Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2457 | 8 - Communications and warnings | Efforts are made to improve the timeliness, accuracy and targeting of Emergency Alert messaging by: |
REC308-2455 | 32 - Doctrine, standards, and reform | The Queensland Offers of Assistance Policy, particularly for corporate donations, should be updated and exercised prior to the next season. |
REC308-2466 | 41 - Emergency Management exercises | Exercising should focus on vertical integration and include all levels of the system. A strategic program of exercises should be developed and implemented. |
REC308-2454 | 10 - Infrastructure | Local disaster management groups should focus on the business continuity of local critical infrastructure and its integration with other plans. |
REC308-2465 | 29 - Operational Health and Safety | Fatigue management strategies and guidance should be improved to ensure sustainable staffing practices are incorporated into disaster management planning. |
REC308-2453 | 32 - Doctrine, standards, and reform | Business continuity planning should feature permanently in disaster management doctrine. |
REC308-2464 | 16 - Training and behaviour | The provision of system-wide education, guidance and testing to enhance requests for Assistance is strengthened. |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3341 | 32 - Doctrine, standards, and reform | The definition of ‘good oilfield practice’ in the OPGGS Act is unduly narrow. The current definition is incapable of application except where things ‘are generally accepted as good and safe’. The definition should be amended such that ‘good oilfield practice includes…’. |
REC177-3368 | 32 - Doctrine, standards, and reform | The regulatory framework should provide that in respect of all activities in Commonwealth waters: |
REC177-3275 | 32 - Doctrine, standards, and reform | Well Operations Management Plan (WOMPs) submitted by licensees to the regulator(s) should continue to be the primary framework document for achieving well integrity. |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3309 | 32 - Doctrine, standards, and reform | If performance of barrier installation is outsourced by a licensee, the contractor (for example, the cementing company) should be engaged on terms which clearly require the provision of expert advisory services by the contractor with respect to barrier integrity. |
REC177-3326 | 32 - Doctrine, standards, and reform | Prior to commencement of drilling operations, senior representatives of the licensee and rig operator should exchange certificates to the effect that their respective key personnel and contractors have been informed in writing of agreed well control arrangements. |
REC177-3353 | 32 - Doctrine, standards, and reform | The regulatory regime should also impose an obligation on an operator to ascertain the availability, and provide details to the regulator, of any potential relief well rigs, prior to the commencement of drilling operations (including prior to each phase of a drilling operation where applicable). |
REC177-3280 | 32 - Doctrine, standards, and reform | Well construction and management plans should include provision for an independent compliance review of well integrity (i) in the event of stipulated triggers; and (ii) at least once in the period between perceived achievement of well integrity and production. The independent compliance review should be undertaken by an expert who is not involved in the day‐to‐day drilling operations. Reviews should be completed in sufficient time to enable results to be implemented in a meaningful manner. |
REC177-3298 | 32 - Doctrine, standards, and reform | Reliance upon one barrier against a blowout must not take place except with the prior written approval of the relevant regulator and then only in a true emergency situation (see below). |
REC177-3315 | 32 - Doctrine, standards, and reform | PCCCs should be installed in a timely manner (for example, to prevent corrosion in the MLS apparatus). Non‐installation in order to park a BOP is not acceptable. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3360 | 42 - Culture and Heritage | DEWHA should participate in training programs and exercises relevant to an oil spill in the marine environment. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3320 | 32 - Doctrine, standards, and reform | Any pro‐formas used by licensees, rig operators and contractors for recording information about installation of barriers should explicitly provide for ‘exception reporting’, that is, the form should include provision for recording any unforseen or untoward events which occur in the course of installation. |
REC177-3340 | 32 - Doctrine, standards, and reform | To better ensure that ‘risks’ are identified and managed in accordance with sound engineering principles and good oilfield practice, it is recommended that regulation 25(1)(a)(i) and (2)(a)(i) of the Management of Well Operations Regulations, be reworded as follows: ‘A titleholder must not commence / continue a well activity if…a well integrity hazard exists in relation to the well’. |
REC177-3367 | 32 - Doctrine, standards, and reform | Procedures and accountabilities should be established to ensure, in the event of a future incident, that: |
REC177-3292 | 32 - Doctrine, standards, and reform | Licensees should be subject to an express obligation to inform regulators of the proposed removal of a barrier, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. Removal of a barrier should not take place without prior written approval of the relevant regulator(s). |
REC177-3308 | 32 - Doctrine, standards, and reform | Volumes of cement used in connection with barrier installation should be calculated with the assistance of a pro‐forma which records all relevant baseline data, which should be verified by onshore personnel. |
REC177-3325 | 32 - Doctrine, standards, and reform | Relevant personnel from licensees and rig operators should meet face to face to agree on, and document, well control issues/arrangements prior to commencement of drilling operations. Well control should be regarded as a so‐called SIMOP to signify its critical importance to both licensees and rig operators, and to ensure that they each take responsibility for achievement and maintenance of well control. |
REC177-3352 | 32 - Doctrine, standards, and reform | The regulator, rather than the responsible Minister, should be given the power to direct an operator to use a particular rig for the purpose of well control operations, if appropriate in the circumstances, and the power should be used in the future if that rig is the best option available. This would necessarily involve the operator fully compensating for the use of the rig and any other associated costs. The Inquiry suggests that this power could be invoked and given effect as a condition of an operator’s licence. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3297 | 32 - Doctrine, standards, and reform | A minimum of two barriers should be in place at all times (including during batched operations) whenever it is reasonably practicable to do so. |
REC177-3314 | 32 - Doctrine, standards, and reform | Secondary barriers (including PCCCs) should only be installed, tested, and removed with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3359 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed to clarify the arrangements to apply in Commonwealth waters regarding key roles and responsibilities, including in relation to the ESC, in the event of an oil spill. This should also address any necessary training required. |
REC177-3284 | 32 - Doctrine, standards, and reform | Memoranda of Agreement should be entered into between operators in relation to provision of emergency assistance in the event of blowouts. |
REC177-3302 | 32 - Doctrine, standards, and reform | Industry, regulators, and training/research institutions should develop standards that address best practices for cementing operations (including liaising, as appropriate, with overseas regulators) with a view to overcoming problems which can effect the integrity of cemented casing shoes, annulus and cement plugs. |
REC177-3319 | 32 - Doctrine, standards, and reform | Drilling programs dealing with barrier installation should incorporate relevant aspects of manufacturer’s instructions. |
REC177-3339 | 32 - Doctrine, standards, and reform | The Inquiry supports the objective (rather than prescriptive) approach to regulation now followed in Australia. However, the pendulum has swung too far away from prescriptive standards. In some areas relating to well integrity there needs to be minimum standards. |
REC177-3366 | 32 - Doctrine, standards, and reform | The National Plan should be reviewed: |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3307 | 32 - Doctrine, standards, and reform | Any indication of a compromised cemented shoe which cannot be resolved with a high measure of confidence should result in the installation of additional well control barrier(s). |
REC177-3324 | 32 - Doctrine, standards, and reform | The mere fact that the rig is over the platform should not be regarded by licensees or regulators as sufficient justification for reliance on only one barrier. The default position should be that producible wells are shut‐in when a rig is moved on and off a platform, or when a drilling unit is moved between wells on a platform. |
REC177-3350 | 32 - Doctrine, standards, and reform | The recommendations of the Inquiry in relation to suitable ways of achieving well integrity contained in Chapter 3 be included in a guidance manual that is issued for the assistance of industry and regulators. |
REC177-3377 | 32 - Doctrine, standards, and reform | The Minister consider legislative amendments to the OPGGS Act which make clear that |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC177-3296 | 32 - Doctrine, standards, and reform | Use of single strings of intermediate casing to penetrate hydrocarbon bearing zones should be carefully risk assessed. Multiple strings of intermediate casing have the advantage of isolating lost circulation zones and sealing off anomalous pressure zones. If intermediate casing is set in a hydrocarbon zone it should be treated as production casing. |
