Rec-ID | Code | Recommendation |
---|---|---|
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1302 | 28 - Personal responsibility | That the State Emergency Service together with the Local Government Association and Country Fire Service establish a plan for coordinated provision of sandbags to the public, including options for what is provided, where and when, and the process for effective communication of availability to the public. |
REC295-1329 | 8 - Communications and warnings | Review and update Part 3, Annex C, of the SEMP ‘Public Information and Warnings’ to: a) clarify the role and responsibilities of the Public Information Functional Support Group and control agencies in relation to public information b) define requirements and processes for liaising with the community, including holding community meetings |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1313 | 16 - Training and behaviour | That regular training and exercising is conducted for all State Emergency Centre participants including Liaison Officers. |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1319 | 24 - Govt responsibility | That a single emergency service multi-agency control centre be established with sufficient capacity and capability to deal with all types of emergency incidents in SA. Also consider Police and State Emergency Centre. |
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1312 | 24 - Govt responsibility | That the Department of Education and Child Development be included as a member of State Emergency Management Council and represented in the State Emergency Centre. |
REC295-1291 | 24 - Govt responsibility | That the Flood Reform Task Group, as proposed by the Department |
REC295-1318 | 24 - Govt responsibility | That the recommendation made following the Pinery bushfire, ‘to review control facilities at State, region and incident level’, be expanded to include all emergency services facilities that will be utilised for major incidents other than bushfire e.g. flood and earthquake and to also be extended into metropolitan areas, and implemented. |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
REC295-1274 | 35 - Business and Industry in relation to industry | That relevant agencies, such as the Department of State Development, SA Police and emergency services, collaborate to establish an education campaign to encourage businesses in South Australia to develop Business Continuity Plans which, among other potential hazards such as flood and fire, also take into account the potential impact of an extended power outage. |
REC295-1308 | 24 - Govt responsibility | That the Department of the Premier and Cabinet revise the ministerial documents relating to emergency management. |
REC295-1288 | 24 - Govt responsibility | That Attorney General’s Department explore options to overcome fatigue and welfare issues of SAGRN staff associated with emergency events of extended duration. |
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
REC295-1324 | 16 - Training and behaviour | Establish a State incident management and emergency management training capability which provides for: a) consistent training across the State b) personal development and endorsement processes for roles c) identification, recruitment and development of personnel from other government agencies; and d) incident management and State emergency centre functional role training and development across all sectors. e) skills maintenance including upskills, refresher training and exercises f)incident and strategic leadership training g) consistent training for inter-agency liaison officers at all levels |
REC295-1306 | 9 - Community education | Develop practical policy outcomes to support resilience (e.g. the 72- hour model) and promote this broadly to community through media, awareness campaigns, policies etc. Research should be undertaken to gain insight into the types of messaging and activities that have the most impact on sustained behaviour change within the community before committing to a particular model. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1316 | 24 - Govt responsibility | That the position of Deputy Director, Office for Digital Government is dedicated to the Office for Digital Government; and that people throughout DPC are identified and trained to perform appropriate roles within the State Crisis Centre |
REC295-1296 | 8 - Communications and warnings | That the SES in collaboration with MFS Communications Centre (Comcen) investigate and implement options to reduce the number of calls coming into the Comcen, (particularly on 132500). Options could include better utilisation of the available options on the Interactive Voice Recording and community education to increase community resilience. |
REC295-1321 | 16 - Training and behaviour | Through the Emergency Management Workforce Project, identify and provide training and development for SA’s emergency management sector personnel (government agencies, and non-government agencies including volunteers). State Emergency Management Committee should consider supporting recommendations from stage two of the project when the project report is tabled. |
REC295-1303 | 16 - Training and behaviour | That the State Emergency Service be provided with resources to enable them to deliver swiftwater awareness training to all first responders including emergency services, SA Police and council crews. |
REC295-1284 | 16 - Training and behaviour | Deliver consistent and regular training in the use of the SA Government Radio Network to all users to maximise the efficiency and effectiveness of the network in times of emergency e.g. reduce the issues associated with network busy signals. |
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2542 | 16 - Training and behaviour | The Civil Aviation Safety Authority publishes and demonstrates the philosophy of ‘just culture’ whereby individuals involved in a reportable event are not punished for actions, omissions or decisions taken by them that are commensurate with their experience and training. However, actions of gross negligence, wilful violations and destructive acts should not be tolerated. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
REC258-2541 | 16 - Training and behaviour | The Civil Aviation Safety Authority finalises its Capability Framework and overhauls its training program to ensure identified areas of need are addressed, including: |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2534 | 16 - Training and behaviour | The Civil Aviation Safety Authority develops a staff exchange program with industry. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2913 | 21 - Role of Commonwealth Government | In developing and improving its policies and practices for stakeholder engagement, NOPSA should ensure that: |
REC189-2910 | 21 - Role of Commonwealth Government | NOPSA should: |
REC189-2908 | 21 - Role of Commonwealth Government | To ensure that NOPSEMA is in a strong position to perform its functions effectively: |
REC189-2906 | 21 - Role of Commonwealth Government | In order to improve the effectiveness of National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA), with similar benefits for State or Territory regulators, attention should be given to the following actions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3290 | 38 - Agency/Department Reporting | The successful installation of every barrier should be the subject of written verification within and between licensees and rig operators; and should be the subject of explicit reporting to the relevant regulator(s). |
REC177-3357 | 21 - Role of Commonwealth Government | In any future similar blowout or offshore emergency situation, the Minister appoint (through either a NOPR or the relevant Department) a senior public servant to establish and oversight a central coordinating body that will facilitate interaction between regulators, industry, AMSA and the owner/operator. Primary responsibility for stopping a blowout should remain with the owner/operator but should be subject to direction from the central coordinating body in consultation with stakeholders (including the owner/operator). |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
REC177-3346 | 21 - Role of Commonwealth Government | A single, independent regulatory body should be created, looking after safety as a primary objective, well integrity and environmental approvals. Industry policy and resource development and promotion activities should reside in government departments and not with the regulatory agency. The regulatory agency should be empowered (if that is necessary) to pass relevant petroleum information to government departments to assist them to perform the policy roles. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3372 | 21 - Role of Commonwealth Government | OSCPs should be endorsed by AMSA prior to regulatory approval to ensure that they align with the National Plan. Once field operations commence, the capability of operators should be assessed against their plans, and exercises conducted to ensure the plans remain effective. |
REC177-3345 | 2 - Emergency powers | NOPSA’s prohibition powers should be extended such that a prohibition notice can be issued where a NOPSA Occupational Health and Safety Inspector believes, on reasonable grounds, that an activity is occurring or may occur at a facility involving an immediate threat to the health or safety of a person. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3287 | 38 - Agency/Department Reporting | Licensees should be subject to an express obligation to inform regulators of problems which arise in the course of installing barriers, even if they consider that well integrity is not thereby compromised. The information should be provided by way of special report, rather than included in a standard reporting document (such as a DDR). The information provided should include risk assessment details. |
REC177-3351 | 21 - Role of Commonwealth Government | In the future, and in the interests of ensuring that all possible well control options are comprehensively pursued to exhaustion, decisions as to well control response options should be the result of collaboration between the regulator and the operator rather than leaving one party to make unilateral judgements as to the appropriateness of various well control operations. The regulator should provide transparent and contemporaneous explanations to the public of all well control options under consideration at any particular time. |
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
REC177-3371 | 21 - Role of Commonwealth Government | The Government should examine the scope for a single environment plan to meet the regulatory requirements of both the OPGGS Act and the EPBC Act. This could possibly be achieved by way of bilateral agreements and accreditation arrangements and/or legislative amendment. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3349 | 21 - Role of Commonwealth Government | In the meantime, the Minister should: |
REC177-3304 | 26 - Research | It is recommended that industry, regulators, and training/research institutions liaise with one another with a view to developing better techniques for testing and verifying the integrity of cemented casing shoes as barriers (particularly in atypical situations such as where the casing shoe is located within a reservoir in a horizontal or high angle position at great depth). |
REC177-3360 | 42 - Culture and Heritage | DEWHA should participate in training programs and exercises relevant to an oil spill in the marine environment. |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3376 | 21 - Role of Commonwealth Government | In carrying out a review of PTTEPAA’s permit and licence, the Minister should have regard to this Report, particularly (i) the adverse findings set out in this Chapter; and (ii) the extent to which PTTEPAA has implemented the Action Plan submitted to the Inquiry, or otherwise addressed the matters canvassed in this Report. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3348 | 21 - Role of Commonwealth Government | Responsibility for well integrity should be moved to NOPSA (as also proposed by the Productivity Commission). |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3358 | 21 - Role of Commonwealth Government | The body established to undertake a central coordination and facilitation role in the event of any future blowout in Commonwealth waters should undertake to make all relevant information publically available from one, authoritative and easy to access source. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3375 | 21 - Role of Commonwealth Government | For the purposes of that review, the Minister should issue a ‘show cause’ notice to PTTEPAA under s 276 of the OPGGS Act. |
REC177-3347 | 21 - Role of Commonwealth Government | The proposal of the Productivity Commission’s Research Report (Review of Regulatory Burden on the Upstream Petroleum (Oil and Gas) Sector, April 2009) to establish a NOPR should be pursued at a minimum. |
REC177-3274 | 21 - Role of Commonwealth Government | The Minister should appoint a senior policy adviser to investigate and report on the best means to implement the recommendations contained in this Chapter 3 of this report. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3138 | 38 - Agency/Department Reporting | The current KPI measures used by the Regulator and industry need to be reassessed and the performance indicators need to be related to the risk profiles of the industry. The industry needs to develop the indicators, which need to be agreed and measured by the industry in discussion with other stakeholders. The KPI's selected should be published in comparison with the worldwide offshore industry and with other industries. NOPSA should continue discussions with Australian Safety and Compensation Council (ASCC) with a view to adopting their goals. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3137 | 16 - Training and behaviour | As professional competency is one of the key pillars of any Safety Case, commitment to training for current and future needs remains a fundamental requirement for achieving best practice outcomes in safety. Industry should be encouraged to build on its training commitment now being made to achieve a competent and fully accredited workforce over the next five years. |
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3136 | 16 - Training and behaviour | There is a need for industry in consultation with NOPSA to establish a priority programme of accredited education modules in the Safety Case regime targeting stakeholders in the regime at their respective levels to improve the understanding of the Safety Case and correspondent responsibilities. |
REC149-3143 | 21 - Role of Commonwealth Government | The role of the advisory Board, namely to give advice to Ministers and NOPSA when asked, should be made clear to Board members and all stakeholders. The Board and NOPSA should consider the need for a clear description of who does what based on the legislated responsibilities of the NOPSA CEO. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3669 | 16 - Training and behaviour | All operational rail staff should be trained by RailCorp in the action check list relevant to each. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3677 | 16 - Training and behaviour | A training centre for emergency services personnel should be established by RailCorp. The emergency services personnel should be required to undertake training at such a centre, which should be equipped with features replicating railway infrastructure and rolling stock. |
REC121-3715 | 16 - Training and behaviour | RailCorp should use its simulators to train drivers and guards in methods of dealing with degraded operations on the rail network. |
REC121-3751 | 16 - Training and behaviour | RailCorp should make it a condition of employment that all level 2 managers have or obtain a formal qualification in system safety management. |
REC121-3650 | 16 - Training and behaviour | Staff at the Rail Management Centre (RMC) should receive training from RailCorp to enable them to quickly and accurately assess that an emergency has occurred and to provide precise and reliable information to emergency response personnel about the location of the emergency, the available access to the site and the resources necessary. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3725 | 13 - Mapping and data quality | The data and information management system should be compatible with any data and information management system established by the ATSB for the designated interstate rail network, provided that the establishment of a compatible system does not reduce the amount or quality of the information obtained by ITSRR below the optimum levels which it needs to conduct trend analysis, and otherwise properly manage the safety of rail operations in New South Wales. |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
REC121-3675 | 16 - Training and behaviour | All rail employees should be trained by their employer to commence any emergency communication with the words “Emergency, emergency, emergency”, thereafter to identify themselves, the train, its location, what has occurred, the approximate passenger load and whether death or injuries have occurred. |
REC121-3714 | 16 - Training and behaviour | RailCorp should use its simulators in an interactive manner. |
REC121-3746 | 16 - Training and behaviour | All emergency services personnel should be trained in the location and operation of emergency door release mechanisms on all rail cars. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3719 | 16 - Training and behaviour | The position of team leader should be created by RailCorp to be responsible for a group of approximately 30 train drivers, with responsibility to ensure that each train driver’s training needs are being met and that any safety concerns of train drivers are being properly addressed. The team leaders are to have direct access to the Chief Executive of RailCorp if any safety concerns they have are not addressed. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |
REC121-3724 | 13 - Mapping and data quality | The ITSRR should establish a data and information management system, containing all data and information that it requires, to continually monitor the safety of the New South Wales rail system. |
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3744 | 16 - Training and behaviour | All RailCorp operational personnel should be trained in the location and operation of external emergency door release mechanisms. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3718 | 16 - Training and behaviour | Training should be based upon a needs analysis, to determine what skills a particular person will require to carry out the tasks of any position safely and efficiently, and instruction and practice, to acquire and demonstrate those skills. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3654 | 16 - Training and behaviour | All train guards should be trained by RailCorp in the use of the Metronet radio and instructed to use it in any emergency. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3672 | 16 - Training and behaviour | All emergency response personnel should be specifically trained in the features of railways which are relevant to their work, such as the location and means of operation of all emergency door releases on trains, the location and use of signal telephones, the methods by which electrical power can be isolated and the means by which they can readily identify and obtain information from the on-site rail commander. |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3717 | 16 - Training and behaviour | RailCorp must establish a task analysis for particular categories of employees, to identify the specific skills and responsibility of those employees or groups of employees, and thereafter undertake a training needs analysis, to develop the skills required in particular areas. |
REC121-3756 | 16 - Training and behaviour | RailCorp should ensure that where the safety competency of any manager is deficient such manager is required to undertake professional development courses to raise his or her safety competency level to an adequate standard. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3670 | 16 - Training and behaviour | The RailCorp emergency response plan should be provided to all emergency response agencies. The officers of each emergency service should be trained in any rail specific features of the plan, so as to better ensure inter-agency co-ordination in the circumstances of an emergency. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3716 | 16 - Training and behaviour | Train driver and guard training should encourage teamwork and discourage authority gradients. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |