REC286-1445 | 41 - Emergency Management exercises | Develop, implement, review and exercise inter-agency community evacuation and recovery plans across the State. |
REC286-2051 | 1 - Land-use and building regs | Establish arrangements to enable the buy-back of specified landslip prone land. |
REC286-1452 | 39 - Disaster Risk Management | Improve understanding of the allocation of ownership across government, business and individuals. |
REC286-2023 | 1 - Land-use and building regs | Locate and design new public infrastructure so that it can continue to operate during flood events. |
REC286-2072 | 35 - Business and Industry in relation to industry | Relax the requirement for medical certificates in the event of an outbreak. |
REC286-1464 | 41 - Emergency Management exercises | Exercise time-critical decision making processes within the context of an earthquake scenario. |
REC286-2039 | 41 - Emergency Management exercises | Nuance the exercises for flood / dam-break / debris flow to incorporate consideration. |
REC286-2089 | 39 - Disaster Risk Management | Identify and analyse statewide storm hazard risk. |
REC286-1441 | 5 - Hazard reduction burns | Continue the Fuel Reduction Program. |
REC286-1478 | 39 - Disaster Risk Management | Review environmental risks associated with hazardous uses within flood prone areas. |
REC286-2050 | 1 - Land-use and building regs | Ensure landuse planning and building systems, including appeal mechanisms, are transparent, equitable and integrated at the municipal, State and national levels. |
REC286-1451 | 1 - Land-use and building regs | Include consideration of coastal inundation in land use planning for new developments and uses. |
REC286-2017 | 39 - Disaster Risk Management | Improve maintenance of flood mitigation infrastructure. |
REC286-2066 | 39 - Disaster Risk Management | Advocate for an National Notifiable Diseases Database. |
REC286-1463 | 39 - Disaster Risk Management | Develop enablers and capacity for Tasmanian earthquake risk owners. |
REC286-2038 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-2087 | 41 - Emergency Management exercises | Develop and exercise Severe Storm Emergency Management Plan. |
REC286-1436 | 4 - Fire season preparation | Continue the development and implementation of community level Bushfire Mitigation Plans. |
REC286-1474 | 1 - Land-use and building regs | Raised access routes. |
REC286-2049 | 39 - Disaster Risk Management | Pro-actively manage landslide areas. |
REC286-1450 | 39 - Disaster Risk Management | Improve the understanding of the vulnerability of critical infrastructure. |
REC286-2015 | 1 - Land-use and building regs | Build flood capable infrastructure. |
REC286-2064 | 35 - Business and Industry in relation to industry | Encourage businesses to consider human influenza pandemics in business continuity planning. |
REC286-1461 | 39 - Disaster Risk Management | Review all hazards response and recovery plans to ensure they address likely earthquake consequences. |
REC286-2037 | 1 - Land-use and building regs | Make property level information on landslide hazards publicly available |
REC286-2084 | 10 - Infrastructure | Establish emergency services ICT redundancy arrangements for damage loss of communications infrastructure. |
REC286-1435 | 1 - Land-use and building regs | Monitor effectiveness of new Land Use Planning and Building System reforms to evaluate effectiveness of delivering desired outcomes. |
REC286-1471 | 1 - Land-use and building regs | Promote the use of Water Sensitive Urban Design in stormwater systems. |
REC286-2046 | 1 - Land-use and building regs | Incentivising safer sites (charge people less rates and discounts for defensive actions by land managers). |
REC286-1448 | 39 - Disaster Risk Management | Utilise coastal mapping to assess need for coastal defences. |
REC286-2061 | 41 - Emergency Management exercises | Review and exercise the Tasmanian Mass Vaccination Plan. |
REC286-1455 | 39 - Disaster Risk Management | Assess options for managed coastal retreat. |
REC286-2031 | 10 - Infrastructure | Improve information about electricity demand during heatwaves. |
REC286-2082 | 41 - Emergency Management exercises | Undertake inter-agency severe storm exercises. |
REC286-1469 | 39 - Disaster Risk Management | Actively manage riparian vegetation to manage flood dynamics. |
REC286-2044 | 1 - Land-use and building regs | Develop linkages between landslide risk assessors and building engineers/structural works. |
REC286-1447 | 39 - Disaster Risk Management | Assess vulnerability of ecosystems and species to coastal inundation. |
REC286-2056 | 39 - Disaster Risk Management | Review Ambulance Tasmania surge capacity. |
REC286-1453 | 1 - Land-use and building regs | Review building controls to ensure they are adaptive to changing coastal inundation risks. |
REC286-2025 | 41 - Emergency Management exercises | Exercise heatwave arrangements with a focus on the public administration sector and management of vulnerable people |
REC286-2081 | 39 - Disaster Risk Management | Engage with industry bodies to explore opportunities to better understand and manage risks. |
REC286-1468 | 39 - Disaster Risk Management | Identify and anlalyse the location of critical infrastructure within defined flood areas. |
REC286-2040 | 1 - Land-use and building regs | Further development of Landslide Hazard Banding of the State (MRT). |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1570 | 1 - Land-use and building regs | All governments should put in place best-practice institutional and governance arrangements for the provision of public infrastructure, including road infrastructure. These should include: |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2711 | 39 - Disaster Risk Management | That the Inspector General Emergency Management be empowered to provide an assurance to Government that the disaster management system is both appropriate and capable of dealing with complex events. |
REC239-2692 | 39 - Disaster Risk Management | That the Queensland Police Service Disaster Management Unit is to be permanently located at the State Disaster Coordination Centre to work on a day to day basis with the proposed new Department of Fire and Emergency Services. |
REC239-2691 | 39 - Disaster Risk Management | That the Commissioners of Police and the Queensland Fire and Rescue Service review the current district disaster boundaries as a matter of urgency in-line with the findings and recommendations of the Auditor–General’s report into the Queensland disaster management system. |
REC239-2675 | 35 - Business and Industry in relation to industry | That social benefit bonds and other opportunities with the business and not-for-profit sectors be developed to reduce reoffending and to provide rehabilitation programs. Such an instrument should be available to the market within two years. |
REC239-2774 | 39 - Disaster Risk Management | Those final determinations of disaster management districts include consultation with the Local Government Association Queensland, the Queensland Fire and Rescue Service and other Government departments. |
REC239-2723 | 1 - Land-use and building regs | That the Queensland Fire and Rescue Service examine alternative contractual arrangements with building owners which would reduce the need for physical attendance at alarm activations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC237-0825 | 1 - Land-use and building regs | That the NSW Rural Fire Service hold discussions with the Department of Planning and Infrastructure and Local Government NSW on ways to improve compliance with development consents under section 76A of the Environmental Planning and Assessment Act 1979. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2888 | 35 - Business and Industry in relation to industry | Foster private sector service providers who can offer tailored services or broadcast high quality presentation of general purpose weather information |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1901 | 1 - Land-use and building regs | The Council of Australian Governments’ Building Ministers’ Forum should provide formal direction to the Australian Building Codes Board to: |
REC205-1900 | 1 - Land-use and building regs | As a priority, state and territory governments should ensure that land-use planning systems are sufficiently flexible to enable a risk management approach to incorporating climate change risks into planning decisions at the state, territory, regional and local government levels. Consideration should be given to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
Rec-ID | Code | Recommendation |
---|---|---|
REC162-3011 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to expanding the role of AEMO in providing market information on gas by: |
REC162-3017 | 35 - Business and Industry in relation to industry | ESWG notes NGERAC already informally advises ministers on the possible effects of gas emergencies on electricity supplies. ESWG recommends formalising this role by acknowledging it in NGERAC’s MOU. ESWG also recommends an editorial review of NGERAC’s MOU to ensure accuracy and consistency. |
REC162-3022 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of how to ensure good communication and flow of information between the liquid fuels and other energy sectors. One approach that may be considered is that: |
REC162-3010 | 35 - Business and Industry in relation to industry | Energy Security Working Group (ESWG) recommends consideration be given to government and industry working together to understand that investment opportunities in the energy sector are realised in a timely fashion to better manage potential longer term supply shortfalls. |
REC162-3015 | 35 - Business and Industry in relation to industry | ESWG recommends National Gas Emergency Response Advisory Committee maintain its industry, jurisdiction and consumer representation noting the importance of input from each of these groups in developing its advice. |
REC162-3021 | 35 - Business and Industry in relation to industry | ESWG notes that existing and future contracts and the impending introduction of the Short Term Trading Market will be the primary mechanisms for addressing future gas supply shortfalls. |
REC162-3014 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to leveraging AEMO’s expanded responsibilities in gas markets by undertaking the role of the National Gas Emergency Response Advisory Committee (NGERAC) Secretariat while the Commonwealth continue as Chair, with the Chair’s position to be reviewed once the short term trading market (STTM) commences in June 2010. ESWG also recommends that the review be undertaken by NGERAC jurisdictional members. |
REC162-3020 | 35 - Business and Industry in relation to industry | ESWG recommends that as far as reasonably practical, arrangements for load shedding be as transparent as possible to give consumers confidence in the process. |
REC162-3013 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to consolidating gas and electricity network status and emergency information on one webpage for central communication. |
REC162-3019 | 35 - Business and Industry in relation to industry | ESWG recommends consideration be given to the spokesperson role AEMO can undertake during an electricity and/or gas supply shortfall in its covered markets and relevant jurisdictional emergencies, noting that AEMO has clear responsibility for the bulk supply of electricity as outlined in the Power System Emergency Management Plan and the Victorian wholesale gas market, and that for multi-jurisdiction gas supply emergencies, any AEMO spokesperson role would be to reflect NGERAC’s advice. |
REC162-3012 | 35 - Business and Industry in relation to industry | ESWG recommends reviewing AEMO’s Gas Bulletin Board (GBB) to ensure it is effectively communicating all publicly available information to market participants to assist in monitoring daily gas supplies, and any changes to the GBB rules required to improve information and awareness of any potential shortages that will assist the market to make the necessary investments and/or adjustments in maintenance. |
REC162-3018 | 35 - Business and Industry in relation to industry | ESWG recommends consideration of a review of communication protocols with the aim of achieving high level policy consistency of communication across jurisdictions to the maximum extent possible. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2115 | 41 - Emergency Management exercises | The Working Group recommends that the results of the scenario modeling be presented to the Australian Emergency Management Committee (AEMC) upon completion, and that AEMC form Sub Working Groups of State/Territory emergency management representatives as appropriate to be tasked with considering response and recovery capability (both state/territory and national) against the identified consequences. |
REC116-2107 | 10 - Infrastructure | The Working Group recommends that State/Territory emergency management plans should explicitly take the need for rapid assessment of damaged physical infrastructure into account. The importance of rapid physical infrastructure assessment in ensuring the supply of utilities including sewerage and drainage, electricity, water and gas to residential structures and other types should be recognised and considered. |
REC116-2129 | 41 - Emergency Management exercises | The Working Group recommends that Emergency Management Australia and the jurisdictions through the AEMC develop a three year rolling national exercise strategy aimed at testing the response and recovery aspects of large scale disasters. |
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |
REC116-2102 | 35 - Business and Industry in relation to industry | The Working Group recommends that jurisdictions identify appropriate commercial organisations/bodies able to ensure maintenance of supply of food items and packaged water to commercial outlets in times of disaster. |
REC116-2121 | 35 - Business and Industry in relation to industry | The Working Group recommends that the Australian Government investigate, in consultation with the finance and banking sector, the development of arrangements to ensure that essential transactions can continue in the event of a catastrophic failure of the banking system that includes access to cash. |