Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
REC002-4012 | 38 - Agency/Department Reporting | Complete sets of daily-report books should be provided, and kept in the mine or office, to be overlooked by the Inspector during his periodical visits. |
REC002-4011 | 32 - Doctrine, standards, and reform | The Commission feel that the 4th clause in the present Act, relating to the spacing of cut-throughs, should be amended to admit of any convenient or safe system of mining being pursued. This is a matter of detail that would be better out of the Act. The Commission would advise that the word should not occur at all, and that, if bratticing be used, or the air by some other satisfactory device be conveyed to the face, scope would be given to Managers to introduce systems of mining adapted to the circumstance of each particular coal-seam, with advantage to all concerned. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0530 | 32 - Doctrine, standards, and reform | That, if necessary, regulation be amended to require Health to approve any script used by any party concerned, for door knocking or other information dissemination, if Health is not the first source of information to affected residents. |
REC208-0529 | 32 - Doctrine, standards, and reform | That, when developing requirements concerning pollution incident response management plans pursuant to the recent legislative amendments, the Office of Environment and Hertiage include appropriate definitions as to the meaning of ‘immediately’, and when ‘material harm to the environment is caused or threatened’. |
REC208-0528 | 32 - Doctrine, standards, and reform | That, as part of the Pollution Incident Management Response Plan to be developed for Orica’s Kooragang Island site, or by another appropriate mechanism, the Office of Environment and Heritage ensure that Orica’s incident-response procedures address the need to consider all relevant factors when assessing potential impacts, including the height and force of emissions as well as the location of any onsite fallout and whether there are off-site impacts following all serious incidents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3621 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and establish a time table to finalise all emergency and contingency plans. |
REC129-3632 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and develop distinct surge capacity plans within each Area Health Service to manage emergency staffing needs, isolation facilities, intensive care units, assisted ventilation services, hospital beds and medical supplies. |
REC129-3631 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and continue to develop plans to respond to the surge in demand for diagnostic tests and for laboratory personnel. |
REC129-3630 | 32 - Doctrine, standards, and reform | We recommend that NSW Health continue with its good work and continue to develop systems to bring all the information relevant to the surge in demand for health resources together in real time. |
REC129-3625 | 38 - Agency/Department Reporting | We recommend that NSW Health continue with its good work and establish a performance management framework with targets and indicators to assess progress in preparing for infectious disease emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3601 | 38 - Agency/Department Reporting | That, as a matter of principle, the NSW Government provide public reports on the lessons learned from emergency exercises which it manages or in which it participates. If necessary, such reports should exclude material which might jeopardise security. |
REC128-3610 | 32 - Doctrine, standards, and reform | That the Minister for Primary Industries consider amending the Stock Diseases Act 1923 to ban the supply of waste swill to pig owners by food retailing businesses such as bakeries, restaurants and supermarkets. |
REC128-3619 | 38 - Agency/Department Reporting | That the Department of Primary Industries should ensure the roles and capacities of Rural Lands Protection Boards and industry are effectively monitored to enable assessment of the effectiveness of animal health programs. |
REC128-3599 | 32 - Doctrine, standards, and reform | In order to improve the response to animal health emergencies, that the Department of Primary Industries prioritise the finalisation of Memoranda of Understanding with the four jurisdictions bordering New South Wales. |
REC128-3605 | 38 - Agency/Department Reporting | That the Department of Primary Industries make every effort to meet its targets for the TSE program and encourage public and private sector veterinarians across the State to submit samples. The Department should include reports on its performance against these targets in annual reports. |
REC128-3618 | 32 - Doctrine, standards, and reform | That the Department of Primary Industries should complete a review of the Memorandum of Understanding and ensure the roles of the Department and Rural Lands Protection Boards are more clearly identified outlined for effective delivery of animal health programs. |
REC128-3604 | 37 - Funding | That the Department of Primary Industries restore the level of discretionary testing funds provided to District Veterinarians to previous levels and maintain these in the future in real terms. |
REC128-3617 | 37 - Funding | That the Department of Primary Industries should provide specific information on levies to contributing producers through a separate document, rather than rely on standard audit documents and annual reporting requirements. |
REC128-3603 | 37 - Funding | That the Department of Primary Industries consider applying discretion to the use of user charging policies for testing in times when farm incomes are affected by external circumstances such as widespread drought. |
REC128-3616 | 37 - Funding | That the Department of Primary Industries continue to pursue improvements to consultation with industry and accountability mechanisms to further build trust between industry and government, thereby enhancing the effectiveness of the OJD Program. |
REC128-3602 | 38 - Agency/Department Reporting | That the Department’s performance against tactical and strategic benchmarks be regularly reported in annual reports or animal and plant health emergency evaluation reports and compared to other jurisdictions where possible. |
REC128-3614 | 37 - Funding | The Committee encourages the Department and the Rural Land Protection Boards to discuss the need for funding of poultry surveillance activities in the context of reviewing the Memorandum of Understanding between the two parties. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3685 | 32 - Doctrine, standards, and reform | The ITSRR should impose a standard in relation to the collection and use of data from data loggers. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3655 | 32 - Doctrine, standards, and reform | Procedures should be put in place by RailCorp to ensure that electrical power supply to the area of an accident can be immediately isolated, if necessary, in the event of a rail accident, so as to reduce any risk of exposure of emergency response personnel to injury or harm. |
REC121-3696 | 32 - Doctrine, standards, and reform | Defects reporting, recording and rectification should be integrated with the RailCorp regimes for train maintenance. |
REC121-3761 | 32 - Doctrine, standards, and reform | Legislative changes should be enacted to ensure the complete independence of ITSRR from the Minister for Transport Services. |
REC121-3662 | 32 - Doctrine, standards, and reform | The rail displan should provide for the site controller to have complete control of the site, with other agencies co-ordinating with and supporting him or her, until the rescue phase of the emergency response has been completed. |
REC121-3705 | 32 - Doctrine, standards, and reform | The ITSRR should develop standards for periodic medical examinations which include the following: |
REC121-3771 | 32 - Doctrine, standards, and reform | RailCorp should establish an integrated safety management system which includes the following: |
REC121-3679 | 32 - Doctrine, standards, and reform | The rail safety regulator should set standards for the design, manufacture, testing and commissioning of rolling stock to ensure that the rolling stock is fit for its purpose. |
REC121-3728 | 32 - Doctrine, standards, and reform | Any barriers to communication between OTSI and ITSRR should be removed, so as to ensure that any findings made by OTSI in relation to any investigation it conducts are reported immediately to ITSRR. |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
REC121-3692 | 32 - Doctrine, standards, and reform | Communications protocols and procedures should be standardised and mandated by regulations making them a condition of accreditation. |
REC121-3760 | 32 - Doctrine, standards, and reform | The Advisory Board established under the Transport Legislation Amendment (Safety and Reliability) Act 2003 must be abolished. |
REC121-3661 | 32 - Doctrine, standards, and reform | The rail displan should include provision for the appointment of a rail emergency management co-ordinator at the RMC, and an on-site rail commander with the sole function of assisting and supporting the emergency services during the rescue phase of the emergency response. |
REC121-3701 | 32 - Doctrine, standards, and reform | Train inspections should be carried out at the time of stabling RailCorp trains, as well as a part of train preparation prior to entering service. |
REC121-3770 | 32 - Doctrine, standards, and reform | A safety management system regulation should be promulgated, specifying the requirements of safety management systems in all accredited organisations, using Annexure I to this report as a guide |
REC121-3674 | 32 - Doctrine, standards, and reform | Uniform verbal descriptions identifying that power has been isolated should be developed by RailCorp and utilised by all railway personnel, electrical service providers and all emergency response personnel. |
REC121-3727 | 32 - Doctrine, standards, and reform | The relevant legislation should be amended to provide expressly that OTSI and the Chief Investigator have the power to initiate a rail accident or incident investigation. |
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3690 | 32 - Doctrine, standards, and reform | All communications protocols must be strictly enforced by all accredited rail organisations. |
REC121-3750 | 32 - Doctrine, standards, and reform | ITSRR should initiate and/or participate in the development of a national standard for crashworthiness of all passenger trains. |
REC121-3660 | 32 - Doctrine, standards, and reform | The rail displan should include the use by all emergency response personnel of a uniform incident command system, involving procedures for such matters as the establishment of inner and outer perimeters, control of access to the site, orderly evacuation of injured passengers and the establishment of a staging area remote from the accident site, in a unified command structure with the site controller co-ordinating the various emergency services through representatives of each service. |
REC121-3699 | 32 - Doctrine, standards, and reform | All reported train defects should be certified by a person in a supervisory position in RailCorp as having been rectified. |
REC121-3769 | 32 - Doctrine, standards, and reform | The ITSRR should continue to participate in the development of a national system for rail safety regulation, provided that any ultimate agreement between the States and Territories and the Australian Government does not produce a safety outcome for New South Wales that is less than would be achieved by the implementation of all the recommendations contained in this report. |
REC121-3671 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include a requirement for the debriefing of all senior rail and emergency response personnel involved in any rail accident, so as to determine the way or ways in which emergency response arrangements for rail accidents can be continually improved, and thereafter implement such improvements. |
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3688 | 32 - Doctrine, standards, and reform | Communications procedures must be standardised throughout the rail network, so that all railway employees describe the same subject matter in an identical way. |
REC121-3736 | 32 - Doctrine, standards, and reform | The RailCorp passenger containment policy must be abandoned. |
REC121-3659 | 32 - Doctrine, standards, and reform | A railway disaster plan, or rail displan, should be developed by RailCorp and the emergency services to ensure co-ordinated inter-agency response to rail accidents and incidents on the RailCorp network. |
REC121-3698 | 32 - Doctrine, standards, and reform | No RailCorp train should enter into revenue service or remain in service if, in the opinion of the driver in charge of that train, any defect in it creates a risk of injury. |
REC121-3763 | 32 - Doctrine, standards, and reform | The ITSRR should publish guidelines to be followed by accredited organisations. |
REC121-3668 | 32 - Doctrine, standards, and reform | The RailCorp emergency response plan should include action checklists of the steps that each employee is required to take, and the order for specific employees to follow in case of emergency. |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3773 | 32 - Doctrine, standards, and reform | The ITSRR should ensure that RailCorp establishes a safety management system containing the 29 elements identified in the SMSEP report, and ensure the ongoing monitoring and improvement of the safety management system established. |
REC121-3686 | 32 - Doctrine, standards, and reform | The standard in relation to the collection and use of data from data loggers should provide that such information must be accessed in the circumstances of any accident or incident and can be accessed to monitor driver performance generally. |
REC121-3730 | 32 - Doctrine, standards, and reform | Legislation should be enacted and any necessary arrangements made, to enable the ATSB to review any reports of any investigation by a rail organisation or the OTSI into any serious incident or accident in New South Wales. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |
REC121-3762 | 32 - Doctrine, standards, and reform | The Chief Executive of ITSRR should have sole accountability and responsibility for the regulation of rail safety in New South Wales. |
REC121-3667 | 32 - Doctrine, standards, and reform | RailCorp should develop and implement an emergency response plan for management of all rail accidents. Such a plan should be subsumed by the rail displan in the case of serious accidents or incidents. |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3772 | 32 - Doctrine, standards, and reform | RailCorp should establish a safety management system containing the 29 elements identified in the SMSEP report which is in volume 2 of this report. |