Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC324-4295 | 11 - Evacuation and shelters | Roads: That, to improve the planning and protection of road infrastructure and to ensure communities, freight movers, combat agencies and emergency services have appropriate access and egress during and following a flood event, Government, through TfNSW and NSWRA and working with combat agencies and local and federal governments as needed, should: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
Rec-ID | Code | Recommendation |
---|---|---|
REC302-2399 | 24 - Govt responsibility | Implement a fully integrated civilianised single call and dispatch centre, that includes a redundancy option outside the Sydney CBD, which will adopt an agnostic approach to deploy the quickest most suitable resource to an emergency. Such a centre should be managed by either a non uniformed public servant staffed organisation like the Office for Emergency Management, or the NSW Police Force |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1184 | 24 - Govt responsibility | The Tasmanian fire agencies think more broadly about how staff who are already employed by Government could support the management of future emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0939 | 5 - Hazard reduction burns | That Tasmania Fire Service conducts a review of the fire permit system in the Fire Service Act 1979, and implements change to improve the efficiency and effectiveness of the system by: • considering whether it is appropriate to authorise persons or organisations to conduct fuel reduction burning during a permit period • providing a better match between the period, area and fire risk • maintaining a timely and efficient process for issuing permits • naming the period in a way that draws attention to bushfire risk • establishing a reporting and accountability process. |
REC247-0888 | 11 - Evacuation and shelters | That arrangements are made and appropriate pre-planning occurs to effectively implement the policy on evacuation. |
REC247-0938 | 5 - Hazard reduction burns | That Tasmania Fire Service or another suitable agency provides information to the community which shows, in simple form, the legislation applicable to approvals for lighting fires on private property and the various relationships between that legislation. |
REC247-0887 | 11 - Evacuation and shelters | That qualifying the evacuation authority in section 47 of the Fire Service Act 1979 be considered — by exempting those people with a pecuniary interest in a property from a directed evacuation where it is reasonable for them to remain. |
REC247-0928 | 24 - Govt responsibility | That the Government take into account demographic change in its assessment of the consequences of climate change on emergency events. |
REC247-0886 | 11 - Evacuation and shelters | That a state-level policy on evacuations be developed in the emergency management plans, including specific requirements for vulnerable people and guidelines for its implementation. |
REC247-0901 | 11 - Evacuation and shelters | That evacuation centres and other centres have plans and arrangements for electrical power redundancy. |
REC247-0890 | 11 - Evacuation and shelters | That decisions to open Community Fire Refuges and evacuation centres be coordinated with Tasmania Police. |
REC247-0889 | 11 - Evacuation and shelters | That Tasmania Police be identified as the lead agency on evacuations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3575 | 24 - Govt responsibility | The preferred model for the Tasmanian Medical Retrieval Services is to have TMRS and NETS staff based in RHH. The fixed wing would remain based in Launceston (for the present) with the helicopter to remain based in Hobart. |
REC140-3574 | 38 - Agency/Department Reporting | Formation of a subcommittee of the DHHS Tasmanian Medical Retrieval Services Committee to identify risk exposures, system problems and potential solutions. The subcommittee should review data, problem cases, system issues and generate a risk register. Meetings should occur at least quarterly. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3774 | 38 - Agency/Department Reporting | The ITSRR must provide a quarterly report to the Minister for Transport Services on the progress made by RailCorp in implementing these recommendations, including: |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3712 | 38 - Agency/Department Reporting | RailCorp and ITSRR should co-operate with national programs for the collection, collation, trend analysis and dissemination of safety critical information. |
REC121-3729 | 38 - Agency/Department Reporting | All reports of the Chief Investigator of OTSI should be delivered, upon completion and without being reviewed, to ITSRR and the Minister for Transport Services. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3723 | 38 - Agency/Department Reporting | All ATSB accident investigation reports should be made public. |
REC121-3776 | 38 - Agency/Department Reporting | The Minister for Transport Services should retain, independently of ITSRR, safety auditors to provide a report to the Minister confirming or qualifying the contents of each such ITSRR quarterly report. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3722 | 38 - Agency/Department Reporting | The ATSB should deliver any report of any such rail accident which it investigates to the Board of any rail organisation involved in the accident, ITSRR and the Minister for Transport Services. |
REC121-3775 | 38 - Agency/Department Reporting | The Minister for Transport Services must table in Parliament, each such quarterly report by ITSRR. |
REC121-3697 | 38 - Agency/Department Reporting | All train drivers’ defects reports should be entered by RailCorp into a computerised record and tracked to finalisation. |