Rec-ID | Code | Recommendation |
---|---|---|
REC310-2487 | 39 - Disaster Risk Management | The state’s arrangements for disaster management, including recovery, are articulated in the Disaster Management Act (2003), the Queensland Reconstruction Authority Act (2011), the State Disaster Management Plan and the Queensland Recovery Plan. To enable state-level arrangements to better support community-led recovery and to improve Queensland’s recovery governance |
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2457 | 8 - Communications and warnings | Efforts are made to improve the timeliness, accuracy and targeting of Emergency Alert messaging by: |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2466 | 41 - Emergency Management exercises | Exercising should focus on vertical integration and include all levels of the system. A strategic program of exercises should be developed and implemented. |