Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC319-4190 | 11 - Evacuation and shelters | Humanitarian relief: The Inspector-General for Emergency Management recommends that the Department of Jobs, Precincts and Regions work with the Municipal Association of Victoria and councils to build contingencies into emergency relief centre planning to ensure places of shelter are inclusive, recognise diversity and are better placed to support all displaced people in circumstances of: |
Rec-ID | Code | Recommendation |
---|---|---|
REC318-4175 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that the Department of Environment, Land, Water and Planning (or the single entity referenced in Recommendation 4) – supported by other organisations with a legislated responsibility for fuel management – plan for and increase the application of non-burning fuel management treatments including mechanical means. The annual fuel management report should include the non-burn component of fuel management treatment, track annual change, and provide a comparison to the previous three years. |
REC318-4170 | 4 - Fire season preparation | The Inspector-General for Emergency Management recommends that responder agencies and Emergency Management Victoria review preparedness arrangements to ensure procedural documentation (including plans), recruitment, briefings and training are completed before significant seasonal events are likely to occur. Seasonal preparedness should culminate in attestations of assurance to confirm that: |
REC318-4180 | 11 - Evacuation and shelters | The Inspector-General for Emergency Management recommends that Victoria Police – in collaboration with the community and the emergency management sector – reflect on events of the 2019–20 fire season to review and enhance evacuation plans and processes with consideration of: |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-2015 | 1 - Land-use and building regs | Build flood capable infrastructure. |
REC286-2061 | 41 - Emergency Management exercises | Review and exercise the Tasmanian Mass Vaccination Plan. |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2087 | 41 - Emergency Management exercises | Develop and exercise Severe Storm Emergency Management Plan. |
REC286-1441 | 5 - Hazard reduction burns | Continue the Fuel Reduction Program. |
REC286-1472 | 11 - Evacuation and shelters | Develop flood evacuation plans for at risk communities. |
REC286-2044 | 1 - Land-use and building regs | Develop linkages between landslide risk assessors and building engineers/structural works. |
REC286-1451 | 1 - Land-use and building regs | Include consideration of coastal inundation in land use planning for new developments and uses. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-2026 | 11 - Evacuation and shelters | Identify facilities that can be used as cool spaces during heatwaves and establish linkages between operators and emergency management organisations |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1436 | 4 - Fire season preparation | Continue the development and implementation of community level Bushfire Mitigation Plans. |
REC286-1471 | 1 - Land-use and building regs | Promote the use of Water Sensitive Urban Design in stormwater systems. |
REC286-2040 | 1 - Land-use and building regs | Further development of Landslide Hazard Banding of the State (MRT). |
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-2051 | 1 - Land-use and building regs | Establish arrangements to enable the buy-back of specified landslip prone land. |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-2025 | 41 - Emergency Management exercises | Exercise heatwave arrangements with a focus on the public administration sector and management of vulnerable people |
REC286-2082 | 41 - Emergency Management exercises | Undertake inter-agency severe storm exercises. |
REC286-1435 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning and Building System reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-2039 | 41 - Emergency Management exercises | Nuance the exercises for flood / dam-break / debris flow to incorporate consideration. |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-2050 | 1 - Land-use and building regs | Ensure landuse planning and building systems, including appeal mechanisms, are transparent, equitable and integrated at the municipal, State and national levels. |
REC286-1454 | 11 - Evacuation and shelters | Review coastal inundation evacuation and response plans. |
REC286-2023 | 1 - Land-use and building regs | Locate and design new public infrastructure so that it can continue to operate during flood events. |
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2038 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-1453 | 1 - Land-use and building regs | Review building controls to ensure they are adaptive to changing coastal inundation risks. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
REC286-1464 | 41 - Emergency Management exercises | Exercise time-critical decision making processes within the context of an earthquake scenario. |
REC286-2037 | 1 - Land-use and building regs | Make property level information on landslide hazards publicly available |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-1445 | 41 - Emergency Management exercises | Develop, implement, review and exercise inter-agency community evacuation and recovery plans across the State. |
REC286-1474 | 1 - Land-use and building regs | Raised access routes. |
REC286-2046 | 1 - Land-use and building regs | Incentivising safer sites (charge people less rates and discounts for defensive actions by land managers). |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1877 | 39 - Disaster Risk Management | Regulators can help to achieve improved outcomes by considering the issues identified by this review |
REC215-1876 | 39 - Disaster Risk Management | Fire services can improve outcomes by initiating discussions with landfill operators about fire management planning and emphasising the critical importance of water supplies and early intervention |
REC215-1875 | 1 - Land-use and building regs | Fire services can improve outcomes by seeking input to decisions about siting, design and fire water systems as part of the planning and licensing processes |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0334 | 4 - Fire season preparation | The Fire Services Commissioner leads a task force to: a. identify legislation, policies and guidelines that impact on vegetation management and recommend necessary changes b. develop a set of risk-based standards for vegetation management with respect to strategic firebreaks and the assets being protected c. integrate maintenance standards across all areas of responsibility and tenure. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0197 | 1 - Land-use and building regs | Standards Australia do the following: ■ amend the objective of AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, to ensure that it incorporates reducing the risk of ignition from ember attack; ■ review, and amend as appropriate, the testing methods prescribed in its standards for Tests on Elements of Construction for Buildings Exposed to Simulated Bushfire Attack (AS 1530.8.1 and AS 1530.8.2) to ensure that, so far as is possible, the methods provide a reliable predictor of the performance of construction elements under bushfire conditions. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0204 | 2 - Emergency powers | The State amend the Country Fire Authority Act 1958 to enable the Chief Officer to delegate the power to issue fire prevention notices. |
REC181-0188 | 1 - Land-use and building regs | The State implement a regional settlement policy that: ■ takes account of the management of bushfire risk, including that associated with small, undeveloped rural lots; ■ includes a process for responding to bushfire risk at the planning stage for new urban developments in regional cities, the process being similar to that used for new developments in Melbourne’s Urban Growth Zone. |
REC181-0211 | 4 - Fire season preparation | The State and Commonwealth provide for municipal councils adequate guidance on resolving the competing tensions arising from the legislation affecting roadside clearing and, where necessary, amend environment protection legislation to facilitate annual bushfire-prevention activities by the appropriate agencies. |
REC181-0196 | 1 - Land-use and building regs | The State develop and implement a retreat and resettlement strategy for existing developments in areas of unacceptably high bushfire risk, including a scheme for non-compulsory acquisition by the State of land in these areas. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0203 | 1 - Land-use and building regs | The State amend s. 32 of the Sale of Land Act 1962 to require that a vendor’s statement include whether the land is in a designated Bushfire-prone Area, a statement about the standard (if any) to which the dwelling was constructed, the bushfire attack level assessment at the time of construction (where relevant) and a current bushfire attack level assessment of the site of the dwelling. |
REC181-0210 | 4 - Fire season preparation | The State amend the exemptions in clause 52.17-6 of the Victoria Planning Provisions to ensure that the provisions allow for a broad range of roadside works capable of reducing fire risk and provide specifically for a new exemption where the purpose of the works is to reduce bushfire risk. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0192 | 4 - Fire season preparation | The Department of Sustainability and Environment develop and administer a collective offset solution for individual landholders who are permitted to remove native vegetation for the purpose of fire protection. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0200 | 1 - Land-use and building regs | Standards Australia move expeditiously to develop a standard for bushfire sprinklers and sprayers. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0207 | 5 - Hazard reduction burns | The Department of Sustainability and Environment report annually on prescribed burning outcomes in a manner that meets public accountability objectives, including publishing details of targets, area burnt, funds expended on the program, and impacts on biodiversity. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0191 | 1 - Land-use and building regs | The State: ■ amend the Victoria Planning Provisions to require that, when assessing a permit to remove native vegetation around an existing dwelling, the responsible authority and the Department of Sustainability and Environment, as referral authority, take into account fire hazard and give weight to fire protection purposes; ■ develop guidelines for determining the maximum level of native vegetation removal for bushfire risk mitigation, beyond which level the application would be rejected. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0199 | 1 - Land-use and building regs | The State modify its adoption of the Building Code of Australia for the following purposes: ■ to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ to apply bushfire construction provisions to non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities; ■ other than in exceptional circumstances, to apply a minimum AS 3959-2009 construction level of BAL-12.5 to all new buildings and extensions in bushfire-prone areas. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0206 | 5 - Hazard reduction burns | The State fund and commit to implementing a long-term program of prescribed burning based on an annual rolling target of 5 per cent minimum of public land. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0190 | 1 - Land-use and building regs | The Country Fire Authority amend its guidelines for assessing permit applications for dwellings, nondwellings and subdivisions in the Bushfire-prone Overlay in order to accommodate the amendments to the Wildfire Management Overlay that are implemented as a result of recommendation 39 and make the guidelines available to municipal councils and the public. The revised guidelines should do the following: ■ substantially restrict new developments and subdivisions in those areas of highest risk in the Bushfire-prone Overlay; ■ set out the CFA’s guidelines for assessing permit applications for dwellings, non-dwellings and subdivisions—including the minimum defendable space requirements for different risk levels; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ clarify that the CFA will approve new developments and subdivisions only if the recommended bushfire protection measures—including the minimum defendable space—can be created and maintained on a continuing basis; ■ emphasise the need for enduring permit conditions—in particular, conditions for the creation and maintenance of minimum defendable space to be maintained for the life of the development. |
REC181-0198 | 1 - Land-use and building regs | The Australian Building Codes Board do the following: ■ amend the performance requirements in the Building Code of Australia to ensure that they incorporate reducing the risk of ignition from ember attack; ■ work with Standards Australia to effect expeditious continuing review and development of AS 3959, Construction of Buildings in Bushfire-prone Areas, and other bushfire-related standards referred to in the Building Code of Australia; ■ negotiate with Standards Australia and SAI Global Ltd an arrangement for free online access to AS 3959-2009, Construction of Buildings in Bushfire-prone Areas, the other Australian standards referred to in AS 3959-2009, and any other bushfire-related Australian standards referred to in the Building Code of Australia; ■ amend the Building Code of Australia to remove deemed-to-satisfy provisions for the construction of buildings in BAL-FZ (the Flame Zone); ■ include in the Building Code of Australia bushfire construction provisions for non-residential buildings that will be occupied by people who are particularly vulnerable to bushfire attack, such as schools, child care centres, hospitals and aged care facilities. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0205 | 1 - Land-use and building regs | The State initiate the development of education and training options to improve understanding of bushfire risk management in the building and planning regimes by: ■ providing regular training and guidance material to planning and building practitioners; ■ providing regular training and guidance material to planning and building practitioners. |
REC181-0189 | 1 - Land-use and building regs | The State amend the Victoria Planning Provisions relating to bushfire to ensure that the provisions give priority to the protection of human life, adopt a clear objective of substantially restricting development in the areas of highest bushfire risk—giving due consideration to biodiversity conservation—and provide clear guidance for decision makers. The amendments should take account of the conclusions reached by the Commission and do the following: ■ outline the State’s objectives for managing bushfire risk through land-use planning in an amended state planning policy for bushfire, as set out in clause 15.07 of the Victoria Planning Provisions; ■ allow municipal councils to include a minimum lot size for use of land for a dwelling, both with and without a permit, in a schedule to each of the Rural Living Zone, Green Wedge Zone, Green Wedge A Zone, Rural Conservation Zone, Farming Zone and Rural Activity Zone; ■ amend clause 44.06 of the Victoria Planning Provisions to provide a comprehensive Bushfire-prone Overlay provision. |
REC181-0212 | 4 - Fire season preparation | VicRoads implement a systematic statewide program of bushfire risk assessment for all roads for which it is responsible, to ensure conformity with the obligations in s. 43 of the Country Fire Authority Act 1958 and with the objectives expressed in the VicRoads 1985 Code of Practice. |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3885 | 5 - Hazard reduction burns | Align policies and processes, within the year round 365 day focus on fire management, to provide consistency in the approach to fire regardless of its origins,- that is fuel reduction burning, regeneration and ecological burning or unplanned fire; |
REC124-3884 | 5 - Hazard reduction burns | Develop new prescriptions for prescribed burning to accommodate local conditions in those areas where standard prescriptions are assessed to be inappropriate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3882 | 41 - Emergency Management exercises | The Office of the Emergency Services Commissioner convene a working group of key emergency services and emergency management agencies to develop a flow chart based on scenario testing, to support decision making and the assessment of response requirements to medical, hazardous materials and CBR emergencies including their transition from one type to another. |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2335 | 41 - Emergency Management exercises | That the fire agencies develop a program to significantly increase the amount of joint training and exercises undertaken. |
REC104-2220 | 2 - Emergency powers | That CFA should not be given the power to direct Forest Industry Brigades to engage in fire prevention and suppression activities off their land and that decision should remain the responsibility of the plantation company. |
REC104-2325 | 39 - Disaster Risk Management | That CFA, DSE and MFESB continue to develop the partnership approach for fire safety with Local Government, industry and communities. |
REC104-2203 | 11 - Evacuation and shelters | That CFA further develops the information supporting the decision to stay or go, to incorporate a better understanding of both the likely consequences of leaving home at inappropriate times, and the conditions and |
REC104-2317 | 39 - Disaster Risk Management | That DSE, with adequate resourcing, moves to a 12-month cycle of fire management to establish and maintain a more appropriate and balanced work program of prevention/mitigation and suppression. |
REC104-2189 | 39 - Disaster Risk Management | That DSE and CFA as part of their long term planning, and in conjunction with the Commonwealth Bureau of Meteorology, consider ways in which evidence for climate change and El Niño–Southern Oscillation cycle impacts on the likelihood of unplanned fire, can be better incorporated into preparedness and response planning. |
REC104-2251 | 11 - Evacuation and shelters | That Victoria Police ensure all police members understand the Victorian legislation in relation to evacuation, and that any decision to recommend evacuation remains with the Incident Controller. |
REC104-2250 | 41 - Emergency Management exercises | That DSE and CFA work in cooperation with the Municipal Emergency Response Coordinators to develop and conduct joint exercises that practise the skills and test procedures for operations of the Municipal Emergency Coordination Centre, Municipal Recovery Centre and Incident Control Centres. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3952 | 4 - Fire season preparation | It is recommended that the question of the future responsibility be made certain and that the body so made responsible keep the grounds of the hospital free from undergrowth and trees wherever their presence may be a possible source of future danger. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3950 | 4 - Fire season preparation | It is recommended that on days of abnormal danger loads of briquettes be not kept in the station yard. The real danger, which transcends in gravity the danger of time destruction of loads of briquettes, is that the prevailing wind or a change of wind might carry showers of burning embers to the town, which is but the width of a road away, and thereby cause material damage in the town. It is further recommended that the yard and its surroundings be kept clear of scrub and growth; and that special provision be made for quelling fire which may break out in the deposits of inflammable dust which lie in time yard. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |