Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
REC199-0458 | 7 - Inter-agency communication | the state ensure: • a common, functional and accessible system be introduced to enable effective Municipal Emergency Coordination Centre and Incident Control Centre communications • a regime of regular Municipal Emergency Coordination Centre exercising is introduced with oversight by an appropriate independent body. Such exercising should include testing of systems utilised for Incident Control Centre and Municipal Emergency Coordination Centre communications • those required to perform Emergency Management Liaison Officer roles have undertaken appropriate training; and • resource requesting arrangements are clarified and documented so that control and coordination functions do not overlap. |
REC199-0449 | 7 - Inter-agency communication | the state ensure that interoperable information management practices are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0447 | 7 - Inter-agency communication | the state ensure that common and interoperable resource management systems are developed and implemented by emergency management agencies. Common systems should be utilised to the fullest extent possible. |
REC199-0446 | 7 - Inter-agency communication | the state commit to securing effective multi-agency interoperable communications as a high level priority and that all future communications projects and upgrades incorporate compliance provisions mandating interoperability requirements. |
REC199-0418 | 7 - Inter-agency communication | the state develop an efficient process to ensure that, during flood events, temporary construction of flood mitigation works, such as levees, is controlled so as not to unacceptably impact on flood intelligence. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |