REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2399 | 24 - Govt responsibility | Implement a fully integrated civilianised single call and dispatch centre, that includes a redundancy option outside the Sydney CBD, which will adopt an agnostic approach to deploy the quickest most suitable resource to an emergency. Such a centre should be managed by either a non uniformed public servant staffed organisation like the Office for Emergency Management, or the NSW Police Force |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3725 | 13 - Mapping and data quality | The data and information management system should be compatible with any data and information management system established by the ATSB for the designated interstate rail network, provided that the establishment of a compatible system does not reduce the amount or quality of the information obtained by ITSRR below the optimum levels which it needs to conduct trend analysis, and otherwise properly manage the safety of rail operations in New South Wales. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3724 | 13 - Mapping and data quality | The ITSRR should establish a data and information management system, containing all data and information that it requires, to continually monitor the safety of the New South Wales rail system. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |