Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4307 | 9 - Community education | Flood education: That, to build disaster resilience in future generations as floods and other natural disasters are a fact of Australian life, the Department of Education should design, implement and deliver an evidence-based, targeted education campaign (like sun exposure) in schools (new disaster curriculum). |
REC324-4312 | 17 - Assets and technology | Impact to essential services: That, to minimise disruption to essential services, including outages which compromise basic communication coverage, and to ensure access to safe water supply and power during flood events, Government work directly or together with the Australian and other state governments and/or their relevant power and telecommunications regulatory, policy and market bodies to: |
REC324-4293 | 17 - Assets and technology | Essential services and floodplain infrastructure: That, to minimise disruption to essential services (power, communications, water, sewerage) and to ensure flood infrastructure is fully serviceable before flooding, Government ensure: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2402 | 17 - Assets and technology | Explore better options for call and dispatch, telecommunications and information sharing capability across the emergency management portfolio including the adoption of a multi-agency emergency management operations complex |
REC302-2398 | 17 - Assets and technology | As a matter of priority commence the roll out of AVL capability for the Rural Fire Service fleet, completing as much work as possible before the 2018/19 bushfire season, capitalising where necessary on current and future work undertaken with the NSW Government Radio Network to ensure both officer safety and situational awareness |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0830 | 9 - Community education | That Bush Fire Risk Management Plans be tabled at Local Emergency Management Committees for comment. |
REC237-0829 | 9 - Community education | That Bush Fire Risk Management Plans be posted on the NSW Rural Fire Service website. |
REC237-0828 | 9 - Community education | That the NSW Rural Fire Service develop a strategy to better inform the community and NSW Rural Fire Service members about the NSW bush fire management system and its components. |
Rec-ID | Code | Recommendation |
---|---|---|
REC164-0074 | 9 - Community education | SERCon consider a review of existing community-based educational programs, with a view to informing the community |
REC164-0073 | 25 - Inquiry, audit, lessons management and after action review | SERCon consider that the proposed State Recovery Committee provide an interim report to government on these and |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |