Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1604 | 8 - Communications and warnings | Governments and other stakeholders consider reviewing their existing emergency management arrangements to ensure public communications are clear and the public is kept informed of the incident response. |
REC233-1603 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy (DBCDE) to work with the Triple Zero Awareness Work Group through Australian Communications and Media Authority's (ACMA) Emergency Service Advisory Committee to review Triple Zero awareness messages with regard to telecommunications outages. |
REC233-1592 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy will work with the Communications Sector Group within the Trusted Information Sharing Network to develop best practice guidance for owners of critical communications infrastructure regarding public messaging during a prolonged telecommunications outage covering: |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1873 | 8 - Communications and warnings | Fire services can improve outcomes by implementing standard procedures that ensure the welfare and safety of crews and the public are not compromised |
REC215-1871 | 14 - Incident Mgt Teams | Fire services can improve outcomes by developing a checklist for use by incident controllers |
REC215-1877 | 39 - Disaster Risk Management | Regulators can help to achieve improved outcomes by considering the issues identified by this review |
REC215-1876 | 39 - Disaster Risk Management | Fire services can improve outcomes by initiating discussions with landfill operators about fire management planning and emphasising the critical importance of water supplies and early intervention |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1920 | 6 - Insurance and legal liability | The Attorney General gives urgent consideration to determining an ex gratia payment for: |
REC204-1910 | 6 - Insurance and legal liability | As part of its review of its contract management processes, Tourism WA (with the Board of Tourism WA taking a lead role) should amend its contract template for event sponsorship to ensure that: |
REC204-1908 | 39 - Disaster Risk Management | As part of the current revision of its contract template for sponsorship agreements, Tourism WA should ensure that: |
Rec-ID | Code | Recommendation |
---|---|---|
REC198-2905 | 14 - Incident Mgt Teams | The Fire Services Commissioner ensures that there is a single standard for the tabards worn by the IMT on the fireground and in control centres to ensure consistency and aid interoperability. |
REC198-2902 | 14 - Incident Mgt Teams | The Fire Services Commissioner clarifies the role of regional controller for major fires and incidents other than bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
REC177-3369 | 6 - Insurance and legal liability | The obligation of companies involved in an incident to meet the full costs of monitoring and remediation should be made a condition of approval of proposals under the EPBC Act and OPGGS Act. Suitable arrangements (insurance or otherwise) need to be in place to ensure that companies have this capacity. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3310 | 6 - Insurance and legal liability | Consideration should be given to ways to ensure that contractors who are involved in barrier installation (such as cementing companies) have a direct interest in the performance of works to a proper standard. In particular, consideration should be given to (i) preventing contractors from avoiding the economic consequences of negligent installation of barriers; and/or (ii) imposing specific legislative standards of workmanship on contractors with respect to well control (similar to those which presently apply to licensees). |
REC177-3365 | 6 - Insurance and legal liability | The National Plan should specify that the cost of responding to an oil spill, or other damage to the offshore marine environment, will be totally met by the owner/operator. This would be consistent with the Inquiry’s recommendation for legislative changes to the regulatory framework concerning owner/operators meeting the cost of monitoring and remediation of environmental damage. |
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3364 | 37 - Funding | The funding arrangements that support the National Plan should be reviewed to ensure that the costs associated with both preparedness and response capability are equitably shared between the shipping and offshore petroleum industries. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3004 | 17 - Assets and technology | That the Tasmania Fire Service consider improvements in radio units installed in breathing apparatus: |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3251 | 37 - Funding | The Committee recommends that the Government act urgently to make the existing system of funding the fire services fair and equitable to all Victorians. |
REC061-3416 | 37 - Funding | The Committee recommends that the Government act urgently to make the existing system of funding the fire services fair and equitable to all Victorians. |
REC061-3249 | 37 - Funding | That the cost of a Bureau of Emergency Services Telecommunications centre be recovered through user charges. |
REC061-3414 | 37 - Funding | That the cost of a Bureau of Emergency Services Telecommunications centre be recovered through user charges. |
REC061-3253 | 37 - Funding | The Committee recommends that any change to the funding system reflect in a reduction of the total price charged to consumers through premiums by the insurance industry. |
REC061-3418 | 37 - Funding | The Committee recommends that any change to the funding system reflect in a reduction of the total price charged to consumers through premiums by the insurance industry. |
REC061-3252 | 37 - Funding | The Committee recommends that an equitable funding system be implemented which relates premiums to: |
REC061-3417 | 37 - Funding | The Committee recommends that an equitable funding system be implemented which relates premiums to: |