REC177-3313 | 32 - Doctrine, standards, and reform | Barriers should not be installed or removed off‐line. The derrick should be located over a well at the time of removal and installation of any barrier. This will enable more decisive action to be taken in the event a problem arises. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3283 | 32 - Doctrine, standards, and reform | A separate, identifiable barrier manual should be agreed upon and used by licensees, rig operators, and cementing contractors. These manuals should set out best industry practice in relation to achieving and maintaining well integrity. They should describe barrier types, barrier standards, general principles of well integrity, testing and verification methods and technologies, standard operating procedures (including procedures for the capture and communication of relevant information within and between relevant stakeholder entities). Barrier manuals should address blowout control during drilling, completion, re‐entry, tie‐back of casing strings and so on. Barrier manuals should be the subject of expert external review, and should be regularly updated. |
REC177-3301 | 32 - Doctrine, standards, and reform | The industry standard of two barriers should be replaced with the concept of ‘two or more barriers’ as a minimum standard. A minimum standard when operations proceed normally should never be regarded as a sufficient standard in other circumstances. |
REC177-3318 | 32 - Doctrine, standards, and reform | Manufacturers should be consulted about how to address non‐routine operational problems affecting their well control equipment. |
REC177-3335 | 32 - Doctrine, standards, and reform | Licensees, rig operators and relevant third party contractors should develop well control competency standards for key personnel in other entities involved in well control operations. |
REC177-3363 | 32 - Doctrine, standards, and reform | DEWHA, in concert with AMSA and with expert input, should develop ‘off the shelf’ monitoring programs that can be speedily implemented following incidents in Commonwealth waters. In this context, the utility of the current Scientific Monitoring program should be peer reviewed to inform future policy. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3306 | 32 - Doctrine, standards, and reform | It should be standard industry practice to re‐test a cemented casing shoe (that is, after WOC) whenever the plugs do not bump or the float valves apparently fail. Standard industry practice should require consideration of other tests in addition to a repeat pressure test. |
REC177-3323 | 32 - Doctrine, standards, and reform | Where multiple wells are drilled, operations and occurrences at one well must be carefully assessed for any implications with respect to well control at other wells. |
REC177-3343 | 32 - Doctrine, standards, and reform | The OPGGS Act should be amended to allow for a power to suspend a petroleum production licence (in addition to the current power to cancel a licence or suspend its conditions). |
REC177-3373 | 32 - Doctrine, standards, and reform | Arrangements should be developed to minimise duplication between the EPBC Act and the OPGSS Act Environment Regulation. |
REC177-3277 | 32 - Doctrine, standards, and reform | The concept of ‘good oilfield practice’ should be supplemented by the requirement to incorporate into WOMPs non‐exhaustive minimum compliance standards in relation to well control: for example, stipulations as to when BOPs and/or well control systems must be in place and when they can be removed and minimum barrier requirements (a number of other factors that should be stipulated are outlined in other recommendations below). |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3312 | 32 - Doctrine, standards, and reform | The BOP and rig should not move from a well until barrier integrity has been verified. |
REC177-3328 | 32 - Doctrine, standards, and reform | All communications between on‐rig and onshore personnel relating to well control should be documented in a timely manner. |
REC177-3355 | 32 - Doctrine, standards, and reform | The Inquiry also supports Bills and Agostini’s recommendation: ‘…in relation to safety case development and compliance overall, that NOPSA revise its approach to interacting with operators prior to the safety case assessment process and subsequently direct more resources into its advisory functions. We further recommend that NOPSA develop and implement a formal plan for supporting and guiding each operator prior to safety case acceptance, as well as for ongoing compliance with that safety case, recognising the unique experience, capabilities and assessed risk of that operator. Each plan needs to include advice, education and liaison meetings with the operators. The plan needs to be continuously reviewed and reassessed based on the latest information, including the interaction with the operator’. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3300 | 32 - Doctrine, standards, and reform | Licensees and rig operators should install an additional barrier whenever (i) there is any real doubt as to the integrity of any barrier; (ii) whenever the risk of flow from a reservoir increases materially in the course of operations; and (iii) where the consequences of a blowout are grave (for example, for reef systems or shorelines). |
