Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC286-2032 | 26 - Research | Quantify the effect of heatwaves on vulnerable people. |
REC286-2092 | 26 - Research | Investigate usefulness of satellite data for PPRR (prevention, preparedness, response, recovery) planning. |
REC286-2024 | 26 - Research | Improve knowledge and understanding of the effect heatwaves coinciding with other hazard events have on the effectiveness and capability of response and recovery capabilities |
REC286-1441 | 5 - Hazard reduction burns | Continue the Fuel Reduction Program. |
REC286-2090 | 26 - Research | Increase understanding of the Puysegur Trench dynamics to improve certainty around the likelihood and magnitude of future Tsunamis. |
REC286-2078 | 15 - Inter-service cooperation | Review interagency information sharing arrangements. |
REC286-1480 | 26 - Research | Deliver Flood Studies. |
REC286-2079 | 26 - Research | Develop capacity to utilise the new high-resolution satellite products now available. |
REC286-2014 | 15 - Inter-service cooperation | Integrate non-government entities into emergency response and recovery arrangements. |
REC286-1457 | 26 - Research | Improve understanding of how coastal inundation events interact with riverine flood events. |
REC286-2048 | 26 - Research | Conduct research into changes of owners’ and occupiers stated and revealed risk tolerance and preference for treatment measures before and after natural hazard events. |
REC286-1467 | 15 - Inter-service cooperation | Review the allocation of responsibilities for earthquake risk management. |
REC286-1456 | 26 - Research | Improve understanding of the weather systems that cause storm surge events to improve predictability and warnings. |
REC286-2045 | 26 - Research | Investigate the potential effectiveness of economic and financial mechanisms to manage the risk appetites of land owners. |
REC286-1465 | 15 - Inter-service cooperation | Improve the coordination and delivery of the National seismic monitoring program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-0994 | 5 - Hazard reduction burns | That the Rural Fire Service Queensland needs to provide greater emphasis and acknowledgement of the use of fire as a tool in sustainable land management. |
REC241-0973 | 17 - Assets and technology | That all land on which rural fire brigade sheds are located be re-evaluated to formalise enforceable lease agreements. |
REC241-1026 | 17 - Assets and technology | That the Rural Fire Service Queensland catalogue accurately reflects the range of equipment available. |
REC241-1004 | 15 - Inter-service cooperation | That a memorandum of understanding be developed between RFSQ and other organisations with fire fighting capacity at state level, to establish operational procedures when these organisations may be required for a joint response roles. Specifically, the intent will be: Vegetation Fire in a Rural Area: The Rural Fire Brigade in that area (boundary) is in charge and is the first Brigade called by Firecom. Structural Fire in a Rural Area: Firecom calls the Urban Brigade first and they control the incident. Local Rural Fire Brigade must also be notified by Firecom at the same time. Vegetation Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. At their discretion they may call Rural Fire Brigades for assistance. Structural Fire in an Urban Levy Area: Firecom call the local Urban Brigade first and they control the incident. |
REC241-1039 | 17 - Assets and technology | That the State Government supply and logistics for Personal Protective Equipment and other equipment be urgently reviewed with a focus on timely and cost effective delivery to volunteer members. |
REC241-0970 | 17 - Assets and technology | That RFSQ retain responsibility for Air Operations and re-evaluate avenues for cost recovery when aircraft are used by other agencies. The coordination of incendiary tasking to support mitigation should sit with the RFSQ in coordination with other agencies |
REC241-1025 | 17 - Assets and technology | That an ‘Options Paper’ be developed by District Inspectors on the suitability and supply of PPE and equipment to volunteers for their district. |
REC241-1036 | 17 - Assets and technology | That each District Inspector prepare a report on vehicles required over the next ten years based on current age of fleet. |
REC241-0997 | 5 - Hazard reduction burns | That the electronic fire permit system used in the Mackay District be made available across the state for Fire Wardens who wish to use it. |
REC241-1024 | 17 - Assets and technology | That the Rural Fire Service Queensland revoke its current 20 year maximum age policy on volunteer Brigade vehicles to allow Brigades wanting to retain their vehicle to do so, providing the vehicle has an annual mechanical certificate. A 30 year maximum age policy for vehicles will replace the 20 year policy. |
REC241-1029 | 17 - Assets and technology | That a policy be developed around the ownership, insurance and safe use and operation of All Terrain Vehicle 4WD vehicles by brigades for fire fighting purposes. |
REC241-0996 | 5 - Hazard reduction burns | That Section 66 (2) of the Fire and Rescue Service Act 1990 relating to the exemption for issuing of permits to burn in State Forests, National Parks and Reserves is withdrawn and Departments must work within the District Fire Management Plan. |
REC241-1012 | 17 - Assets and technology | Use of private aircraft to be at the discretion of District Inspector or Incident Control and reimbursement of fuel to be authorised accordingly. |
REC241-1028 | 17 - Assets and technology | That vehicles are fit for the purpose and the Brigade locality for which they are intended. A group of two volunteers, in conjunction with the Rural Fire Brigades Association Queensland, should be charged with reviewing current models and providing Recommendations on vehicle suitability. |
REC241-0995 | 5 - Hazard reduction burns | At the next reprint of the ‘Permit to Light Fire’ book, the requirement to notify neighbours when applying for a permit is reinstated to properly reflect the requirement under the Fire and Rescue Service Act 1990. |
REC241-1009 | 17 - Assets and technology | That the reflective livery on Rural Fire Service Queensland staff vehicles be kept to a minimum of a light bar and affixed Rural Fire Service Queensland logo. These vehicles are to be appropriate to the task and location. |
REC241-1027 | 17 - Assets and technology | That Rural Fire Service Queensland, in consultation with Primary Producer Brigade volunteers, redesign and reconfigure slip-on units to bring the total cost below the level required for asset registration. The redesign should allow for the foam system to be optional. |
REC241-1042 | 17 - Assets and technology | The issue of red and blue lights for RFSQ and SES vehicles be further pursued by the Department of Community Safety |
REC241-0967 | 26 - Research | That a Rural Fire Research and Investigation Team be established to coordinate and communicate fire research knowledge, including fire behaviour as well as coordinate fire investigations and complaints for the state. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4153 | 17 - Assets and technology | No opportunity be lost by the Forests Department to improve the efficiency of their fire fighting gangs, radio and other equipment in the light of the latest practical and scientific developments. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
REC019-4156 | 26 - Research | A fire control research advisory committee be formed to co-operate with the Forests Department in carrying out scientific research into fire control. |
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4151 | 26 - Research | The Forests Department carry out more research into both the technical and practical side of fire control as a necessary accompaniment to the expenditure of money on other forest works and that forest fire control officers be sent overseas at intervals to gain information regarding the latest developments in this work. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |