Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2858 | 13 - Mapping and data quality | I recommend that the Commonwealth prioritise completion of a hydrographic survey of Christmas Island and ensure that such a survey is completed in the near future. |
REC227-2857 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth ensure that there is a mooring buoy which will enable the mooring of SIEVs to take place and free up the Christmas Island response vessel for ongoing surveillance duties. |
REC227-2853 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth liaise closely with representatives of the Christmas Island VMRS prior to purchasing or replacing any vessels for the VMRS in the future. |
REC227-2852 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth and the Shire of Christmas Island take steps to ensure that the Ethel Beach boat ramp is significantly upgraded, that it should be provided with shelter in the form of a rock groyne or similar buffer and that provision should be made so that a person can walk beside the ramp on a stable footing; or If this is not considered likely to be effective in providing an appropriate means of deploying a rescue vessel in adverse conditions, such other action be taken as is necessary to ensure that there is a means of deploying a rescue vessel in adverse conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
REC210-0681 | 19 - Offences | Councils and distributor-retailers should agree to protocols for the exchange of information about suspected illegal connections, the steps being taken to investigate them or the basis for concluding that no investigation is required, and the results of any investigations or enforcement actions. |
REC210-0696 | 21 - Role of Commonwealth Government | Carriers, councils and the Australian Communications and Media Authority should take into account the risk of flooding when considering the placement of telecommunications facilities. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0665 | 13 - Mapping and data quality | Councils should make their flood and overland flow maps and models available to applicants for development approvals, and to consultants engaged by applicants. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0755 | 13 - Mapping and data quality | CS Energy should supplement physical monitoring of Splityard Creek Dam with visual monitoring by installing surveillance cameras or similar devices. |
REC210-0664 | 13 - Mapping and data quality | Councils should, resources allowing, maintain flood maps and overland flow path maps for use in development assessment. For urban areas these maps should be based on hydraulic modelling; the model should be designed to allow it to be easily updated as new information (such as information about further development) becomes available. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0746 | 13 - Mapping and data quality | Seqwater should consider engaging a technical writer to develop completely new manuals after the operational strategies for Wivenhoe, Somerset and North Pine dams are set by the Queensland Government. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
REC210-0683 | 13 - Mapping and data quality | All councils should, resources allowing, map the overland flow paths of their urban areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC137-3533 | 21 - Role of Commonwealth Government | Accordingly I recommend that the Federal Minister for Transport, consider engaging an external consultant to assess whether high level intervention is warranted. |
REC137-3532 | 16 - Training and behaviour | I recommend that CASA reconsider the introduction of measures to ensure the efficiency of training and checking organisations for air transport operations. I recommend that this include the way in which particular training needs of an air operator’s flight crew are to be identified (including recurrent training and CRM training) and how those needs are to be met by approved or certified training and checking organisations. |
REC137-3530 | 16 - Training and behaviour | I recommend that Civil Aviation Safety Authority (CASA) expedite the introduction of mandatory crew resource management training. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4144 | 16 - Training and behaviour | No opportunity be lost of encouraging the formation of bush fire brigades and the maintenance of enthusiasm and that the Bush Fires Board assist the brigades in any way possible to obtain adequate training and equipment. |
REC019-4139 | 19 - Offences | Local authorities prosecute in all cases of deliberate breaches of the provisions of the Bush Fires Act and thay failing this the Bush Fires Board take appropriate action to initiate such prosecutions. |
REC019-4158 | 16 - Training and behaviour | That needs in the direction of a fire emergency service be met as far as practicable by the Bush Fires Board in its training programme and in the tactical organisation of existing brigades for use as reserves in districts other than their own. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |