REC317-4104 | 33 - Relief and recovery | Australian, state and territory governments should refine arrangements to support localised planning and the delivery of appropriate mental health services following a natural disaster. |
REC317-4120 | 16 - Training and behaviour | Australian, state and territory governments should establish a national mechanism for sharing of trained and qualified recovery personnel and best practice during and following natural disasters. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4119 | 33 - Relief and recovery | The Australian Government, through the mechanism of the proposed standing national recovery and resilience agency, should convene regular and ongoing national forums for charities, non-government organisations and volunteer groups, with a role in natural disaster recovery, with a view to continuous improvement of coordination of recovery support. |
REC317-4130 | 21 - Role of Commonwealth Government | The Australian Government should establish accountability and assurance mechanisms to promote continuous improvement and best practice in natural disaster arrangements. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4118 | 33 - Relief and recovery | Australian, state and territory governments should create a single national scheme for the regulation of charitable fundraising. |
REC317-4127 | 33 - Relief and recovery | Australian, state and territory governments should incorporate the principle of ‘build back better’ more broadly into the Disaster Recovery Funding Arrangements. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4117 | 33 - Relief and recovery | State and territory governments should develop and implement efficient and effective arrangements to: |
REC317-4126 | 33 - Relief and recovery | Australian, state and territory governments should expedite the development of pre-agreed recovery programs, including those that address social needs, such as legal assistance domestic violence, and also environmental recovery. |
REC317-4116 | 33 - Relief and recovery | Governments should create and publish standing policy guidance on whether they will or will not assist to clean-up debris, including contaminated debris, resulting from natural hazards. |
REC317-4122 | 33 - Relief and recovery | Australian, state and territory and local governments should evaluate the effectiveness of existing financial assistance measures to inform the development of a suite of pre-effective pre-determined recovery supports. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
REC210-0696 | 21 - Role of Commonwealth Government | Carriers, councils and the Australian Communications and Media Authority should take into account the risk of flooding when considering the placement of telecommunications facilities. |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0175 | 16 - Training and behaviour | The Country Fire Authority and the Department of Sustainability and Environment require without exception that all relevant staff be trained in the need for Incident Controller approval to be obtained before a back-burn is lit. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0186 | 21 - Role of Commonwealth Government | The Commonwealth, states and territories continue to pursue the National Action Plan to Reduce Bushfire Arson in Australia, giving priority to producing a nationally consistent framework for data collection and evaluating current and proposed programs in order to identify and share best-practice approaches. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4144 | 16 - Training and behaviour | No opportunity be lost of encouraging the formation of bush fire brigades and the maintenance of enthusiasm and that the Bush Fires Board assist the brigades in any way possible to obtain adequate training and equipment. |
REC019-4158 | 16 - Training and behaviour | That needs in the direction of a fire emergency service be met as far as practicable by the Bush Fires Board in its training programme and in the tactical organisation of existing brigades for use as reserves in districts other than their own. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3948 | 16 - Training and behaviour | It is recommended that workers and volunteers generally be instructed in accordance with a pre-arranged plan, as to what they should do in future times of emergency. Since the fighting of fires is for the greater part a matter of voluntary action, some estimate could perhaps be made, after investigation, of the numbers of men in each department who would be willing to volunteer. It would be necessary that each department should become a component part of an over-riding scheme and that it and its members should be fully instructed in the matter of whistle or siren warnings, places of assembly, reception of messages from the director of proceedings, use of equipment, and the various details which would necessarily be parts of an effective scheme. The training need not be onerous. If given once or twice at the beginning of possible danger periods, it would make for some degree of order and efficiency instead of a probable state of confusion. |
REC016_3945 | 16 - Training and behaviour | It is recommended that a large proportion of men employed in and about the open-cut be systematically trained in the use of equipment and in the tactical disposition of it. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3960 | 33 - Relief and recovery | It is recommended that the Forests Commission recognize and provide for the efficient exercise of three major functions, namely those of Commerce, Reclamation and Rehabilitation. |