REC309-2467 | 9 - Community education | Further work be undertaken to develop effective public flood risk messaging and community education materials that are easy to understand and tested with the community to ensure flood risk is understood. |
REC309-2476 | 11 - Evacuation and shelters | Energy Queensland and local groups consider establishing formal arrangements that embed measures that assist evacuation plans to increase levels of safety. |
REC309-2473 | 22 - Role of local Gvt | Councils, with the support of stakeholders, continue to develop and promote local disaster dashboards as the ‘point of truth’ for community information and messaging during disaster events. Greater use during recovery should be considered. |
REC309-2472 | 38 - Agency/Department Reporting | A single point of truth be established for accurately capturing and reporting on disaster management group activation levels for any given timeframe. |
REC309-2480 | 22 - Role of local Gvt | Councils should formalise arrangements with entities that have the skills, capability and capacity to effectively manage spontaneous volunteers. These should be documented and integrated into planning and exercising. |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
REC309-2470 | 11 - Evacuation and shelters | Evacuation centre plans be revised to better manage vulnerable persons, including the safe storage of medications and providing alternate arrangements for evacuees with additional needs. (e.g. evacuation centre for aged persons). |
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4003 | 35 - Business and Industry in relation to industry | Where gas exists, and no provisions are made for its constant removal, no shots should be fired, and, where permitted in a gassy mine, shots should be fired only by a man specially appointed, and at such hours when the miners are not within the mine. All shots should be tamped by stone well damped, and only copper or wooden tools should be employed. As far as possible the use of explosives should be discouraged, and skilful mining encouraged. Danger-boards should be placed further from the faces whence gas issues (say), where practicable, 50 yards. |
REC002-4012 | 38 - Agency/Department Reporting | Complete sets of daily-report books should be provided, and kept in the mine or office, to be overlooked by the Inspector during his periodical visits. |
REC002-4002 | 19 - Offences | Where safety-lamps are necessary - gas being present for (say) one month after being found in dangerous quantity - they should be securely locked by a man duly appointed, and tampering with them must be punishable by a simple and inexpensive process of law. |
REC002-4010 | 35 - Business and Industry in relation to industry | The Commission do not approve of removing any responsibility from the management by increasing the power or number of the Inspectors. The visits of these officials should, so far as possible, be visits of surprise. |
REC002-4001 | 35 - Business and Industry in relation to industry | The Commission consider that in all mines where gas exists the course of the air should be directed to sweep along the working-faces; in mines worked by Pillar and Stall, bratticing must be resorted to to carry the gas from the face as it issues, and so prevent any accumulation of explosive gases or of gases inimical to life. In cases where gas exists it would be better that no bords should be broken off the back or return heading or supplied with air fouled by dangerous gases. The panel system of working by confining and localising districts, or some modification thereof, might be pursued with advantage. |
REC002-4008 | 35 - Business and Industry in relation to industry | Where dust exists in quantity, and under conditions favourable for ignition, it should be periodically and sufficiently dampened by water |
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
REC002-4004 | 35 - Business and Industry in relation to industry | Where safety-lamps are used, and the obligation is laid upon the men to cleanse the same, all examinations, tests, and repairs to these should be done by the owners. |
REC002-4013 | 19 - Offences | Infringement of the regulations by either party should be followed by a summary form of justice, instituted before two Magistrates. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1203 | 22 - Role of local Gvt | Impact Assessment Data Sharing The Office of Emergency Management: · with the SEOCON, jointly provides further guidance to Regional Emergency Management Officers about their role in facilitating local council access to the Impact Assessment Data Base · with REMOs and the SEOCON jointly provides further information to local councils about Impact Assessment Data Sharing Arrangements and the data available through this mechanism · includes information about the Impact Assessment Data Sharing Arrangements in the Local Recovery Toolkit · develops a mechanism to allow local councils to have direct access to the collated impact data. |
REC281-1201 | 25 - Inquiry, audit, lessons management and after action review | Preventing Flood Related Fatalities: The NSW Government consider the recommendations from the Preventing Flood Related Fatalities Report when it is released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1420 | 24 - Govt responsibility | The Department of Housing and Public Works should consider preparing an annual communique to asset owners of, and local governments with access to public cyclone shelters, outlining the maintenance and certification process and pre-season status. |
REC272-1419 | 22 - Role of local Gvt | Opportunities should be identified through the Local Government Association of Queensland council to council arrangement to share structural engineers to assess potential places of refuge against the Department of Housing and Public Works’ structure classification criteria. |
REC272-1418 | 24 - Govt responsibility | A state-wide engagement strategy is coordinated to ensure community messaging is consistent across all levels of Queensland’s disaster management arrangements. |
REC272-1416 | 24 - Govt responsibility | A state-wide strategy, including a common definition, is developed for identifying and engaging vulnerable people in emergencies. |
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1151 | 24 - Govt responsibility | Government Communications Coordination |
REC267-1150 | 9 - Community education | Media Engagement Consideration should be given on future recovery operations to adopting a more structured approach to media engagement, with regular media briefings undertaken at a frequency dependent upon the phase of the recovery activities and the level of media interest. These briefings could be conducted at different locations around the region, if appropriate, and would provide the opportunity for communication of key messages and provide journalists with the opportunity to ask questions regarding the recovery. This could be complemented by media coverage of community engagement visits. For all recovery operations, |
REC267-1159 | 9 - Community education | Improving Community Preparedness and Resilience |
REC267-1158 | 28 - Personal responsibility | Farm Management Deposits |
REC267-1157 | 35 - Business and Industry in relation to industry | Improvements to the Targeting of Government Support to Build Primary Industry Resilience |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0527 | 35 - Business and Industry in relation to industry | That the Office of Environment and Heritage require Orica to engage and fund appropriate independent experts to oversee any modifications to the plant in the next major maintenance overhaul of the plant in 2016 and in any upgrades to the plant prior to that date. |
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
Rec-ID | Code | Recommendation |
---|---|---|
REC137-3533 | 21 - Role of Commonwealth Government | Accordingly I recommend that the Federal Minister for Transport, consider engaging an external consultant to assess whether high level intervention is warranted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |