REC002-4009 | 16 - Training and behaviour | In gassy mines the Manager should be specially competent, and one possessing a thorough knowledge of the principles and practice of mining, the properties of gases, and systems of ventilation; and, above all, he must be prudent and cautious, yet resolute, possessing sound judgement. He must have absolute and supreme control over the whole operations, and of the men within the mine, to maintain rigid discipline, and be perfectly free and untrammelled by any outside influences. The competency of a manager should be certified by an examination before a specially-appointed Board. The Commission consider that better results may be obtained if such examinations be oral, and probably assume a more practical form than those hitherto conducted in Great Britain for the same object. |
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
REC258-2560 | 29 - Operational Health and Safety | The Civil Aviation Safety Authority devolve to Designated Aviation Medical Examiners the ability to renew aviation medical certificates (for Classes 1, 2, and 3) where the applicant meets the required standard at the time of the medical examination. |
REC258-2542 | 16 - Training and behaviour | The Civil Aviation Safety Authority publishes and demonstrates the philosophy of ‘just culture’ whereby individuals involved in a reportable event are not punished for actions, omissions or decisions taken by them that are commensurate with their experience and training. However, actions of gross negligence, wilful violations and destructive acts should not be tolerated. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2541 | 16 - Training and behaviour | The Civil Aviation Safety Authority finalises its Capability Framework and overhauls its training program to ensure identified areas of need are addressed, including: |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2534 | 16 - Training and behaviour | The Civil Aviation Safety Authority develops a staff exchange program with industry. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2788 | 16 - Training and behaviour | The committee recommends that, as far as available resources allow, ATSB investigators be given access to training provided by the agency's international counterparts. Where this does not occur, resultant gaps in |
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
REC236-2787 | 16 - Training and behaviour | The committee recommends that the training offered by the ATSB across all investigator skills sets be benchmarked against other agencies by an independent body by, for example, inviting the NTSB or commissioning an industry body to conduct such a benchmarking exercise. |
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
REC236-2791 | 37 - Funding | The committee recommends that the government develop a process by which the ATSB can request access to supplementary funding via the minister. |
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC232-2826 | 21 - Role of Commonwealth Government | The Australian Government coordinate the development of a highly skilled workforce which can respond effectively to a sustained pandemic in Australia. |
REC232-2818 | 16 - Training and behaviour | The Royal Australian College of General Practitioners provide resources and training to general practitioners on the complex health needs of migrants and refugees, with a focus on identifying infectious diseases which are notifiable in Australia, or diseases which are of specific concern to refugee and migrant communities. |
REC232-2825 | 21 - Role of Commonwealth Government | The Commonwealth Government support the growth of vaccine development and production capacity for vaccines in Australia, to enhance Australia’s preparedness to respond to outbreaks of infectious disease in Australia, and in particular, pandemic influenza. |
REC232-2817 | 21 - Role of Commonwealth Government | The Australian Government work with the state and territory governments to assess the viability of providing a centralised refugee and migrant health service in each state and territory, which would automatically refer people who move from immigration detention into the wider Australian community. |
REC232-2824 | 41 - Emergency Management exercises | The Australian Department of Health and Ageing consult with members of the general public or representatives of health consumers in the pandemic planning process, including in pandemic exercises designed to test the ability of government to respond to a pandemic event. Consumer involvement should include testing the ability of any communication strategy designed to inform and engage consumers about a pandemic event. |
REC232-2815 | 25 - Inquiry, audit, lessons management and after action review | The Department of Health and Ageing review the existing evidence base to evaluate the cost-effectiveness of its policy to use heat scanners at ports of entry as a measure to mitigate the risk of infectious disease importation. |
REC232-2822 | 41 - Emergency Management exercises | The Australian Government test Australia’s ability to respond to a widespread outbreak of infectious disease other than influenza, by undertaking a pandemic exercise across the relevant Commonwealth, state and territory government agencies. |
REC232-2828 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, commission an independent review to assess the case for establishing a national centre for communicable disease control in Australia. The review should outline the role of a national centre and how it might be structured to build on and enhance existing systems. It should examine different models, considering a range of options for location, governance and staffing. The review should incorporate a cost-benefit analysis for each of the models presented. |
REC232-2821 | 26 - Research | The National Health and Medical Research Council, in conjunction with key stakeholders, work collaboratively to provide more support for initiatives to increase international infectious disease research collaborations and build research capacity, particularly with neighbouring countries in the Asia-Pacific region. |
REC232-2827 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government, in consultation with state and territory governments, conduct a comprehensive national audit and mapping exercise to: |
REC232-2820 | 21 - Role of Commonwealth Government | Having regard to the terms of the Torres Strait Treaty, the Department of Health and Ageing, Queensland Health, AusAID and the Papua New Guinea Government: |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2859 | 17 - Assets and technology | I recommend that the issue of RHIB jet intake protection be allocated a high priority and that there be ongoing investigation of possible solutions to reduce the problem. |
REC227-2850 | 17 - Assets and technology | I recommend that the AFP be provided with a search and rescue vessel which is suitable to the specific conditions of Christmas Island. I further recommend that steps be taken to ensure that if for any reason the search and rescue vessel is not available, there is a replacement vessel on Christmas Island capable of providing an emergency response in difficult sea conditions. |
REC227-2858 | 13 - Mapping and data quality | I recommend that the Commonwealth prioritise completion of a hydrographic survey of Christmas Island and ensure that such a survey is completed in the near future. |
REC227-2848 | 17 - Assets and technology | I recommend that the AFP take steps to determine whether access can be obtained to the National Search and Rescue Council endorsed SARMAP program covering the Australian Search and Rescue Region as well as adjoining tiles for Indonesia. Steps should be taken to ensure that if possible coverage would include high traffic areas where SIEVs enter the Australian Search and Rescue region allowing timely search and rescue plans to be drawn up for any potential incidents. |
REC227-2857 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth ensure that there is a mooring buoy which will enable the mooring of SIEVs to take place and free up the Christmas Island response vessel for ongoing surveillance duties. |
REC227-2846 | 17 - Assets and technology | I recommend that Border Protection Command continues to examine ways of improving its surveillance capability around Christmas Island so that the risk of SIEVs arriving undetected is reduced. |
REC227-2853 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth liaise closely with representatives of the Christmas Island VMRS prior to purchasing or replacing any vessels for the VMRS in the future. |
REC227-2852 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth and the Shire of Christmas Island take steps to ensure that the Ethel Beach boat ramp is significantly upgraded, that it should be provided with shelter in the form of a rock groyne or similar buffer and that provision should be made so that a person can walk beside the ramp on a stable footing; or If this is not considered likely to be effective in providing an appropriate means of deploying a rescue vessel in adverse conditions, such other action be taken as is necessary to ensure that there is a means of deploying a rescue vessel in adverse conditions. |
REC227-2851 | 17 - Assets and technology | I recommend that consideration should be given to acquiring two personal water craft for deployment by appropriately trained and equipped staff of the AFP or the VMRS or both on Christmas Island. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2911 | 29 - Operational Health and Safety | The review team recommend that: |
REC189-2910 | 21 - Role of Commonwealth Government | NOPSA should: |
REC189-2908 | 21 - Role of Commonwealth Government | To ensure that NOPSEMA is in a strong position to perform its functions effectively: |
REC189-2907 | 29 - Operational Health and Safety | a) For the purposes of designing and implementing its regulatory activities, National Offshore Petroleum Safety Authority (NOPSA) should continue to identify priority hazards and risks and their underlying causes, in consultation with the NOPSA Advisory Board and stakeholders (see Theme 9, Stakeholder engagement). |
REC189-2913 | 21 - Role of Commonwealth Government | In developing and improving its policies and practices for stakeholder engagement, NOPSA should ensure that: |
REC189-2906 | 21 - Role of Commonwealth Government | In order to improve the effectiveness of National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA), with similar benefits for State or Territory regulators, attention should be given to the following actions. |
REC189-2912 | 29 - Operational Health and Safety | The review team recommend that the safety case system be strengthened by including provisions for a design notification scheme along the lines of that under the British Offshore Safety Case Regulations. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3450 | 37 - Funding | That emergency services are responsible for funding the development of the emergency services marine emergency response capacity/capability to meet their statutory obligations. |
REC158-3449 | 37 - Funding | That port/channel managers are responsible for funding the preparation of marine emergency risk assessments and marine emergency response arrangements and ensuring the availability of identified marine resources in support of response to a marine emergency, to meet their statutory obligations. |
REC158-3432 | 17 - Assets and technology | That port/channel managers are required to ensure, through service agreements, licensing, direct acquisition or other means as appropriate, the availability of the critical Level 1declared assets. |
REC158-3431 | 17 - Assets and technology | That port/channel managers are required to identify in the declared asset system (in conjunction with the emergency services) critical Level 1 declared assets and other Level 2 declared assets, that may be required in support of a marine emergency within the port, and that identified resource availability, accessibility and call out time is recorded. |
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
REC158-3430 | 17 - Assets and technology | That the nominated marine safety authority is responsible for development of a declared asset system and is required to ensure that port/channel managers utilise and maintain the declared asset system. |
REC158-3451 | 37 - Funding | That port/channel managers should be able, within the general context of the pricing/cost recovery arrangements established under the Port Services Act 1995 and pricing determinations made by the Essential Services Commission, to recover the reasonable costs of meeting their statutory obligations (as per recommendation 26) through charges for prescribed service applied to port users. |
Rec-ID | Code | Recommendation |
---|---|---|
REC154-3463 | 13 - Mapping and data quality | Biosecurity Victoria should enhance controls to provide assurance regarding data integrity. This process should include: |
REC154-3462 | 41 - Emergency Management exercises | DPI should formalise the approach and framework for evaluating simulation exercises and response to Emergency Animal Disease incidents with guidelines to define the nature of the review process. This should include: |
REC154-3459 | 41 - Emergency Management exercises | To improve response preparedness, DPI should clearly link the selection of simulation exercises to the risk management framework to target coverage of high risks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3147 | 29 - Operational Health and Safety | As all stakeholders have responsibility for safe outcomes, decisions regarding target subjects for safety promotion need to have the support of all stakeholders including NOPSA and the workforce. Industry, which ultimately has the responsibility for managing risk as well as funding the promotion, should take a leadership role in implementation. |
REC149-3136 | 16 - Training and behaviour | There is a need for industry in consultation with NOPSA to establish a priority programme of accredited education modules in the Safety Case regime targeting stakeholders in the regime at their respective levels to improve the understanding of the Safety Case and correspondent responsibilities. |
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3135 | 29 - Operational Health and Safety | The initial acceptance of a new facility Safety Case should be in conjunction with inspection of a facility upon commencement of operations. |
REC149-3144 | 29 - Operational Health and Safety | The Safety Case proponent should be allowed some flexibility to involve appropriate experience matched with the proposed workforce competencies to enable the Safety Case to be developed with value adding processes. Subsequent to the hiring of the workforce Final Government Response Offshore Petroleum Safety Regulation Inquiry and 2008 Review of NOPSA Operational Activities and preferably before the commencement of operations a review of the Safety Case should take place with the new workforce to ensure they understand the accepted Safety Case, its risks and Safety Management Plan. |
REC149-3128 | 29 - Operational Health and Safety | National Offshore Petroleum Safety Authority (NOPSA) should develop guidelines in consultation with stakeholders to provide clarity and consistency to the process which ultimately will result in better safety outcomes. |
REC149-3143 | 21 - Role of Commonwealth Government | The role of the advisory Board, namely to give advice to Ministers and NOPSA when asked, should be made clear to Board members and all stakeholders. The Board and NOPSA should consider the need for a clear description of who does what based on the legislated responsibilities of the NOPSA CEO. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3137 | 16 - Training and behaviour | As professional competency is one of the key pillars of any Safety Case, commitment to training for current and future needs remains a fundamental requirement for achieving best practice outcomes in safety. Industry should be encouraged to build on its training commitment now being made to achieve a competent and fully accredited workforce over the next five years. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3170 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to conduct within six months, an inspection and review of the process of horse importation from the time horses arrive in Australia until the completion of their post-arrival quarantine in order to: |
REC148-3152 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse Importation may be removed in the following circumstances only: |
REC148-3185 | 37 - Funding | That, until the review of those fees has been completed, the fee charged by the government controlled and operated quarantine stations for thoroughbred stallions temporarily imported into Australia be not be less than $165.00 plus GST a day and the fee for all other horses be not less than $65.00 plus GST a day. No discount is to be allowed for the number of horses in a consignment. |
REC148-3164 | 21 - Role of Commonwealth Government | That there be similar facilities for the unloading and transfer of horses at any other airport in Australia that might receive horses imported from places other than New Zealand. |
