Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2475 | 15 - Inter-service cooperation | Greater emphasis be placed on pre-planned and pre-determined arrangements between the Australian Defence Force and State and local agencies. |
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2460 | 11 - Evacuation and shelters | The Queensland Chief Health Officer should work with the Office of the Inspector-General Emergency Management to raise, with the Commonwealth, the need for all aged care providers to plan and exercise for evacuation to a similar safe establishment. |
REC308-2458 | 39 - Disaster Risk Management | A strategy should be developed to improve the availability of information to decision-makers and other audiences. Information should be searchable, more specific, timely, and allow stake-holders to find what they want. |
REC308-2457 | 8 - Communications and warnings | Efforts are made to improve the timeliness, accuracy and targeting of Emergency Alert messaging by: |
REC308-2452 | 39 - Disaster Risk Management | Planning and warnings for storm tide should be based on modelling that shows the chances of an event occurring (probabilistic). |
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
REC308-2462 | 11 - Evacuation and shelters | Relevant authorities should work with the tourism sector to clarify future arrangements for evacuation. In particular they should look closely at differentiating voluntary and directed evacuations in their messaging, |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC136-3528 | 8 - Communications and warnings | An early and high priority task in recovery from a natural disaster should be the development of a coordinated, succinct, practical and flexible public communications plan. |
REC136-3527 | 8 - Communications and warnings | In any future large-scale disaster or event, consideration be given to a centrally located Media Operations Centre. |
REC136-3526 | 8 - Communications and warnings | That consideration be given to additional ways and means to improve broadcast capability into disaster-affected regions, particularly for the early aftermath of any disaster when a loss of power characterises the event. |
REC136-3523 | 38 - Agency/Department Reporting | This Report should be considered for publication so that the insights, data, conclusions and recommendations are available within Queensland and other jurisdictions to assist with disaster management issues in the future. |