potential hazards such as flood and fire, also take into account the potential impact of an extended power outage. |
REC295-1314 | 32 - Doctrine, standards, and reform | That an Emergency Management Assurance Framework be established as soon as possible to support the emergency management arrangements and the State Emergency Management Plan. Consider establishing an Inspector General Emergency Management department or position. |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1332 | 32 - Doctrine, standards, and reform | Develop a Disaster Waste Management Plan to form part of the State Emergency Management Plan which describe participating agencies and responsibilities for various aspects of waste management during and after emergencies. |
REC295-1292 | 32 - Doctrine, standards, and reform | That, giving consideration to the previous recommendation, the Flood |
REC295-1311 | 32 - Doctrine, standards, and reform | That the State Emergency Management Plan be reviewed and updated including: a) a better description of the responsibilities of Hazard Leaders Page xx b) establish a mechanism for a hazard leader to identify systemic failures in coordination of their hazard, with a clear process to raise those issues with SEMC and seek a remedy c) establish resilience as a key heading in the plan, with clearly documented strategies and responsibilities; and d) consider the Schar/Mulroney submission and taking a ‘fresh eyes’ approach |
REC295-1282 | 32 - Doctrine, standards, and reform | That the Office for Digital Government, in close partnership with telecommunications companies (e.g. Telstra, Optus, Vodaphone), develop a Control Agency Plan for Information and Communication Technology including mobile communications. The plan should consider: |
REC295-1331 | 32 - Doctrine, standards, and reform | Task South Australian Fire and Emergency Services Commission with further developing the Emergency Alerts capability across government agencies including to: a) establish and maintain a centralised training program for emergency alert initial and refresher training. b) establish a pool of endorsed Emergency Alert personnel from across government agencies to enable control agencies to assist each other with the emergency alert function during emergencies. c) develop supporting processes to ensure that the capability supports: emergencies involving any hazard; consistent issuing of alerts and warnings; consistent messages; and effective communication and notification of alerts issued to relevant internal and external stakeholders |
REC295-1290 | 32 - Doctrine, standards, and reform | Continue development of the Damage Assessment Support Plan to: |
REC295-1310 | 32 - Doctrine, standards, and reform | That additional guidance be provided in the State Emergency Management Plan regarding the activation, structure and operation of Zone Emergency Support Teams. This should include: a) the reporting relationship between the Zone Emergency Support Teams, the State Emergency Centre and the State Coordinator b) briefing requirements between the State Coordinator (or their representative) and the Zone Emergency Support Teams when the State Emergency Centre is activated c) responsibilities for provision of local public information; and d) the appointment of public information officers in Zone Emergency Support Teams (where there is no incident management team (established) to provide information to local communities |
REC295-1281 | 32 - Doctrine, standards, and reform | In order to increase resilience and public safety during emergencies, the State Emergency Management Committee should request the Australia and New Zealand Emergency Management Committee to place on the agenda, and consider establishing a national position, on redundancies for mobile communications (including phone tower back-up power) and the National Broadband Network. |
REC295-1330 | 32 - Doctrine, standards, and reform | Update the Public Information Functional Support Group Plan to include: a) standards, outputs, systems and processes required to be used by control agencies and the Public Information Functional Support Group during emergencies b) guidance on the public information cycle through the prevention, preparedness, response and recovery phases which includes the responsibilities and information requirements during different phases, and effective transition between phases c) establishing a public information intelligence cell within the Public Information Functional Service Group; and d) identifying tools or resources to monitor social media |
REC295-1289 | 32 - Doctrine, standards, and reform | That SA Police, emergency services, health facilities, utility providers and other key service providers, review their Business Continuity Plans giving consideration to factors such as: a) identification of: business critical needs; essential services power requirements; back-up power requirements for all facilities including State, regional and local facilities such as Police, SES, MFS and CFS stations; the need for any arrangements for back-up power to be included in contracts for design and or lease of Government premises b) contingencies for black system events and extended power outages c) regular back-up generator testing regime protocols, including testing under load and for long durations d) contingencies for communications when mobile, landline and/or radios are not operational e.g. satellite phones; and e) alternative State control centre facilities that are pre-identified, equipped and have procedures for moving to the alternative facility. |
REC295-1309 | 32 - Doctrine, standards, and reform | That members of Emergency Management Council ensure they are prepared to undertake their roles and responsibilities during emergency events, including establishing: a) contingencies for communication e.g. satellite phone b) access to relevant documents such as the State Emergency Management Plan, supporting plans, ministerial guidelines, agency plans and contacts in hard copy and/or portable device c) formalised arrangements for briefings (up and down), and d) arrangements for suitable representation e.g. relevant Chief Executive(s) or their deputy, at all Emergency Management Council meetings . |
REC295-1280 | 32 - Doctrine, standards, and reform | That a State Plan be developed for managing the consequences of a black system event or other major power outage. The plan should include: |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1417 | 32 - Doctrine, standards, and reform | That the following disaster management doctrine are reviewed and reissued to ensure consistency and improved guidance to local government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1157 | 35 - Business and Industry in relation to industry | Improvements to the Targeting of Government Support to Build Primary Industry Resilience |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2535 | 32 - Doctrine, standards, and reform | Airservices Australia, in conjunction with the Department of Infrastructure and Regional Development and the Civil Aviation Safety Authority, reconsiders the policy on ‘Assessment of Priorities’ that stipulates that air traffic controllers sequence arriving aircraft based on category of operation, rather than on the accepted international practice of ‘first come, first served’. |
REC258-2554 | 32 - Doctrine, standards, and reform | Recreational Aviation Administration Organisations, in coordination with the Civil Aviation Safety Authority, develop mechanisms to ensure all aircraft to be regulated under CASR Part 149 are registered. |
REC258-2533 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority: |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2531 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority’s Board exercises full governance control. The nonexecutive directors should possess a range of appropriate skills and backgrounds in aviation, safety, management, risk, regulation, governance and government. |
REC258-2538 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development and Department of Defence (and appropriate agencies) establish an agreed policy position on safety oversight of civil operations into joint user and military airports. |
REC258-2529 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority utilise the provision in their bilateral Memorandum of Understanding to accredit CASA observers to ATSB investigations. |
REC258-2537 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority delegates responsibility for the day-to-day operational management of airspace to Airservices Australia, including the designation of air routes, short term designations of temporary Restricted Areas, and temporary changes to the classification of airspace for operational reasons. |
REC258-2562 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority amends the current Terms of Reference of the Industry Complaints Commissioner so that: |
REC258-2527 | 32 - Doctrine, standards, and reform | The Department of Infrastructure and Regional Development plays a stronger policy role in the State Safety Program. |
REC258-2536 | 32 - Doctrine, standards, and reform | The Australian Transport Safety Bureau and the Civil Aviation Safety Authority amend the wording of their existing Memorandum of Understanding to make it more definitive about interaction, coordination, and cooperation. |
REC258-2555 | 32 - Doctrine, standards, and reform | The Civil Aviation Safety Authority changes the current two-tier regulatory framework (act and regulations) to a three-tier structure (act, regulations and standards), with: |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2789 | 32 - Doctrine, standards, and reform | The committee recommends that the Transport Safety Investigation Act 2003 be amended to require that the Chief Commissioner of the ATSB be able to demonstrate extensive aviation safety expertise and experience as a prerequisite for the selection process. |
REC236-2803 | 32 - Doctrine, standards, and reform | The committee recommends that the government consider setting a time limit for agencies to implement or reject recommendations, beyond which ministerial oversight is required where the agencies concerned must report to the minister why the recommendation has not been implemented or that, with ministerial approval, it has been formally rejected. |
REC236-2786 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB be required to document investigative avenues that were explored and then discarded, providing detailed explanations as to why. |
REC236-2802 | 32 - Doctrine, standards, and reform | The committee recommends that where the consideration and implementation of an ATSB recommendation may be protracted, the requirement for regular updates (for example 6 monthly) should be included in the TSI Act. |
REC236-2785 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB move away from its current approach of forecasting the probability of future events and focus on the analysis of factors which allowed the accident under investigation to occur. This would enable the industry to identify, assess and implement lessons relevant to their own operations. |
REC236-2798 | 32 - Doctrine, standards, and reform | The committee recommends that, where relevant, the ATSB include thorough human factors analysis and discussion in future investigation reports. Where human factors are not considered relevant, the ATSB should include a statement explaining why. |
REC236-2784 | 32 - Doctrine, standards, and reform | The committee recommends that the minister, in issuing a new Statement of Expectations to the ATSB, valid from 1 July 2013, make it clear that safety in aviation operations involving passengers (fare paying or those with no control over the flight they are on, e.g. air ambulance) is to be accorded equal priority irrespective of flight classification. |
REC236-2796 | 32 - Doctrine, standards, and reform | The committee recommends that the ATSB-CASA Memorandum of Understanding be re-drafted to remove any ambiguity in relation to information that should be shared between the agencies in relation to aviation accident investigations, to require CASA to: |
REC236-2807 | 32 - Doctrine, standards, and reform | The committee recommends that the Aeronautical Information Package (AIP) En Route Supplement Australia (ERSA) is updated to reflect the need for caution with regard to Norfolk Island forecasts where the actual conditions can change rapidly and vary from forecasts. |
REC236-2794 | 32 - Doctrine, standards, and reform | The committee recommends that CASA, in consultation with an Emergency Medical Services industry representative group (eg. Royal Flying Doctor Service, air ambulance operators, rotary wing rescue providers) consider the merit, form and standards of a new category of operations for Emergency Medical Services. The minister should require CASA to approve the industry plan unless there is a clear safety case not to. Scope for industry to assist as part of an audit team should also be investigated where standardisation is an issue. This should be completed within 12 months and the outcome reported publicly. |
REC236-2804 | 32 - Doctrine, standards, and reform | The committee recommends that Airservices Australia discuss the safety case for providing a hazard alert service with Fijian and New Zealand ATC (and any other relevant jurisdictions) and encourage them to adopt this practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2855 | 32 - Doctrine, standards, and reform | I recommend that arrangements be put in place which would remove the requirements for Masters of Volunteer Marine Rescue vessels to hold a commercial certificate of competency. Operators could then be qualified through the FESA Volunteer Marine Rescue Training pathway as skippers and crew. This would increase the number of available skippers in the event of a search and rescue incident and would make appropriate training easier to arrange. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0528 | 32 - Doctrine, standards, and reform | That, as part of the Pollution Incident Management Response Plan to be developed for Orica’s Kooragang Island site, or by another appropriate mechanism, the Office of Environment and Heritage ensure that Orica’s incident-response procedures address the need to consider all relevant factors when assessing potential impacts, including the height and force of emissions as well as the location of any onsite fallout and whether there are off-site impacts following all serious incidents. |
REC208-0527 | 35 - Business and Industry in relation to industry | That the Office of Environment and Heritage require Orica to engage and fund appropriate independent experts to oversee any modifications to the plant in the next major maintenance overhaul of the plant in 2016 and in any upgrades to the plant prior to that date. |
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
REC208-0530 | 32 - Doctrine, standards, and reform | That, if necessary, regulation be amended to require Health to approve any script used by any party concerned, for door knocking or other information dissemination, if Health is not the first source of information to affected residents. |
REC208-0529 | 32 - Doctrine, standards, and reform | That, when developing requirements concerning pollution incident response management plans pursuant to the recent legislative amendments, the Office of Environment and Hertiage include appropriate definitions as to the meaning of ‘immediately’, and when ‘material harm to the environment is caused or threatened’. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2914 | 32 - Doctrine, standards, and reform | The review team recommend that: |
REC189-2909 | 32 - Doctrine, standards, and reform | Equipping the regulator with a wider range of compliance tools under the legislation should continue to be a policy priority. The aim should be to enhance the regulator’s capacity to secure compliance in an appropriately graduated way. The opportunity should be taken to ensure that the regulator and inspectors can, in appropriate cases, bring proceedings that do not require referral to the Commonwealth Director of Public Prosecutions, such as actions for civil penalties or injunctions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3441 | 32 - Doctrine, standards, and reform | That, where practical, risk assessments, emergency planning, training and exercising are integrated to minimise duplication of effort. |
REC158-3424 | 32 - Doctrine, standards, and reform | That legislation is prepared by the Department of Transport to ensure marine emergency management arrangements are clarified and provide: |
REC158-3435 | 32 - Doctrine, standards, and reform | That Harbour Masters have the appropriate powers, authority, accountability, skills, responsibility and indemnity to provide a coordinated response of marine resources in support of emergency services, except where the nominated marine safety authority is the control agency for a marine pollution or marine casualty emergency. |
REC158-3440 | 32 - Doctrine, standards, and reform | That the Water Division Emergency Response Plan is amended, by the Water Division emergency response coordinator, to provide a framework to coordinate a marine response that crosses declared port water boundaries and requires resource coordination and prioritisation. |
REC158-3434 | 32 - Doctrine, standards, and reform | That the accountability relationship between Harbour Masters and the Director of Marine Safety is strengthened in the relevant legislation. |
REC158-3439 | 32 - Doctrine, standards, and reform | That the port marine emergency management arrangements are integrated with the Victorian Water Division Emergency Response Plan. |
REC158-3427 | 32 - Doctrine, standards, and reform | That the standards and guidelines determined by the nominated marine safety authority require port/channel managers to conduct a marine emergency risk assessment using AS/NZ 4360:2004 Risk Management and, in addition, must require port/channel managers to: |
REC158-3438 | 32 - Doctrine, standards, and reform | That the port/channel managers coordinate marine emergency management planning in the port and are required to ensure that individual port stakeholder marine emergency management arrangements plans are integrated with the whole of port marine emergency management arrangements. |
REC158-3426 | 32 - Doctrine, standards, and reform | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner, senior emergency services personnel and relevant port stakeholders, is responsible for establishing appropriate performance standards, risk management guidelines and good practice guidelines for marine emergency management. |
REC158-3437 | 32 - Doctrine, standards, and reform | That port/channel managers coordinate marine emergency planning for the port and are required to ensure that marine emergency arrangements are integrated with whole of port emergency management plans. |
REC158-3453 | 32 - Doctrine, standards, and reform | That, where applicable, consideration is given to legislative amendment that will enable the findings of this report to be applied to areas inside State waters but outside commercial port waters. |
REC158-3425 | 32 - Doctrine, standards, and reform | Consequential or complementary amendments to the Emergency Management Act are required to ensure that: |
REC158-3436 | 32 - Doctrine, standards, and reform | That Harbour Masters are the designated principle marine specialists within the port and work directly with emergency services to provide advice and the interface with the marine legislative powers, to manage a marine emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3134 | 32 - Doctrine, standards, and reform | Improved and agreed guidelines for Safety Case application and assessment, including suggested structure and content, would alleviate many current problems related to Safety Case processes. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3141 | 32 - Doctrine, standards, and reform | NOPSA should complete the next revision of Safety Case guidelines in consultation and agreement with stakeholders and continue its program to achieve consistency with a firmer hand from the CEO and management. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3140 | 32 - Doctrine, standards, and reform | The industry should provide advice to NOPSA on where the regulations do not provide sufficient clarity and consider developing broad policy/process guidelines in consultation with the regulator to provide clarity and consistency. Regulators should not take personal views or preferences. |
REC149-3130 | 32 - Doctrine, standards, and reform | The regulations pertaining to vessels of opportunity or their interpretation should be changed to facilitate a risk based approach to regulation. This approach will be consistent with the approach taken in other jurisdictions. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3129 | 32 - Doctrine, standards, and reform | The consequences of the disapplication of the Navigation Act 1912 should be analysed, the actual consequences identified and unintended consequences addressed. |
Rec-ID | Code | Recommendation |
---|---|---|
REC137-3531 | 32 - Doctrine, standards, and reform | I recommend that CASA consider creating firm guidelines that require consideration of workload, lines of authority, potential conflicts of interest and any other factors that impact upon the ability of “key personnel” to discharge their responsibilities within an aviation organisation when its officers are approving appointments to those positions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3674 | 32 - Doctrine, standards, and reform | Uniform verbal descriptions identifying that power has been isolated should be developed by RailCorp and utilised by all railway personnel, electrical service providers and all emergency response personnel. |
REC121-3705 | 32 - Doctrine, standards, and reform | The ITSRR should develop standards for periodic medical examinations which include the following: |
REC121-3659 | 32 - Doctrine, standards, and reform | A railway disaster plan, or rail displan, should be developed by RailCorp and the emergency services to ensure co-ordinated inter-agency response to rail accidents and incidents on the RailCorp network. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3736 | 32 - Doctrine, standards, and reform | The RailCorp passenger containment policy must be abandoned. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3692 | 32 - Doctrine, standards, and reform | Communications protocols and procedures should be standardised and mandated by regulations making them a condition of accreditation. |
REC121-3763 | 32 - Doctrine, standards, and reform | The ITSRR should publish guidelines to be followed by accredited organisations. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3701 | 32 - Doctrine, standards, and reform | Train inspections should be carried out at the time of stabling RailCorp trains, as well as a part of train preparation prior to entering service. |
REC121-3773 | 32 - Doctrine, standards, and reform | The ITSRR should ensure that RailCorp establishes a safety management system containing the 29 elements identified in the SMSEP report, and ensure the ongoing monitoring and improvement of the safety management system established. |
REC121-3655 | 32 - Doctrine, standards, and reform | Procedures should be put in place by RailCorp to ensure that electrical power supply to the area of an accident can be immediately isolated, if necessary, in the event of a rail accident, so as to reduce any risk of exposure of emergency response personnel to injury or harm. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3730 | 32 - Doctrine, standards, and reform | Legislation should be enacted and any necessary arrangements made, to enable the ATSB to review any reports of any investigation by a rail organisation or the OTSI into any serious incident or accident in New South Wales. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3690 | 32 - Doctrine, standards, and reform | All communications protocols must be strictly enforced by all accredited rail organisations. |
REC121-3762 | 32 - Doctrine, standards, and reform | The Chief Executive of ITSRR should have sole accountability and responsibility for the regulation of rail safety in New South Wales. |
REC121-3671 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include a requirement for the debriefing of all senior rail and emergency response personnel involved in any rail accident, so as to determine the way or ways in which emergency response arrangements for rail accidents can be continually improved, and thereafter implement such improvements. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3772 | 32 - Doctrine, standards, and reform | RailCorp should establish a safety management system containing the 29 elements identified in the SMSEP report which is in volume 2 of this report. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3679 | 32 - Doctrine, standards, and reform | The rail safety regulator should set standards for the design, manufacture, testing and commissioning of rolling stock to ensure that the rolling stock is fit for its purpose. |
REC121-3728 | 32 - Doctrine, standards, and reform | Any barriers to communication between OTSI and ITSRR should be removed, so as to ensure that any findings made by OTSI in relation to any investigation it conducts are reported immediately to ITSRR. |
REC121-3662 | 32 - Doctrine, standards, and reform | The rail displan should provide for the site controller to have complete control of the site, with other agencies co-ordinating with and supporting him or her, until the rescue phase of the emergency response has been completed. |
REC121-3688 | 32 - Doctrine, standards, and reform | Communications procedures must be standardised throughout the rail network, so that all railway employees describe the same subject matter in an identical way. |
REC121-3761 | 32 - Doctrine, standards, and reform | Legislative changes should be enacted to ensure the complete independence of ITSRR from the Minister for Transport Services. |
REC121-3668 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include action checklists of the steps that each employee is required to take, and the order for specific employees to follow in case of emergency. |
REC121-3699 | 32 - Doctrine, standards, and reform | All reported train defects should be certified by a person in a supervisory position in RailCorp as having been rectified. |
REC121-3771 | 32 - Doctrine, standards, and reform | RailCorp should establish an integrated safety management system which includes the following: |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3727 | 32 - Doctrine, standards, and reform | The relevant legislation should be amended to provide expressly that OTSI and the Chief Investigator have the power to initiate a rail accident or incident investigation. |