REC177-3317 | 32 - Doctrine, standards, and reform | Any equipment (including PCCCs) used as, or to install, a barrier should be manufactured for that purpose and be generally recognised as fit for purpose. If equipment is designed in‐house by a licensee or rig operator it should not be approved for use unless and until it is subjected to expert external analysis. |
REC177-3334 | 32 - Doctrine, standards, and reform | Licensees, rig operators, and relevant third party contractors should develop well control competency standards for their key personnel. Wherever possible, the competencies of key personnel should be benchmarked against their roles and responsibilities. |
REC177-3362 | 32 - Doctrine, standards, and reform | Procedures for the approval of development projects should ensure that conditions of approval are comprehensive and clearly set out the obligations of their proponents in relation to environmental matters (including expected monitoring and remediation obligations). |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3305 | 32 - Doctrine, standards, and reform | Cement integrity should be evaluated wherever practicable by way of cement evaluation tests, rather than relying on pre‐operational calculations of cement and displacement fluid volumes. |
REC177-3322 | 32 - Doctrine, standards, and reform | Batched drilling operations should only be undertaken after careful assessment of the special risks which such operations give rise to; well control must be maintained during the course of batched drilling operations. |
REC177-3342 | 32 - Doctrine, standards, and reform | Written (rather than verbal) approval from the DA (or new regulator) should be obtained before the commencement of well activities that lead to a physical change of a wellbore, other than in a true emergency situation (requiring amendment to regulation 17 of the Management of Well Operations Regulations). |
REC177-3370 | 32 - Doctrine, standards, and reform | Environment plans and OSCPs should be made publicly available as a condition of approval of proposals under the OPGGS Act, and should clearly set out Scientific Monitoring requirements in the event of an oil spill. |
REC177-3276 | 32 - Doctrine, standards, and reform | WOMPs should be comprehensive and freestanding, rather than an overarching document cross‐referencing many other documents (although the Inquiry also recommends a freestanding well control manual; this should be a guide to rig and onshore personnel on good oilfield practice). |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3311 | 32 - Doctrine, standards, and reform | Horizontal or high angle penetration of a reservoir should be avoided wherever practicable until such time as the apparent problems associated with the cementing of a casing shoe in these situations are satisfactorily overcome. If a casing string does penetrate a well horizontally or at a high angle, standard practice should be to install two secondary barriers in addition to the cemented casing shoe. |
REC177-3327 | 32 - Doctrine, standards, and reform | Information relevant to well control must be captured and communicated within and between licensees and rig operators (and relevant third party contractors), in a manner which ensures it comes to the attention of relevant personnel. In particular, protocols should be developed to ensure that changes in shift and hitch do not operate as communication barriers. |
REC177-3354 | 32 - Doctrine, standards, and reform | NOPSA develop a policy of engagement with operators so as to enable experts (including safety experts) to canvas all available options for well control in the event of a blowout. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3316 | 32 - Doctrine, standards, and reform | Wells should be re‐entered with a BOP in place unless a documented risk assessment indicates that well control can be maintained at all times. |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3361 | 32 - Doctrine, standards, and reform | The National Plan should be revised to ensure that it fully comprehends environmental matters and that it recognises the importance of the prompt implementation of Scientific Monitoring to facilitate the assessment of the environmental impacts of an incident. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3504 | 32 - Doctrine, standards, and reform | The Emergency Services Telecommunications Authority develop a protocol to direct the suspension or cessation of scheduled telecommunication maintenance or testing to emergency alert systems during an emergency event. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3509 | 8 - Communications and warnings | The Victoria State Emergency Service, Department of Primary Industries, Energy Safe Victoria and the energy sector develop a coordinated set of safety messaging about preparedness for storm events and clearly outline the responsibilities for delivering these messages before during and after an emergency. |
REC156-3497 | 8 - Communications and warnings | Emergency Service Organisations work with government departments, local governments and private industry to identify and implement a model for communication flow during an emergency incident. |
REC156-3503 | 8 - Communications and warnings | Emergency Service Organisations review their use of Emergency Alerting System paging message categories to ensure that priority messages are not compromised by inappropriate use. An education program may be required to ensure that all users understand message categories, their intended use and ramifications of each category on network and message delivery sequence. |
REC156-3484 | 32 - Doctrine, standards, and reform | The Victoria State Emergency Service finalise its development of strategic emergency response management plans including severe weather and storm events. |
REC156-3508 | 32 - Doctrine, standards, and reform | The Australian Broadcast Corporation and Emergency Services Organisations redevelop the protocols for the use of the Memorandum of Understanding; and all relevant emergency services and ABC staff are trained in the use of the protocols. |
REC156-3495 | 16 - Training and behaviour | The Department of Primary Industries should work through the appropriate Ministerial Councils to seek alignment of competency standards for line workers across jurisdictions. |
REC156-3515 | 8 - Communications and warnings | The electricity distribution businesses enhance power outage information on their websites which are accessible to electricity retail businesses, the media and the public and also consider improving their capacity to communicate with customers. |
REC156-3501 | 32 - Doctrine, standards, and reform | The Country Fire Authority review their procedures regarding receipt of Triple Zero calls on the Brigade Spectrum Preset Conference including training material, testing procedures and interface back to the Emergency Services Telecommunications Authority Computer Aided Dispatch system. |
REC156-3507 | 8 - Communications and warnings | Victoria progress, as a matter of priority, a telephony based public emergency notification system to reduce demand on Triple Zero and other emergency telephone lines during a major emergency. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3513 | 32 - Doctrine, standards, and reform | The Department of Primary Industries in consultation with the energy sector develop and implement a Memorandum of Understanding or similar authorising instrument that provides a single contact for emergency |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3506 | 26 - Research | The Office of the Emergency Services Commissioner facilitate further research into technologies that will reduce the need for the public to speak to an operator during an emergency as a component of the proposed emergency warning and alert system and Victorian Emergency Information Line. |
REC156-3491 | 8 - Communications and warnings | The Victoria State Emergency Service improve its communication with local governments, especially in relation to severe weather and storm warning information. |
REC156-3511 | 32 - Doctrine, standards, and reform | The operational protocols of the Emergency Management Joint Public Information Committee be formally endorsed by the State Emergency Response Planning Committee and the Victorian Emergency Management |
REC156-3499 | 32 - Doctrine, standards, and reform | The Department of Primary Industries clearly document responsibilities within the Department to ensure better co-ordination of public information during emergencies. |
REC156-3505 | 32 - Doctrine, standards, and reform | The Emergency Service Organisations and the Emergency Services Telecommunications Authority agree on the direct telephone numbers to be used for contacting the Emergency Services Telecommunications Authority in relation to emergency incidents. The Emergency Service Organisations need to ensure an effective process is in place to educate their personnel in relation to the use of these numbers. |
REC156-3489 | 32 - Doctrine, standards, and reform | The Department of Primary Industries responsibility for emergency management within the energy sector needs to be reinforced consistent with Recommendation 5. |
REC156-3510 | 32 - Doctrine, standards, and reform | Victoria’s emergency management arrangements as they relate to the Emergency Management Joint Public Information Committee be enhanced to include greater clarity of its operational role in the Emergency Management Manual Victoria. |
REC156-3498 | 32 - Doctrine, standards, and reform | The Department of Primary Industries, Department of Premier and Cabinet, and the Office of the Emergency Services Commissioner review and clarify energy sector emergency event trigger points for the activation of Central Government Response Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3526 | 8 - Communications and warnings | That consideration be given to additional ways and means to improve broadcast capability into disaster-affected regions, particularly for the early aftermath of any disaster when a loss of power characterises the event. |
REC136-3528 | 8 - Communications and warnings | An early and high priority task in recovery from a natural disaster should be the development of a coordinated, succinct, practical and flexible public communications plan. |
REC136-3527 | 8 - Communications and warnings | In any future large-scale disaster or event, consideration be given to a centrally located Media Operations Centre. |