REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC292-2370 | 25 - Inquiry, audit, lessons management and after action review | I recommend that the New South Wales Police Force undertake a formal assessment of alternatives to the TOU’s current soft-point ammunition to determine whether a more appropriate form of ammunition is reasonably available. |
REC292-2369 | 26 - Research | I recommend that the New South Wales Police Force evaluate whether the use of noise-attenuation devices should be mandated when explosive distraction devices are used. |
REC292-2348 | 17 - Assets and technology | I recommend that if it has not already done so, the New South Wales Police Force acquires the audio surveillance technology that in similar circumstances would allow a device to be monitored in the Police Forward Command Post and/or the Police Operations Centre and that the organisation ensures that its capacity in this regard keeps pace with technological advances in the area. |
REC292-2342 | 13 - Mapping and data quality | The development of an integrated intelligence system that allows police officers secure access to all information platforms should also provide for the recording of all command decisions, the reasons for them, and the dissemination of those decisions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3725 | 13 - Mapping and data quality | The data and information management system should be compatible with any data and information management system established by the ATSB for the designated interstate rail network, provided that the establishment of a compatible system does not reduce the amount or quality of the information obtained by ITSRR below the optimum levels which it needs to conduct trend analysis, and otherwise properly manage the safety of rail operations in New South Wales. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3724 | 13 - Mapping and data quality | The ITSRR should establish a data and information management system, containing all data and information that it requires, to continually monitor the safety of the New South Wales rail system. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |