REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0723 | 28 - Personal responsibility | Councils should support and encourage business owners to develop private flood evacuation plans by providing the following to business owners in areas known to be affected by flood: • information about the benefits of evacuation plans • contact details of relevant council and emergency service personnel for inclusion in evacuation plans. |
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0679 | 28 - Personal responsibility | If the Queensland Development Code is amended to include provisions requiring homeowners to install sewage reflux valves, the Queensland Government should develop and make available to homeowners appropriate guidance material to assist them in meeting their responsibilities to maintain reflux valves. |
REC210-0724 | 28 - Personal responsibility | Councils should consider making available to business owners locality specific information that would assist them to develop evacuation plans for commercial premises, for example, any evacuation sub-plan created under Emergency Management Queensland’s disaster evacuation guidelines. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0444 | 2 - Emergency powers | the state, as a matter of urgency, develop a multi-agency Incident Control Team capability to be readily available for statewide deployment to establish incident control or to relieve functioning control structures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3295 | 29 - Operational Health and Safety | Wells drilled into hydrocarbon zones should be treated as live wells, with the potential to blowout unless a documented risk assessment establishes otherwise. |
REC177-3279 | 29 - Operational Health and Safety | Well construction and management plans, and drilling programs, should include provision for testing and verifying the integrity of all barriers as soon as practicable after installation. |
REC177-3294 | 29 - Operational Health and Safety | Perceived time and cost savings relating to any matters impacting upon well control should be subjected to rigorous safety assessment. |
REC177-3278 | 29 - Operational Health and Safety | Well construction and management plans should include provision(s) for reviewing the integrity of barriers at safety‐critical times or milestones, such as (i) prior to suspension involving departure of the rig from the platform; (ii) prior to re‐entry of a well after suspension; (iii) prior to removal of any barrier. |
REC177-3293 | 29 - Operational Health and Safety | If a dispute arises between a licensee and a rig operator in relation to a well control issue, and is not resolved between them, the matter must be raised with the relevant regulator before discretionary operations proceed. |
REC177-3321 | 29 - Operational Health and Safety | Careful consideration must be given to equipment compatibility as part of well construction design. |
REC177-3288 | 29 - Operational Health and Safety | As soon as a risk of barrier failure arises, no other activities should take place in the well other than those directed to removal of the risk. |
REC177-3303 | 29 - Operational Health and Safety | Tracking and analysis of cementing problems/failures should occur to assess industry trends, principal causes, remedial techniques and so on. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC177-3282 | 29 - Operational Health and Safety | If a risk assessment or compliance review is triggered by the happening of a predetermined event, specific consideration should be given to whether a ‘hold point’ should be introduced such that work must cease until the problem is resolved (and the subject of appropriate certification). |
REC177-3299 | 29 - Operational Health and Safety | Regulatory approval to rely on only one barrier should not be given unless (i) a proper risk assessment is carried out; (ii) exceptional circumstances exist; and (iii) risks involved are reduced to ‘as low as reasonably practicable’. The default position must be that well integrity must be assured. |
REC177-3281 | 29 - Operational Health and Safety | Wellbore gas bubbling should be regarded as a trigger for independent review of well integrity. Industry and regulators should identify and document other triggers. |