Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC316-4024 | 32 - Doctrine, standards, and reform | The Government consider amendments to the Emergencies Act to include provision for a Deputy ESA Commissioner. |
REC316-4035 | 32 - Doctrine, standards, and reform | Review, refine and implement the joint ESA/EPSDD Arrangement for Fire Management in the ACT with the previous recommendation in mind. |
REC316-4050 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the provision for a Deputy Emergency Controller to be appointed, independent of the initial appointment of an EC. The powers and functions of this appointment to be contingent on the absence of the EC. |
REC316-4022 | 12 - EM agency and authority | That when determining their Management Executive, at a minimum the EC should consider appointing Director-General JACS and the PIC as standing members. |
REC316-4031 | 12 - EM agency and authority | The ESA hold bi-lateral executive level meetings with the utility providers on a regular basis in consultation with other relevant Government stakeholders. |
REC316-4049 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended to allow for the appointment of the EC to be made for a discretionary time period of up to 28 days with the requirement for a legislated review of the appointment to be removed. Alternatively, a period of review should fall within the Chief Ministers discretion for up to seven (7) days following appointment. |
REC316-4021 | 32 - Doctrine, standards, and reform | The Emergency Plan be amended to better reflect the intent of the Emergencies Act in the establishment of a Management Executive, separate to SEMSOG, on the appointment of an EC. It should describe the role of SEMSOG and the Management Executive as distinct in the emergency management architecture. |
REC316-4027 | 12 - EM agency and authority | All organisations who have a role in the ECC should review their existing arrangements to ensure there is a sufficient cohort of staff to maintain a presence in the ECC at a level and with an imprimatur sufficient to make decisions and allocate resources and have access to senior executive levels if needed. |
REC316-4044 | 11 - Evacuation and shelters | A Relocation and Evacuation working group be established from stakeholder organisations to consider and develop an Evacuation and Relocations Sub- Plan. The Sub-Plan should consider the lessons learned this year and address principles, lead agency, WHoG coordination, trigger points etc. This could be the same working group formed for reviewing the Emergencies Act, Plan and sub-plans. |
REC316-4016 | 12 - EM agency and authority | That the Emergency Plan be amended to include considerations for declaring a State of Alert or Emergency (and also wind back from these) and guidance as to what actions and decisions at a minimum should be taken as a consequence of such a declaration. |
REC316-4026 | 12 - EM agency and authority | The role, level, requirements and expectations of an ECC LO be clarified in the Emergency Plan and ECC Ops Sub-plan. |
REC316-4039 | 12 - EM agency and authority | Establish a Communications Working Group (CWG) with representatives from across key Directorates (CMTEDD, ESA, ACT Policing, Health, CHS, EPSDD for example) to review the CCIP and to further identify how the CCIP can be best implemented and utilised. The CWG should report its progress though SEMSOG and coordinate with other WG’s. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4052 | 32 - Doctrine, standards, and reform | The ACT Emergencies Act 2004 be amended to clarify that the powers of the EC encompass the power to direct agencies and directorates to share personal information for the preservation of life and protection of Canberrans. |
REC316-4015 | 12 - EM agency and authority | The working group should report to SEMSOG on progress. |
REC316-4025 | 32 - Doctrine, standards, and reform | The Emergency Plan and ECC Ops Plan be amended to better articulate the delivery of emergency management vs the delivery of the emergency plan. The Plan should facilitate principles for emergency management and clear role delineations whilst allowing flexibility in how the mechanisms are structured. |
REC316-4036 | 12 - EM agency and authority | Government give consideration to investment in professional specialities such as fire behaviour analysts, airbase managers, aerial firefighting technical specialists etc for the RFS. |
REC316-4051 | 32 - Doctrine, standards, and reform | The Emergencies Act 2004 be amended so that the powers, including delegations, available to an EC be granted on their appointment and remain in place under the same section of the Act for the duration of their appointment rather than being drawn from different sections of the Act that are dependent on the existing alert state for the specified event. |
Rec-ID | Code | Recommendation |
---|---|---|
REC286-1472 | 11 - Evacuation and shelters | Develop flood evacuation plans for at risk communities. |
REC286-2068 | 24 - Govt responsibility | Develop a disaster client record system. |
REC286-2026 | 11 - Evacuation and shelters | Identify facilities that can be used as cool spaces during heatwaves and establish linkages between operators and emergency management organisations |
REC286-2058 | 24 - Govt responsibility | Clarify the relationship between the DHHS and THS in the establishment of flu services. |
REC286-1470 | 32 - Doctrine, standards, and reform | Integrate Storage Operating Rules with downstream flood response plans. |
REC286-2067 | 24 - Govt responsibility | Improve integration of health information systems. |
REC286-2022 | 12 - EM agency and authority | Increase SES Capability and Capacity to respond to flood event. |
REC286-2096 | 32 - Doctrine, standards, and reform | Review current all-hazards emergency management arrangements to evaluate if they adequately address Tsunami response and recovery requirements. |
REC286-2042 | 32 - Doctrine, standards, and reform | Increased regulation of landslide risk assessment. |
REC286-1462 | 32 - Doctrine, standards, and reform | Develop a strategic plan for the operation and management of the seismic monitoring network in Tasmania. |
REC286-2063 | 24 - Govt responsibility | Review Tas Govt interoperability arrangements. |
REC286-2019 | 24 - Govt responsibility | Assess water supply resilience in the case of an interruption. |
REC286-2086 | 32 - Doctrine, standards, and reform | Develop SOP for recovery package. |
REC286-2033 | 24 - Govt responsibility | Incorporate heatwave surge response planning into business continuity planning. |
REC286-1454 | 11 - Evacuation and shelters | Review coastal inundation evacuation and response plans. |
REC286-2062 | 32 - Doctrine, standards, and reform | Review State Special Emergency Plan: Human Influenza Pandemic Emergencies. |
REC286-2018 | 12 - EM agency and authority | Review flood response sustainment capacity of organisations. |
REC286-2080 | 32 - Doctrine, standards, and reform | Formalise response triage arrangements. |
REC286-2030 | 32 - Doctrine, standards, and reform | Develop innovative response models of patient care to improve surge capacity. |
REC286-2060 | 32 - Doctrine, standards, and reform | Develop a flexible plan for establishing flu-specific services. |
REC286-1481 | 32 - Doctrine, standards, and reform | Integrate clean-up arrangements into emergency plans. |
REC286-2069 | 24 - Govt responsibility | Implement a database management approach for notifiable disease record systems. |
REC286-2029 | 32 - Doctrine, standards, and reform | Create a stakeholder plan template to aid heatwave preparedness and response in facilities occupied by people vulnerable to heatwaves (e.g. nursing homes) |
REC286-2059 | 24 - Govt responsibility | Enhance business continuity planning by the Tasmanian Health Service. |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3000 | 32 - Doctrine, standards, and reform | That the Tasmania Fire Service establish clear systems and protocols for dealing with fires. |
REC166-3005 | 32 - Doctrine, standards, and reform | That the Coroner prepare a discussion paper and draft guidelines for the clarification of investigative roles of the Tasmania Police Service, the Tasmania Fire Service, and the Coroners Office for adoption in relation to future fires where a Coroner’s Inquest is established. |
REC166-3003 | 12 - EM agency and authority | That the Tasmania Fire Service provide additional training in power disconnection and improvements in communication between Tasmania Fire Service and Aurora: |
Rec-ID | Code | Recommendation |
---|---|---|
REC144-3380 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develop and publish an operational policy document which spells out the command and control structures and procedures should an emergency event arise. |
REC144-3388 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government re-investigate the suitability of the Fairbairn site as a proposed centralised accommodation facility for emergency services. |
REC144-3394 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government develops a joint strategic bushfire management plan with the NSW Government and the NSW Rural Fire Service in relation to those areas which have the potential to impact on both jurisdictions. |
REC144-3386 | 24 - Govt responsibility | The Committee considers that the ACT Government should table in the ACT Legislative Assembly the cost-benefit analysis and business plan for Fairbairn as a central site for emergency services in the ACT. |
REC144-3392 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government finalise Version 2 of the Strategic Bushfire Management Plan as required under the Emergencies Act. |
REC144-3383 | 32 - Doctrine, standards, and reform | The Committee recommends that, if the Bushfire Council is to have an advisory role generally in emergency management, it should be renamed to reflect a general emergency role rather than a role specifically in relation to bushfires. |
REC144-3391 | 32 - Doctrine, standards, and reform | The Committee recommends that the ACT Government explain its reasons to the Legislative Assembly for not proceeding with the release of Version 2 of the Strategic Bushfire Management Plan in July 2005. |
REC144-3382 | 24 - Govt responsibility | The Committee recommends that responsibility for oversighting the progress of the implementation of agreed recommendations of the Coroner be undertaken by a truly independent body and not by the Bushfire Council. |
REC144-3390 | 24 - Govt responsibility | If the ACT Government decides to proceed with the site as the emergency services headquarters, that it accord a high priority to the finalisation of the site preparations for the ESA at Fairbairn as a matter of urgency. |
REC144-3381 | 32 - Doctrine, standards, and reform | The Committee recommends that the Bushfire Council consultative requirements under the Emergencies Act 2004 be reviewed, with a view to removing the requirement to consult with the Bushfire Council on operational matters, such as staff appointments and matters prescribed by regulation. |
REC144-3389 | 24 - Govt responsibility | If the Auditor-General does not undertake a review in the near future, the Committee recommends that the ACT Government make a public announcement about the future accommodation plans for the Emergency Services Agency and its component parts so that both the ESA and the ACT public are informed about current proposals and timeframes. |
REC144-3400 | 12 - EM agency and authority | The Committee recommends that each element of the Emergency Services Agency publish organisation charts showing names, positions and contact details on the individual webpages. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1962 | 24 - Govt responsibility | That, because of the small jurisdiction of the ACT (equivalent to one fire district in NSW) the ACT Government consider all possible options for the provision of fire services to the ACT, among them: |
REC126-1966 | 32 - Doctrine, standards, and reform | That the Emergency Services Agency investigate and implement arrangements that will provide the capacity to use fire retardant in remote areas |
REC126-1944 | 32 - Doctrine, standards, and reform | That s. 59 of the ACT Coroners ACT 1997 be amended by deleting the words ‘by instrument’ in s. 59(1) and by deleting the words ‘by his or her instrument of appointment’ in s. 59(2)(b) |
REC126-1985 | 24 - Govt responsibility | That the Emergency Services Agency, with the suport of the ACT Government, seek to establish with the NSW Department of Environment and Conservation and the NSW Rural Fire Service a protocol that will provide for the establishment of a joint incident management team as part of unified control arrangements based on adoption of the following principles: |
REC126-1962 | 32 - Doctrine, standards, and reform | That version 2 of the Strategic Bushfire Management Plan be completed and introduced without delay |
REC126-2012 | 24 - Govt responsibility | If they are willing and available to participate, that the taskforce's membership include Mr Phil Cheney, Mr Tony Bartlett, Mr Val Jeffery and Mr John Lowe |
REC126-1965 | 32 - Doctrine, standards, and reform | That helicopters be used wherever possible to facilitate the rapid deployment of remote area firefighting crews |
REC126-1943 | 32 - Doctrine, standards, and reform | That the ACT’s Director of Public Prosecutions Act 1990 be amended by repealing s. 6(d) of the Act |
REC126-1984 | 24 - Govt responsibility | That the Emergency Services Agency, with the support of the ACT Government, develop a single, new memorandum of understanding with the NSW Department of Environment and Conservation and the NSW Rural Fire Service, providing for liaison and joint operations as soon as it becomes apparent to whichever jurisdiction is managing a fire that the fire will probably affect the other jurisdiction. Joint operations should not be limited to when an incident occurs on both sides of the border, as is the current arrangement |
REC126-1949 | 12 - EM agency and authority | That the Emergency Services Agency be relocated into accommodation that is purpose-built and more sited to the agency’s operations than the current facility at Curtin |
REC126-2009 | 24 - Govt responsibility | That a taskforce be established to give effect to the recommendations in this report |
REC126-1964 | 32 - Doctrine, standards, and reform | That remote area firefighting resources be deployed to a fire in a remote area as a matter of priority and in preference to the deployment of large tankers |
REC126-1942 | 24 - Govt responsibility | That the ACT Attorney-General and the ACT Government - in consulation with the Chief Justice of the ACT and the ACT Chief Magistrate - take legislative action that would have the effect of funds being directly appropriated annually to the courts, preferable along the lines of the Commonwealth model as it applies to the High Court of Australia, the Federal Court of Australia, the Family Court of Australia and the Federal Magistrates Court. Alternatively, the funds could be appropriated in accordance with the South Australian model, which has a seperate Courts Administartion Authority. |
REC126-1979 | 24 - Govt responsibility | That the policy and practice just recommended be the subject of a memorandum of understanding between the Emergency Services Agency and the Department of Territory and Municipal Services (previously the Department of Urban Services) or other relevant department or agency, so as to ensure that the land management agency on whose land a fire starts has responsibility to respond immediately to that fire in accordance with the applicable standards for weight of response. Further, the land management agency should be responsible for efforts to suppress fire until such time as it becomes clear that the suppression task is beyond capacity of the agency, at which point the ACT Rural Fire Service should assume direct responsibility for coordinating the ongoing response |
REC126-1948 | 24 - Govt responsibility | That the Emergency Services Agency be removed from the Department of Justice and Community Safety and transformed into an independent statutory authority reporting directly to the responsible Minister. Note in this regard that Mr McLeod made a similar recommendation, and I endorse it unequivocally. Placing the agency within a government department puts unnecessary layers of bureaucracy between the agency and the responsible Minister, and the bureaucrats concerned usually have no special knowledge of or experience in emergency management, regardless of their seniority in the bureaucracy |
REC126-2006 | 24 - Govt responsibility | I recommend that, as appropriate, the ACT cooperate with the Commonwealth in the implementation of the committee's recommendations and, in particular, give careful consideration to adoption of the following recommendations: |
REC126-1964 | 32 - Doctrine, standards, and reform | That all firefighting agencies adopt a policy and practice that all fires in remote areas of the ACT be responded to as quickly as possible, with vigorous and sustained efforts made to suppress the fires and not leave them unattended – especially at night – unless there are compelling reasons relating to firefighter safety or lack of resources |
REC126-1978 | 32 - Doctrine, standards, and reform | That it be a matter of policy and practice that the relevant land management agency is responsible for the initial response to any fire or fires on the land under its care or management – within the overall operational response of the ACT Rural Fire Service |
REC126-1946 | 32 - Doctrine, standards, and reform | That the ACT Government consider amending the Coroners Act 1997 to include what were ss. 56(1)(d) and 56(2)(c) of the 1956 Coroners Act |
REC126-1995 | 12 - EM agency and authority | That the Emergency Services Agency staff the Media Unit within its planning Section with profesisonal, experienced information officers skilled in dissemination of information and media management and liaison |
REC126-1963 | 12 - EM agency and authority | That priority be given to ensuring that the ACT has an adequate resource of remote area firefighting teams consisting of personnel with high levels of fitness and training in remote fire suppression |
REC126-1976 | 24 - Govt responsibility | That the Emergency Services Agency have authority over the land management agencies and other landholders in order to implement preparedness and prevention measures – including fuel-reduction works where there are failures in compliance |
REC126-1945 | 32 - Doctrine, standards, and reform | That s. 47 of the ACT Coroners Act 1997 be expanded to explicitly state that an inquest and the inquiry are not adversarial in nature and are solely inquisitorial, with a view to establishing the truth |
REC126-1989 | 32 - Doctrine, standards, and reform | That formal protocols be developed and agreed with NSW authorities, so that a concerted effort that combines the resources of both NSW and the ACT can be brought to bear in the future - without impediment caused by lines on a map that make the ACT an island within the state of NSW |