INQ-ref | REC-UID | CODE | SubCode | SrcNUM | Recommendation |
---|---|---|---|---|---|
INQ296 | REC296-1349 | B - Preparedness | 10 - Infrastructure | Recommendation 1 | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
INQ296 | REC296-1362 | B - Preparedness | 10 - Infrastructure | Recommendation 14 | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
INQ296 | REC296-1361 | B - Preparedness | 10 - Infrastructure | Recommendation 13 | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
INQ296 | REC296-1360 | B - Preparedness | 10 - Infrastructure | Recommendation 12 | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
INQ296 | REC296-1359 | B - Preparedness | 10 - Infrastructure | Recommendation 11 | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
INQ296 | REC296-1358 | B - Preparedness | 10 - Infrastructure | Recommendation 10 | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. |
INQ296 | REC296-1357 | B - Preparedness | 10 - Infrastructure | Recommendation 9 | Monthly test results need to be accurately recorded. |
INQ296 | REC296-1356 | B - Preparedness | 10 - Infrastructure | Recommendation 8 | Accurate records need to be provided as to what is done for each service. |
INQ296 | REC296-1355 | B - Preparedness | 10 - Infrastructure | Recommendation 7 | Replacement of all original pipes and hoses not yet done. |
INQ296 | REC296-1354 | B - Preparedness | 10 - Infrastructure | Recommendation 6 | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
INQ296 | REC296-1353 | B - Preparedness | 10 - Infrastructure | Recommendation 5 | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
INQ296 | REC296-1352 | B - Preparedness | 10 - Infrastructure | Recommendation 4 | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
INQ296 | REC296-1351 | B - Preparedness | 10 - Infrastructure | Recommendation 3 | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
INQ296 | REC296-1350 | B - Preparedness | 10 - Infrastructure | Recommendation 2 | Remove any loads that do not need to be on essential power. |
INQ296 | REC296-1363 | B - Preparedness | 10 - Infrastructure | Recommendation 15 | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expan |