REC148-3169 | 37 - Funding | That the budgets for airport reception of horses and government controlled and operated quarantine stations be determined so as to be sufficient to fund the operations of the Quarantine Stations in accordance with these recommendations and any further procedures and requirements that are laid down from time to time. |
REC148-3151 | 21 - Role of Commonwealth Government | That the person holding the position of Inspector General of Horse |
REC148-3184 | 37 - Funding | That the fees charged in relation to the importation and quarantining of horses be reviewed and fixed without delay having regard to the following factors: |
REC148-3163 | 21 - Role of Commonwealth Government | That there be provided without delay at Sydney (Kingsford Smith) and Tullamarine Airports facilities to enable people who might have had contact with imported horses to shower and change their clothes, under supervision, before leaving the airport. |
REC148-3168 | 21 - Role of Commonwealth Government | That each government controlled and operated quarantine station have sufficient staff to carry out properly all activities and measures required by the current operating procedures dealing with the quarantine of horses. |
REC148-3148 | 21 - Role of Commonwealth Government | That the Secretary of the Department of Agriculture, Fisheries and Forestry designate, without delay, a Senior Executive Service officer to be primarily responsible and accountable for the importation of horses into Australia and to that end to have the power to exercise all necessary authority. |
REC148-3182 | 25 - Inquiry, audit, lessons management and after action review | That Biosecurity Australia review that formal import risk analysis at least once every two years to take into account any relevant developments in scientific knowledge—specifically testing methods, vaccines, vaccination procedures and other matters that affect biosecurity. Reports on the reviews should be provided to the officer responsible for the importation of horses and should contain recommendations for any necessary changes to policies for importation. |
REC148-3162 | 21 - Role of Commonwealth Government | That facilities for the unloading and transferring of horses at Tullamarine Airport in Melbourne be constructed urgently, upon advice of experts in biosecurity containment, to enable adequate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. |
REC148-3167 | 25 - Inquiry, audit, lessons management and after action review | That the facilities at Eastern Creek and Spotswood Quarantine Stations be reviewed by AQIS in consultation with experts in biosecurity and interested parties including state and territory governments, import agents, veterinarians, farriers, operators of private quarantine stations, and representatives of horse owners, horse racing organisations and equestrian organisations. There should in any event be constructed without delay, an adequate supply of hygienic, modern showering facilities and places of entry and exit to the stations and the horse sections of them that can be supervised and monitored continually. There should also be provided at those stations as soon as is practicable suitable means of electronic surveillance, including closed-circuit television; a secure place to store chemicals, drugs, instruments and equipment for use by people attending the quarantined horses, and a set of horse stalls and yards separate from the main stalls and yards to enable isolation of horses suffering from contagious or infectious diseases. These reviews should also consider the desirability of separate areas in quarantine stations to hold horses forming part of a single quarantine intake but that have been imported from different regions or have undergone pre-export quarantine in different places. The reviews should be carried out without delay, and the two quarantine stations should be upgraded in accordance with the recommendations of the reviews. |
REC148-3181 | 39 - Disaster Risk Management | That Biosecurity Australia undertake and complete within 12 months a non-regulated but formal import risk analysis relating to the importation of horses from the countries and regions from which Australia currently permits such importation, and make such recommendations for any changes to policies for importation as are warranted by its risk analysis to the officer responsible for the importation of horses and the Executive Director of AQIS. |
REC148-3161 | 21 - Role of Commonwealth Government | That the facilities for unloading and transferring of horses at Sydney (Kingsford Smith) Airport be upgraded without delay, following the advice of experts in biosecurity containment, so as to enable appropriate biosecurity precautions to be taken effectively and to minimise the risk of injury to horses and those handling them. The facilities should include at least one padded box or stall sound-proofed to the extent that it is reasonable to do so. |
REC148-3166 | 21 - Role of Commonwealth Government | That, in the absence of other satisfactory government controlled and operated post-arrival quarantine stations becoming available before the options to renew the leases of Eastern Creek and Spotswood Quarantine Stations expire, those options be exercised. |
REC148-3175 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia to review, at least once every two years, the operating procedures to ensure that they adequately identify and manage the risk of entry and spread of equine influenza associated with the importation of horses into Australia. The outcome of each such review should be the subject of a written report and recommendations to the person responsible for the importation of horses and the Executive Director of AQIS. A determination should then be made as to whether any, and if so what, changes should be made to the operating procedures. |
