Rec-ID | Code | Recommendation |
---|---|---|
REC236-2799 | 38 - Agency/Department Reporting | The committee recommends that the ATSB prepare and release publicly a list of all its identified safety issues and the actions which are being taken or have been taken to address them. The ATSB should indicate its progress in monitoring the actions every 6 months and report every 12 months to Parliament. |
REC236-2808 | 38 - Agency/Department Reporting | The committee recommends that in relation to mandatory and confidential reporting, the default position should be that no identifying details should be provided or disclosed. However, if there is a clear risk to safety then the ATSB, CASA and industry representatives should develop a process that contains appropriate checks and balances. |
REC236-2800 | 38 - Agency/Department Reporting | The committee recommends that where a safety action has not been completed before a report being issued that a recommendation should be made. If it has been completed the report should include details of the action, who was involved and how it was resolved. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2842 | 1 - Land-use and building regs | The committee recommends that building codes incorporate mitigation measures that take into account foreseeable risks from extreme weather events. |
REC229-2841 | 1 - Land-use and building regs | The committee recommends that credible and reliable flood mapping activities and the development of other information that would best inform landowners or prospective landowners of potential risks from extreme weather events are prioritised and used to inform land use planning laws. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1841 | 34 - Local knowledge | The state government establish a well coordinated and formalised system for the reading of river gauges by local people, including flood wardens. Furthermore, the knowledge of local people in predicting flood heights and impacts should be considered by emergency management agencies when predicting floods. |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1833 | 34 - Local knowledge | Local knowledge on the management and ongoing maintenance of waterways, including vegetation clearing and debris removal, needs to be incorporated in the development of regional flood mitigation strategies and local flood plans. Specifically: |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1844 | 34 - Local knowledge | Public authorities such as councils and CMAs should continue to seek local knowledge in relation to flood management issues. In particular, councils will collaborate with VICSES and other key stakeholders in reviewing the system of flood wardens. Roles and responsibilities of flood wardens, and the process for their recruitment, should be formalised and clearly articulated in relevant flood management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
Rec-ID | Code | Recommendation |
---|---|---|
REC176-0142 | 1 - Land-use and building regs | The Commonwealth consult with local, state and territory government planning authorities on the development and dissemination of a house loss risk index for households in Australia's highest risk bushfire areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3477 | 38 - Agency/Department Reporting | That the details of any variation or amendment of a Fire Operations Plan, including: the carrying forward or postponement of burns within the three-year period covered by a Fire Operations Plan; the carry over, removal or rescheduling of burns between past, present and future Fire Operations Plans; and the alteration of burn boundaries (including alterations of less than 25 per cent); should appear on the Department of Sustainability and Environment’s website at the time of the change and be included in the Fire Operations Plan for the following year. |
REC155-3476 | 38 - Agency/Department Reporting | That finalised Fire Operations Plans be made publicly available in their entirety (with the exception of any private information) on the Department of Sustainability and Environment’s website and in hard-copy, and that this requirement be clearly stated in future Codes of Practice. This should include the “district burns list”, or its future equivalents, and a map which shows the corresponding burns for each Fire District. Each map should be provided in a format which can be downloaded directly from the Department’s website without the need for further data manipulation by the user. An identical hardcopy version of the map for each Fire District should be also be available to members of the public on request and free of charge. |
REC155-3468 | 38 - Agency/Department Reporting | That the Department of Sustainability and Environment, Department of Primary Industries, Parks Victoria & VicForests separately cost, and report, annual expenditure on fuel reduction burning, ecological burning and regeneration burning in their Annual Reports. |
REC155-3467 | 38 - Agency/Department Reporting | The Department of Sustainability and Environment should report its performance against the increased prescribed burning target in its annual report, which should also include the following details: |
REC155-3480 | 1 - Land-use and building regs | That the Integrated Fire Management Planning framework establish zones in the interface between public and private land in which bushfire risk management is the shared responsibility of the Victorian Government and private landholders. |
REC155-3478 | 38 - Agency/Department Reporting | That all information pertaining to current and planned prescribed burns be published more prominently on the Department of Sustainability and Environment’s website, with a single prominent link to this material on the website homepage. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3215 | 1 - Land-use and building regs | The Committee recommends that the Building Code of Australia, including cyclone building codes, be revised with the objective of increasing resilience to climate change. |
REC145-3214 | 1 - Land-use and building regs | The Committee recommends that the Australian Government consider the benefits of adopting a nationally consistent sea level rise planning benchmark and, if so, whether this be done on a statutory basis or otherwise. The outcomes of this consideration should then be included as part of the action plan for the proposed Intergovernmental Agreement on the Coastal Zone. |
REC145-3213 | 1 - Land-use and building regs | The Committee notes the Council of Australian Governments initiative (through the Local Government and Planning Ministers Council) to develop state-specific climate change planning policies by mid 2011, to inform local governments and regional planning responses to climate change. The Committee recommends that the Australian Government ensure that the outcomes of this initiative are included as part of the action plan under the proposed new Intergovernmental Agreement on the Coastal Zone. |
REC145-3222 | 1 - Land-use and building regs | The Committee recommends that the Australian Government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC098-2186 | 38 - Agency/Department Reporting | The Committee recommends that the Department of Transport and Regional Services review its record keeping practices to show the type of emergency for which assistance is provided through the Natural Disaster |
REC098-2178 | 1 - Land-use and building regs | The Committee recommends that Standards Australia review the clarity of AS3959–1999: Construction of buildings in Bushfire Prone Areas to ensure that all relevant stakeholders can interpret and apply the Standard in the way it is intended. |
REC098-2176 | 1 - Land-use and building regs | The Committee recommends that Standards Australia incorporate building maintenance into AS3959–1999: Construction of buildings in Bushfire Prone Areas, perhaps renaming it as AS3959–1999: Construction and maintenance of buildings in Bushfire Prone Areas. |
REC098-2133 | 1 - Land-use and building regs | The Committee recommends that the Commonwealth seeks to ensure that the Council of Australian Governments resolve when asset protection zones will be located on private land and when on public land and gain assurances that adequate maintenance of zones will be enforced. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3246 | 38 - Agency/Department Reporting | The Committee recommends that performance monitoring standards be established, reviewed and maintained through a common reporting system by the Minister for Police and Emergency Services. |