REC126-1977 | 4 - Fire season preparation | That a program be implemented to ensure that existing fire tracks and trails are cleared and accessible at all times and that a network of additional fire trails be established so as to allow direct fire suppression operations without undue delay in the event of a wildfire |
REC126-1949 | 12 - EM agency and authority | That the Emergency Services Agency be relocated into accommodation that is purpose-built and more sited to the agency’s operations than the current facility at Curtin |
REC126-2002 | 1 - Land-use and building regs | That consideration be given when building to the positioning of outbuildings around residential structures such that their potential impact on the main structure is reduced |
REC126-1970 | 35 - Business and Industry in relation to industry | That the Emergency Services Agency reconsider and revise the arrangement that exists between the ACT Fire Brigade and Canberra airport in relation to the provision of assistance |
REC126-2011 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the recommendations of the seven reviews of the Emergency Services Bureau carried out before the McLeod inquiry and ensure implementation of any of those recommendations that remain relevant but have not been implemented |
REC126-1975 | 5 - Hazard reduction burns | That prescribed burning operations be conducted according to agreed standard burning prescriptions |
REC126-1947 | 25 - Inquiry, audit, lessons management and after action review | That the ACT Government commission a review of coroners’ jurisdiction in order to determine whether that jurisdiction ought to be limited or expanded and, if so, to what extend |
REC126-2000 | 1 - Land-use and building regs | That the ACT Government consider taking measures to implement the provisions of Australian Standard 3959, Construction of Buildings in Bushfire Prone Areas, for the ACT urban area |
REC126-1963 | 12 - EM agency and authority | That priority be given to ensuring that the ACT has an adequate resource of remote area firefighting teams consisting of personnel with high levels of fitness and training in remote fire suppression |
REC126-2010 | 25 - Inquiry, audit, lessons management and after action review | That the taskforce review the extent to which the recommendations in the McLeod report have been implemented in order to ensure implementation of those not yet implemented |
REC126-1974 | 4 - Fire season preparation | That responsibility for fuel management lie with the land management agency that controls the area and that land managers be given authority to implement prescribed fuel-reduction burns within their area |
REC126-1995 | 12 - EM agency and authority | That the Emergency Services Agency staff the Media Unit within its planning Section with profesisonal, experienced information officers skilled in dissemination of information and media management and liaison |
REC126-1952 | 25 - Inquiry, audit, lessons management and after action review | That regular periodic reviews be undertaken of changes made to the operational and management arrangements for dealing with wildfires and other emergencies in the ACT, to ensure that those arrangements continue to comply with the Australian Inter-Agency Incident Management System Incident Control System |
REC126-2008 | 34 - Local knowledge | That, if he is willing to participate, Mr John Lowe be made a member of the implementation taskforce to which I refer in recommendation 70 |
REC126-1973 | 5 - Hazard reduction burns | If it is not part of the proposed version 2 of the Strategic Bushfire Management Plan, that the plan be revised to provide for a fuel-reduction burning regime in the ‘Land Management Zone’ that is equivalent to that contemplated for the corridors designated as the ‘Landscape Division Zone’ and that the regime involve burning areas in rotation to achieve an appropriately varying fire age spectrum across the entire landscape |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1951 | 4 - Fire season preparation | That before each fire season the Emergency Services Agency, in conjunction with the Bush Fire Council – after consultation with the relevant ACT agencies, the Bureau of Meteorology, relevant NSW agencies and the community – conduct a qualitative risk analysis of the conditions and circumstances prevailing and forecast and develop strategies to ensure heightened preparedness during seasons identified as severe |
REC126-2007 | 34 - Local knowledge | That the views and concerns expressed by the ACT Sustainable Rural Lands Group be taken into account when implementing the recommendations in this report |
REC126-1972 | 5 - Hazard reduction burns | That clarification be provided and information be made public in connection with the hazard reduction proposed under the Strategic Bushfire Management Plan for the area designated ‘Land Management Zone’, which appears to cover about 70 per cent of the ACT landscape and might be excluded from fuel-reduction burning |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-2004 | 35 - Business and Industry in relation to industry | That the ACT Government and ActewAGL jointly develop and implement protocols that will create a procedure whereby each of the water and sewerage, electricity and gas distribution networks, or parts thereof, can safely and promptly be manipulated, controlled, shut off, isolated or disconnected under emergency conditions. |
REC126-1971 | 5 - Hazard reduction burns | That a hazard-reduction program be introduced, involving regular and strategic burning in all areas of the ACT – including the catchment areas – with a view to having fuel-reduced areas in a pattern across the landscape, excluding only small areas of particular ecological or conservation importance |