REC121-3661 | 32 - Doctrine, standards, and reform | The rail displan should include provision for the appointment of a rail emergency management co-ordinator at the RMC, and an on-site rail commander with the sole function of assisting and supporting the emergency services during the rescue phase of the emergency response. |
REC121-3686 | 32 - Doctrine, standards, and reform | The standard in relation to the collection and use of data from data loggers should provide that such information must be accessed in the circumstances of any accident or incident and can be accessed to monitor driver performance generally. |
REC121-3760 | 32 - Doctrine, standards, and reform | The Advisory Board established under the Transport Legislation Amendment (Safety and Reliability) Act 2003 must be abolished. |
REC121-3667 | 32 - Doctrine, standards, and reform | RailCorp should develop and implement an emergency response plan for management of all rail accidents. Such a plan should be subsumed by the rail displan in the case of serious accidents or incidents. |
REC121-3698 | 32 - Doctrine, standards, and reform | No RailCorp train should enter into revenue service or remain in service if, in the opinion of the driver in charge of that train, any defect in it creates a risk of injury. |
REC121-3770 | 32 - Doctrine, standards, and reform | A safety management system regulation should be promulgated, specifying the requirements of safety management systems in all accredited organisations, using Annexure I to this report as a guide |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3660 | 32 - Doctrine, standards, and reform | The rail displan should include the use by all emergency response personnel of a uniform incident command system, involving procedures for such matters as the establishment of inner and outer perimeters, control of access to the site, orderly evacuation of injured passengers and the establishment of a staging area remote from the accident site, in a unified command structure with the site controller co-ordinating the various emergency services through representatives of each service. |
REC121-3685 | 32 - Doctrine, standards, and reform | The ITSRR should impose a standard in relation to the collection and use of data from data loggers. |
REC121-3750 | 32 - Doctrine, standards, and reform | ITSRR should initiate and/or participate in the development of a national standard for crashworthiness of all passenger trains. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3696 | 32 - Doctrine, standards, and reform | Defects reporting, recording and rectification should be integrated with the RailCorp regimes for train maintenance. |
REC121-3769 | 32 - Doctrine, standards, and reform | The ITSRR should continue to participate in the development of a national system for rail safety regulation, provided that any ultimate agreement between the States and Territories and the Australian Government does not produce a safety outcome for New South Wales that is less than would be achieved by the implementation of all the recommendations contained in this report. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3988 | 40 - Equipment and consumables | The Commission recommends that buckets of sand or other apparatus for extinguishing fire be kept in any chamber where high powered electricity is used. |
REC008-3991 | 32 - Doctrine, standards, and reform | The Commission recommends that the provisios of section 185 of the "Mining Act 1905" relating to exits from coal mines be extended to metalliferous mines employing more than 20 men in any one shift. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-4000 | 32 - Doctrine, standards, and reform | That section 22 of the Police Offences Act 1890 be amended, to enable the burning of grass and debris along the railway lines in the summer season to be carried out at an earlier hour than two o'clock in the afternoon, when, in the judgement of the railway inspectors, it is safe and necessary to do so. |
REC004-3997 | 40 - Equipment and consumables | That suitable metal receptacles be fitted under the spittoons of all smoking compartments of country trains, to receive pipe ashes, lighted tobacco, cigars, cigarettes, matches, or other inflammable matter used by smokers. |
REC004-3995 | 32 - Doctrine, standards, and reform | That the standard double arrester, fitted to the locomotives during the summer months, be subjected to more careful daily inspection before and after each journey during such months, in addition to the present periodical examination by the locomotive foreman and boiler inspector; and that any omission of this duty on the part of the running staff be severely punished. |
REC004-3993 | 32 - Doctrine, standards, and reform | That in any case where there is primá facie evidence of a fire, creating damage to the extent of $100 or upwards in value, having been caused by the escape of particles of lighted matter from a locomotive engine, or by the action of railway employes in burning off grass or other inflammable material along any line of railway, a Special Board of Inquiry shall investigate and report on the subject, such Board to consist of a Police Magistrate as Chairman, with a railway officer and a competent person chosen from outside the State service as members. |