REC148-3154 | 25 - Inquiry, audit, lessons management and after action review | That the officer responsible for the importation of horses arrange for Biosecurity Australia or another qualified body to inspect and review the activities and events that occur from the time horses enter pre-export quarantine until the time they arrive at an airport in Australia, in order to identify any biosecurity risks and recommend any necessary changes to import conditions or other requirements. This inspection and review shall be performed without delay for each country or region from which horses are imported to Australia, and it should take account of my other recommendations and comments in this report. |
REC148-3165 | 21 - Role of Commonwealth Government | That there continue to be in Australia government controlled and operated post-arrival quarantine stations for horses. |
Rec-ID | Code | Recommendation |
---|---|---|
REC137-3533 | 21 - Role of Commonwealth Government | Accordingly I recommend that the Federal Minister for Transport, consider engaging an external consultant to assess whether high level intervention is warranted. |
REC137-3532 | 16 - Training and behaviour | I recommend that CASA reconsider the introduction of measures to ensure the efficiency of training and checking organisations for air transport operations. I recommend that this include the way in which particular training needs of an air operator’s flight crew are to be identified (including recurrent training and CRM training) and how those needs are to be met by approved or certified training and checking organisations. |
REC137-3530 | 16 - Training and behaviour | I recommend that Civil Aviation Safety Authority (CASA) expedite the introduction of mandatory crew resource management training. |
Rec-ID | Code | Recommendation |
---|---|---|
REC134-3520 | 21 - Role of Commonwealth Government | To improve the management of the National Medical Stockpile, the ANAO recommends that the Department of Health and Ageing incorporate into its governance framework: |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3624 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and formally establish and oversight a comprehensive program of training, testing and evaluation of plans at the state, area and facility level. |
REC129-3623 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and apply the lessons learnt from Exercise Cumpston to further improve preparedness for major infectious disease emergencies. |
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
REC129-3628 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test the capability of its contact tracing system to deal with a public health emergency. |
REC129-3627 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test its surveillance systems for early detection of infectious diseases. |
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
Rec-ID | Code | Recommendation |
---|---|---|
REC128-3614 | 37 - Funding | The Committee encourages the Department and the Rural Land Protection Boards to discuss the need for funding of poultry surveillance activities in the context of reviewing the Memorandum of Understanding between the two parties. |
REC128-3598 | 25 - Inquiry, audit, lessons management and after action review | That the Department of Primary Industries incorporates reviews of plans and operating procedures as a result of emergency incidents and exercises and ensures that there is adequate commitment from all participants in the review process. |
REC128-3609 | 16 - Training and behaviour | That the Department of Primary Industries be conscious of its responsibilities in maintaining the continued enthusiasm of Industry Liaison Officers and offer training and refresher training as required. |
REC128-3608 | 16 - Training and behaviour | That emergency animal health training be included in induction programs for newly recruited District Veterinarians and all District Veterinarians be encouraged to maintain their skills by attending regular refresher training as appropriate. |
REC128-3607 | 16 - Training and behaviour | That the Department of Primary Industries should continue efforts to develop the skills of private sector veterinarians to increase the level of resources available in emergency responses. |
REC128-3617 | 37 - Funding | That the Department of Primary Industries should provide specific information on levies to contributing producers through a separate document, rather than rely on standard audit documents and annual reporting requirements. |
REC128-3604 | 37 - Funding | That the Department of Primary Industries restore the level of discretionary testing funds provided to District Veterinarians to previous levels and maintain these in the future in real terms. |
REC128-3616 | 37 - Funding | That the Department of Primary Industries continue to pursue improvements to consultation with industry and accountability mechanisms to further build trust between industry and government, thereby enhancing the effectiveness of the OJD Program. |
REC128-3603 | 37 - Funding | That the Department of Primary Industries consider applying discretion to the use of user charging policies for testing in times when farm incomes are affected by external circumstances such as widespread drought. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3724 | 13 - Mapping and data quality | The ITSRR should establish a data and information management system, containing all data and information that it requires, to continually monitor the safety of the New South Wales rail system. |
REC121-3747 | 29 - Operational Health and Safety | All trains should have windows available through which passengers can escape. |
REC121-3675 | 16 - Training and behaviour | All rail employees should be trained by their employer to commence any emergency communication with the words “Emergency, emergency, emergency”, thereafter to identify themselves, the train, its location, what has occurred, the approximate passenger load and whether death or injuries have occurred. |
REC121-3707 | 29 - Operational Health and Safety | The safety document management system should provide for the distribution of electronic versions of safety documentation to relevant staff. |
REC121-3733 | 29 - Operational Health and Safety | RailCorp’s approach to occupational health and safety should be proactive and involve the systematic analysis of all current hazards, risks and controls and an assessment of their adequacy to reduce the risk of injury to, or death of, employees to an acceptable level. |
REC121-3754 | 29 - Operational Health and Safety | The RailCorp Board should ensure that RailCorp has an adequate and integrated safety management system, including adequate systems for risk assessment, clearly defined safety responsibilities and accountabilities for persons holding management positions, and specific performance criteria against which evaluations can be made of safety performance and accountability for safety performance of all managers. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3714 | 16 - Training and behaviour | RailCorp should use its simulators in an interactive manner. |
REC121-3739 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must be fitted with external emergency door releases which do not require any special key or other equipment to operate. |
REC121-3759 | 29 - Operational Health and Safety | A Safety Reform Program Director (hereafter referred to as SRPD), reporting directly to the Chief Executive of RailCorp, should be retained to manage, as head of a Safety Reform Program Office, any safety reform program being undertaken by RailCorp. The SRPD should work with the Chief Executive and senior management to ensure the implementation of an integrated safety management system and the cultural change required. The SRPD must have qualifications suitable for recognition by the Australian Institute of Project Management as a master program director. He or she should report to and be under the control of the Chief Executive, to ensure that the accountability of the Chief Executive is not reduced. The SRPD should co-ordinate and integrate any existing rail safety reform programs and, in consultation with and with the authority of the Chief Executive he or she should: |
REC121-3656 | 17 - Assets and technology | Satellite telephones should be provided by RailCorp to all rail commanders at any emergency. |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3719 | 16 - Training and behaviour | The position of team leader should be created by RailCorp to be responsible for a group of approximately 30 train drivers, with responsibility to ensure that each train driver’s training needs are being met and that any safety concerns of train drivers are being properly addressed. The team leaders are to have direct access to the Chief Executive of RailCorp if any safety concerns they have are not addressed. |
REC121-3746 | 16 - Training and behaviour | All emergency services personnel should be trained in the location and operation of emergency door release mechanisms on all rail cars. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3706 | 29 - Operational Health and Safety | RailCorp should establish a comprehensive safety document management system. |
REC121-3732 | 29 - Operational Health and Safety | If ITSRR accepts such a plan as an appropriate response to the existing weak safety culture, ITSRR should approve it and monitor the effectiveness of the plan. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3682 | 29 - Operational Health and Safety | All new rolling stock should be designed to be compatible with at least level 2 automatic train protection discussed in chapter 7 of this report. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3738 | 29 - Operational Health and Safety | All passenger trains must be fitted with an internal passenger emergency door release. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3654 | 16 - Training and behaviour | All train guards should be trained by RailCorp in the use of the Metronet radio and instructed to use it in any emergency. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3718 | 16 - Training and behaviour | Training should be based upon a needs analysis, to determine what skills a particular person will require to carry out the tasks of any position safely and efficiently, and instruction and practice, to acquire and demonstrate those skills. |
REC121-3744 | 16 - Training and behaviour | All RailCorp operational personnel should be trained in the location and operation of external emergency door release mechanisms. |
REC121-3672 | 16 - Training and behaviour | All emergency response personnel should be specifically trained in the features of railways which are relevant to their work, such as the location and means of operation of all emergency door releases on trains, the location and use of signal telephones, the methods by which electrical power can be isolated and the means by which they can readily identify and obtain information from the on-site rail commander. |
REC121-3704 | 28 - Personal responsibility | RailCorp should continue its system of voluntary self-identification and rehabilitation of employees with alcohol or drug related problems. |
REC121-3731 | 29 - Operational Health and Safety | RailCorp should develop a plan to be submitted to ITSRR to address the deficiencies in the safety culture of RailCorp, including: |
REC121-3751 | 16 - Training and behaviour | RailCorp should make it a condition of employment that all level 2 managers have or obtain a formal qualification in system safety management. |
REC121-3681 | 29 - Operational Health and Safety | RailCorp should progressively implement, within a reasonable time, level 2 automatic train protection with the features identified in chapter 8 of this report. |
REC121-3711 | 29 - Operational Health and Safety | The ITSRR should establish an electronic document control system to enable effective and reliable information to be gathered for monitoring the safety of the New South Wales rail system. |
REC121-3737 | 29 - Operational Health and Safety | There must be a minimum of two independent methods of self-initiated emergency escape for passengers from all trains at all times. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3717 | 16 - Training and behaviour | RailCorp must establish a task analysis for particular categories of employees, to identify the specific skills and responsibility of those employees or groups of employees, and thereafter undertake a training needs analysis, to develop the skills required in particular areas. |
REC121-3743 | 29 - Operational Health and Safety | All passenger trains operating in New South Wales must have the external emergency door release clearly marked with the words “Emergency Door Release”. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
REC121-3670 | 16 - Training and behaviour | The RailCorp emergency response plan should be provided to all emergency response agencies. The officers of each emergency service should be trained in any rail specific features of the plan, so as to better ensure inter-agency co-ordination in the circumstances of an emergency. |
REC121-3702 | 29 - Operational Health and Safety | Random alcohol testing should be continued. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3749 | 29 - Operational Health and Safety | All new rolling stock must be designed with an area of the roof through which emergency services personnel can access a rail car without encountering wiring or other equipment. That access point must be clearly marked with words such as “emergency services cut here”. |
REC121-3680 | 29 - Operational Health and Safety | All trains must be fitted with a minimum of two independent engineering defences to minimise the risk of derailment or collision in the event of train driver incapacitation. |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3735 | 29 - Operational Health and Safety | Risk assessments of occupational health and safety issues by RailCorp should include an analysis of broader public safety risks and not be confined to narrow occupational health and safety issues. |
REC121-3756 | 16 - Training and behaviour | RailCorp should ensure that where the safety competency of any manager is deficient such manager is required to undertake professional development courses to raise his or her safety competency level to an adequate standard. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3716 | 16 - Training and behaviour | Train driver and guard training should encourage teamwork and discourage authority gradients. |
REC121-3741 | 29 - Operational Health and Safety | The operation of the train doors should have an override facility whereby the train driver or the guard can override an internal passenger emergency door release system if the door release is interfered with when there is no emergency. There should be an alarm, together with an intercom, in the train guard’s compartment so that, if a passenger attempts to initiate an emergency door release, there is an appropriate delay during which time an alarm sounds in the train guard’s compartment and the guard can then, after first attempting to speak via the intercom to the person concerned, if necessary, override the door release, and make an appropriate announcement over the intercom system in the train. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3669 | 16 - Training and behaviour | All operational rail staff should be trained by RailCorp in the action check list relevant to each. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3725 | 13 - Mapping and data quality | The data and information management system should be compatible with any data and information management system established by the ATSB for the designated interstate rail network, provided that the establishment of a compatible system does not reduce the amount or quality of the information obtained by ITSRR below the optimum levels which it needs to conduct trend analysis, and otherwise properly manage the safety of rail operations in New South Wales. |
REC121-3748 | 29 - Operational Health and Safety | All new rail cars must have appropriate signage and lighting identifying escape routes in the case of emergency. |
REC121-3677 | 16 - Training and behaviour | A training centre for emergency services personnel should be established by RailCorp. The emergency services personnel should be required to undertake training at such a centre, which should be equipped with features replicating railway infrastructure and rolling stock. |
REC121-3709 | 29 - Operational Health and Safety | RailCorp should provide access to electronic versions of safety documentation for all operational staff at their workplace. |
REC121-3734 | 29 - Operational Health and Safety | RailCorp should integrate its management of occupational health and safety into its overall safety management. |
REC121-3755 | 29 - Operational Health and Safety | The RailCorp Board should require a full review of the safety competence of RailCorp managers to ensure that each has the ability to bring about those safety reforms recommended in this report which are applicable to his or her position. |
REC121-3650 | 16 - Training and behaviour | Staff at the Rail Management Centre (RMC) should receive training from RailCorp to enable them to quickly and accurately assess that an emergency has occurred and to provide precise and reliable information to emergency response personnel about the location of the emergency, the available access to the site and the resources necessary. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3715 | 16 - Training and behaviour | RailCorp should use its simulators to train drivers and guards in methods of dealing with degraded operations on the rail network. |
REC121-3740 | 29 - Operational Health and Safety | The internal passenger emergency door release should be fitted with a facility which prevents it from operating unless the train is stationary. |
REC121-3764 | 29 - Operational Health and Safety | The ITSRR should not grant accreditation to any rail organisation unless it has an integrated safety management system in accordance with any safety management system regulation and the guidelines published from time to time by ITSRR. |
Rec-ID | Code | Recommendation |
---|---|---|
REC112-3926 | 13 - Mapping and data quality | That DPI upgrades the Crop Health Services diagnostic database so that it alerts PSB and PIRVIC to the receipt of samples from nearby areas with similar symptoms and can be linked to other PIRVIC diagnostic databases. |
REC112-3912 | 25 - Inquiry, audit, lessons management and after action review | That DPI, as part of the development of the Victorian plant biosecurity strategy, undertake a strategic review of its plant health planning framework so that: • corporate and business unit plans at all levels of the department align to each other and to government policy so that staff have a coherent frame of reference to guide their work • performance indicators are developed, used, reported against and evaluated regularly • all plans (including service agreements with other parts of DPI) are communicated to staff and implemented in their day-to-day activities and responsibilities. |
REC112-3925 | 13 - Mapping and data quality | That DPI establishes a system to ensure the security of all samples at all times, but particularly during their handling and transport. |
REC112-3934 | 37 - Funding | That DPI prepares guidelines, both internally and externally with Treasury, about funding arrangements for an outbreak. |
REC112-3907 | 25 - Inquiry, audit, lessons management and after action review | That Department of Primary Industries (DPI), in partnership with the Department of Sustainability and Environment, reviews all legislation relating to plant biosecurity with a view to streamlining the legislative framework. |
REC112-3922 | 25 - Inquiry, audit, lessons management and after action review | That DPI maintains ISO 9000 accreditation for at least one laboratory and seeks NATA accreditation for key diagnostic tests. This should be done in combination with Plant Health Australia’s laboratory accreditation project. |
REC112-3932 | 25 - Inquiry, audit, lessons management and after action review | That DPI conducts and documents debriefs after all incursions, and adopts any improvements that are identified through debriefs. |
REC112-3921 | 17 - Assets and technology | That the recommendations of the 2000 DPI report into the reference collection’s storage facility be implemented, to secure the collection in a purpose-built facility. |
REC112-3931 | 16 - Training and behaviour | That DPI ensures that AIIMS training includes information to ensure that everyone understands their role, and how information will be managed internally and externally, in the event of an incursion. |
REC112-3919 | 25 - Inquiry, audit, lessons management and after action review | That the model for state funding be reviewed to ensure that DPI can confidently build and maintain a core level of diagnostic expertise and research capability. |
REC112-3930 | 16 - Training and behaviour | That DPI provides plant incursion-specific AIIMS training for anyone who might be involved in, or providing resources for, an incursion response. This includes senior management, field and research staff, contractors and industry participants. |
REC112-3916 | 16 - Training and behaviour | That DPI reviews the work of entry level graduates to ensure career paths are clear and encourage the retention of staff. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
REC008-3984 | 16 - Training and behaviour | The Commission recommends that the live parts of resistances should be fixed so that no unprotected combustible material is within 6ins of the frames or cases containing them or within 24ins measured vertically above. |
REC008-3990 | 16 - Training and behaviour | The Commission recommends that more than one means of exit should be provided in every mine from every level of it to the surface; and that the miners should be kept informed where they are situated. |
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3994 | 17 - Assets and technology | That the Railway Department, while gradually reducing the number of different types of locomotives, should steadily keep in view the adoption of English and American railway practice, by providing engines with larger boilers, fire boxers, and smoke-boxes, and with wide blast-pipes, in order to insure ample steaming power with a minimum of forced draught. |
REC004-3992 | 17 - Assets and technology | That the use of a spark-arrester and cinder-arrester by the Railway Department shall not constitute a defence to an action for damage caused by fire escaping from a locomotive, unless the Department proves that such spark-arrester and cinder-arrester were in a thoroughly efficient condition when the fire took place. |
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3996 | 17 - Assets and technology | That the standard pattern of cinder arrester be affixed to the ash-pans in all locomotives during the summer months. |