Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC306-2424 | 22 - Role of local Gvt | We recommend that the four councils develop floodplain management plans in accordance with Recommendation 2.12 of the Final Report of the Queensland Floods Commission of Inquiry. |
Rec-ID | Code | Recommendation |
---|---|---|
REC271-1521 | 26 - Research | The Department of Energy and Water Supply and SunWater, undertake the necessary studies to determine whether or not it is feasible to operate Callide Dam as a flood mitigation dam. Such studies should include matters in relation to, but not limited to: |
REC271-1522 | 26 - Research | Banana Shire Council investigate means to prioritise the commissioning of a fit-for-purpose flood study for high-risk areas across the Banana Shire to better inform flood risk management, including improved town planning. The outcomes of such a study should be available to the public and inform flood awareness campaigns, flood warnings, and building approvals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0791 | 22 - Role of local Gvt | Local Government Victoria should lead the design and implementation of strategies to support councils to further develop social capital needed for recovery. |
Rec-ID | Code | Recommendation |
---|---|---|
REC234-2813 | 38 - Agency/Department Reporting | To strengthen its oversight of Queensland reconstruction progress, the Australian National Audit Office (ANAO) recommends that the National Disaster Recovery Taskforce: |
REC234-2810 | 38 - Agency/Department Reporting | The Australian National Audit Office (ANAO) recommends that the Australian Government Reconstruction Inspectorate and the National Disaster Recovery Taskforce seek to maximise the benefits from their value for money review activities by obtaining more timely and comprehensive information on project progress and completion from the Queensland Reconstruction Authority, to enable the preliminary value for money assessments to be finalised based on the scope and cost of works that were actually delivered (rather than estimates). |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3625 | 38 - Agency/Department Reporting | We recommend that NSW Health continue with its good work and establish a performance management framework with targets and indicators to assess progress in preparing for infectious disease emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3901 | 22 - Role of local Gvt | That councils formulate, track and report on measures that show their performance in managing drainage assets. |
REC125-3900 | 12 - EM agency and authority | That agencies integrate condition information into their asset management decision-making practices and use it as the basis for validating asset valuations and depreciation calculations. |
REC125-3899 | 22 - Role of local Gvt | That councils implement a condition assessment and monitoring program conforming to best practice principles. |
REC125-3897 | 17 - Assets and technology | That agencies assess the cost-effectiveness of establishing a dedicated and proven asset management information system which is integrated with the other information systems used to manage drainage assets. |
REC125-3896 | 22 - Role of local Gvt | That councils plan for, and implement, formal consultation arrangements with stakeholders to set drainage goals and objectives, and desired service levels. |
REC125-3894 | 22 - Role of local Gvt | That councils develop flood risk management practices consistent with best practice risk management, and that these incorporate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |
REC112-3917 | 12 - EM agency and authority | That DPI improves monitoring and surveillance of high priority threats and improves the quality of information provided to the Commonwealth. |
REC112-3915 | 12 - EM agency and authority | That DPI makes arrangements to use contract labour for fruit fly trap monitoring and surveillance before the predicted fruit fly outbreak season. |
REC112-3914 | 12 - EM agency and authority | That DPI develops a consistent approach to recording and enforcing breaches of the certification and verification system. |
REC112-3909 | 12 - EM agency and authority | That PSB’s enforcement procedures are consistent with those of the rest of the department. |
REC112-3923 | 12 - EM agency and authority | That DPI negotiates access, as and when required, to an AQIS PC4- accredited laboratory. |