Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4010 | 35 - Business and Industry in relation to industry | The Commission do not approve of removing any responsibility from the management by increasing the power or number of the Inspectors. The visits of these officials should, so far as possible, be visits of surprise. |
REC002-4008 | 35 - Business and Industry in relation to industry | Where dust exists in quantity, and under conditions favourable for ignition, it should be periodically and sufficiently dampened by water |
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
REC002-4004 | 35 - Business and Industry in relation to industry | Where safety-lamps are used, and the obligation is laid upon the men to cleanse the same, all examinations, tests, and repairs to these should be done by the owners. |
REC002-4003 | 35 - Business and Industry in relation to industry | Where gas exists, and no provisions are made for its constant removal, no shots should be fired, and, where permitted in a gassy mine, shots should be fired only by a man specially appointed, and at such hours when the miners are not within the mine. All shots should be tamped by stone well damped, and only copper or wooden tools should be employed. As far as possible the use of explosives should be discouraged, and skilful mining encouraged. Danger-boards should be placed further from the faces whence gas issues (say), where practicable, 50 yards. |
REC002-4001 | 35 - Business and Industry in relation to industry | The Commission consider that in all mines where gas exists the course of the air should be directed to sweep along the working-faces; in mines worked by Pillar and Stall, bratticing must be resorted to to carry the gas from the face as it issues, and so prevent any accumulation of explosive gases or of gases inimical to life. In cases where gas exists it would be better that no bords should be broken off the back or return heading or supplied with air fouled by dangerous gases. The panel system of working by confining and localising districts, or some modification thereof, might be pursued with advantage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1472 | 11 - Evacuation and shelters | Develop flood evacuation plans for at risk communities. |
REC286-2028 | 8 - Communications and warnings | Review community information and warning systems to ensure they cater for heatwave messages |
REC286-1467 | 15 - Inter-service cooperation | Review the allocation of responsibilities for earthquake risk management. |
REC286-2027 | 8 - Communications and warnings | Develop arrangements to identify and communicate with people vulnerable to heat stress |
REC286-2078 | 15 - Inter-service cooperation | Review interagency information sharing arrangements. |
REC286-1465 | 15 - Inter-service cooperation | Improve the coordination and delivery of the National seismic monitoring program. |
REC286-2026 | 11 - Evacuation and shelters | Identify facilities that can be used as cool spaces during heatwaves and establish linkages between operators and emergency management organisations |
REC286-2074 | 8 - Communications and warnings | Continue the enhancement of forecast and warning services. |
REC286-1454 | 11 - Evacuation and shelters | Review coastal inundation evacuation and response plans. |
REC286-2014 | 15 - Inter-service cooperation | Integrate non-government entities into emergency response and recovery arrangements. |
REC286-2072 | 35 - Business and Industry in relation to industry | Relax the requirement for medical certificates in the event of an outbreak. |
REC286-1443 | 14 - Incident Mgt Teams | Build capacity to enable Incident Management Teams to manage the likely increased frequency and intensity of major fire events. |
REC286-1475 | 8 - Communications and warnings | Integrate existing capabilities into a Total Flood Warning System. |
REC286-2064 | 35 - Business and Industry in relation to industry | Encourage businesses to consider human influenza pandemics in business continuity planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2597 | 17 - Assets and technology | That the project team become independent from any of the entities involved in the Whole of Government network. |
REC245-2588 | 7 - Inter-agency communication | That Tasmania Police, Tasmania Fire Service (TFS), Ambulance Tasmania and State Emergency Services (SES) investigate ways of providing secure and confidential radio communications. |
REC245-2595 | 17 - Assets and technology | That stakeholders involved with the Whole of Government radio project re-engage positively to ensure a solution to the current impasse is achieved in the best interests of the stakeholders and the State as a whole. |
REC245-2594 | 17 - Assets and technology | That the network managers produce business cases for all major upgrades. |
REC245-2593 | 17 - Assets and technology | That network managers develop and document strategic plans for the management of their radio networks. |
REC245-2591 | 17 - Assets and technology | That until the outcome of the Whole of Government project is complete (and interoperability is achieved), emergency services should investigate and implement methods for further improving interoperability. |
REC245-2589 | 7 - Inter-agency communication | That TFS and Ambulance Tasmania work together to resolve problems around congestion, particularly during the fire season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0527 | 35 - Business and Industry in relation to industry | That the Office of Environment and Heritage require Orica to engage and fund appropriate independent experts to oversee any modifications to the plant in the next major maintenance overhaul of the plant in 2016 and in any upgrades to the plant prior to that date. |
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
REC208-0524 | 8 - Communications and warnings | That the Premier issue clear and unambiguous guidelines to all Government Ministers specifying the timing of notifications to the public of any matters that may affect public health or safety. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3007 | 15 - Inter-service cooperation | That Tasmania Fire Service implement Recommendation 5 above; and that Aurora continue to co-operate with that Service. |
REC166-3006 | 20 - Role of police | That the recommendations contained in the Police Operational Debrief Report of 22 October 2007 to 7 November 2007, submitted to the Coroner, be further considered by the Tasmania Police for adoption where considered appropriate by Tasmania Police. |
REC166-3004 | 17 - Assets and technology | That the Tasmania Fire Service consider improvements in radio units installed in breathing apparatus: |
REC166-2999 | 35 - Business and Industry in relation to industry | That Aurora ensure that regular audits are conducted of all electrical systems of all commercial buildings to confirm that they comply with modern standards. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3556 | 17 - Assets and technology | The use of hospital transport vehicles to support retrieval operations be investigated. |
REC140-3564 | 17 - Assets and technology | The medical equipment used in retrieval and air ambulance duties undertaken by helicopter and fixed wing must be standardised. |
REC140-3563 | 17 - Assets and technology | An additional secure emergency oxygen supply source to be located in the BK 117 helicopter. An internal supply is preferred. |
REC140-3561 | 17 - Assets and technology | Development of a helipad at Mersey Hospital. |
REC140-3560 | 17 - Assets and technology | RHH requires a helipad. Plans to rebuild RHH must include a helipad at its earliest stage of conception. |
REC140-3559 | 17 - Assets and technology | A service level agreement is negotiated with the Police department that will cover access, tasking, price, equipment and staffing. This will enable a more strategic use of the helicopter. |
REC140-3565 | 17 - Assets and technology | The TMRS medical equipment inventory requires an overhaul. The TMRS medical equipment should be located with the TMRS team. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3629 | 8 - Communications and warnings | We recommend that NSW Health continue with its good work and continue to improve communication mechanisms with those, such as GPs, likely to be affected in major infectious disease outbreaks. |
REC129-3620 | 35 - Business and Industry in relation to industry | We recommend that NSW Health continue with its good work and conclude agreements with private health providers specifying roles, and expectations in the case of an infectious disease pandemic. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3600 | 34 - Local knowledge | The Department of Primary Industries continue to consult local community about emergency planning and sites for disposal to retain confidence in the event of a genuine emergency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3664 | 20 - Role of police | The location of the command post for site control at the scene of any rail accident should be identified by NSW Police by a distinctive flashing light. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |