Rec-ID | Code | Recommendation |
---|---|---|
REC324-4304 | 1 - Land-use and building regs | Landholders can access information on previous disasters: That, to ensure there is a single source of ground truth to prepare for and respond to emergencies, and to provide people with a better understanding of their individual property and community risk exposure, an online visualisation tool be developed to display, for all land parcels (land titles) in NSW, the extent of known disasters that have affected each piece of land in NSW in the past. This information should be made available through the Planning Portal and, particularly in light of climate change, the data involved should be revised and updated at least every two years and after each major natural disaster. |
REC324-4296 | 1 - Land-use and building regs | Caravan parks and manufactured home estates: That, to ensure that permanent residents of caravan parks and mobile housing estates are protected from flood, Government: • prohibit permanent residency in caravan parks and mobile housing estates situated below the risk-based flood planning level. Caravan parks for holiday makers could still be on the floodplain with the provision that, if a flood is imminent, they need to be evacuated • address the issues raised in the 2015 Discussion Paper (Improving the regulation of manufactured homes, caravan parks, manufactured home estates and camping grounds). |
REC324-4305 | 39 - Disaster Risk Management | Cost benefit framework:That, to enable a more systematic prioritisation of investment options in risk mitigation before, during and immediately following a natural disaster event, Government adopt and utilise a Disaster Cost Benefit Framework. This Framework will enable Government to estimate the investment required for any given disaster, starting with flood events, and will enable the fast allocation of funding based on detailed and rapid analysis of flood and property modification, mitigation, preparation, response and finance related options including: |
REC324-4297 | 33 - Relief and recovery | Housing , especially social housing: That, to ease housing stress in flood prone areas and ensure new development is resilient and community-centred, Government pursue a multi-pronged, decadal strategy through: |
REC324-4310 | 41 - Emergency Management exercises | Task Force Hawk: That, to ensure disaster readiness, Government establish a high-level Government standing committee, Task Force ‘Hawk’, comprising key Cabinet Ministers, Secretaries and Commissioners that meets, trains and exercises to ensure Government is prepared to respond to any emergency. Task Force ‘Hawk’ should resonate with the community in difficult times to ensure the highest level of confidence in Government’s response. |
REC324-4299 | 1 - Land-use and building regs | Relocating communities most at risk with good homes and amenities: That, to empower vulnerable people and communities to relocate, Government through the NSWRA: |
REC324-4311 | 33 - Relief and recovery | Transition initiatives: That, to improve the community’s experience during immediate disaster recovery phase, Government through the SEOCON, NSWRA, DCS/Service NSW and other state agencies as required provide greater support (financial, health [including mental health], temporary accommodation, administrative and other support services) to affected communities by: |
REC324-4300 | 1 - Land-use and building regs | Simplify the planning system disaster provisions: That, to simplify and improve the state planning processes especially when anticipating and recovering from a disaster, Government: |
REC324-4303 | 39 - Disaster Risk Management | Risk-based approach to calculating flood planning: That, to take account of greater knowledge of climate change, Government reinforce its adoption of a risk-based approach to calculating the flood planning level for planning purposes and, through the NSWRA, immediately start a process of revising all flood planning level calculations in the state’s high-risk catchments. Flood planning level re-determinations for all high-risk catchments should be completed within 3 years. These revised flood planning levels will need to be factored into all development applications (in-progress and new) in those high-risk catchments. The risk profile of high-risk catchments should be revisited at appropriate time intervals to check that levels are current. A review should take place if there has been a significant trigger event (i.e. changed rainfall, development) or at least every 5 years. As well as reviewing the flood planning level, this 5-yearly review should include reviewing any floodplain lease conditions and adjusting them as necessary in the light of better knowledge of climate change impacts. In working out a tolerable, risk-based flood planning level, consideration should be given to the PMF, 1% AEP, 0.02% AEP, existing development, approved but not yet constructed developments, and existing and approved but not yet constructed evacuation routes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC323-4277 | 33 - Relief and recovery | That the NSW Government develop a more proactive, rapid response to manage animal welfare following natural disasters which includes improved collaboration and communication with local veterinarians and animal welfare organisations. |
REC323-4290 | 20 - Role of police | That the NSW Government embed into its emergency plans the appointment of a senior police officer with combat experience to lead recovery efforts following natural disasters. |
REC323-4266 | 1 - Land-use and building regs | That the NSW Government review the provision of temporary and long term housing options provided to those affected by the February-March 2022 floods, with a view to: • ensuring a range of options are identified and embedded within emergency and recovery plans, so that solutions can be implemented as soon as possible after a natural disaster • ensuring that housing options meet individual and community needs • removing planning impediments that prevent those from accessing more safe and secure housing in times of crisis. |
REC323-4267 | 1 - Land-use and building regs | That the NSW Government consider investing in supporting relocations, land swaps and providing fair and adequate compensation for landowners who wish to relocate from severely flood-impacted areas. |
REC323-4269 | 33 - Relief and recovery | That the NSW Government address the mental health needs of local communities following the February-March 2022 floods by: • embedding within state emergency and recovery plans a strategy that provides surge capacity for mental health and social workers by: • prioritising funding for community groups that are currently providing social and mental health support to their local communities • ensuring all flood-impacted communities receive the mental health support they need to fully recover. |
REC323-4257 | 1 - Land-use and building regs | That the NSW Government work with local government, industry and sustainable planning experts, including the Government Architect, on policy initiatives in the New South Wales planning system that will help deliver more resilient and sustainable homes, buildings and places. |
REC323-4271 | 33 - Relief and recovery | That Service NSW establish teams of assessors that can be on the ground to assess and approve grant applications. |
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
REC323-4273 | 33 - Relief and recovery | That the NSW Government overhaul the way in which it conducts its grants process as it frustrated applicants and further traumatised them by repeatedly re-interviewing them and making them prove that they were flooded. |
REC323-4289 | 33 - Relief and recovery | That the NSW Government ensure that all emergency and recovery plans, including state plans, local emergency management plans and functional area plans, are reviewed and updated regularly and provide clarity on the role of non-government partners. |
REC323-4262 | 33 - Relief and recovery | That the NSW Government provide an increased level of targeted support to flood affected communities contending with widespread mould. |
Rec-ID | Code | Recommendation |
---|---|---|
REC280-1376 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC280-1383 | 1 - Land-use and building regs | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC280-1375 | 5 - Hazard reduction burns | That the NSW Government commit to and fund a long term program of prescribed burning based on the recommendation of the 2009 Victorian Bushfires Royal Commission of an annual rolling target of a minimum of five per cent of public land per year, and that the NSW Government commit to extending the funding for the National Parks and Wildlife Service five year hazard reduction program past 2016. |
REC280-1382 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC280-1399 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service remove from its boundary fencing policy and standard contract the condition that requires adjoining land owners to maintain a fence that has been damaged by trees falling from national park land. |
REC280-1381 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC280-1398 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service: |
REC280-1378 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: -improve accountability in relation to the implementation of bush fire risk management plans as a means of delivering more hazard reduction. |
REC280-1386 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
REC280-1377 | 5 - Hazard reduction burns | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC280-1385 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
Rec-ID | Code | Recommendation |
---|---|---|
REC261-1494 | 4 - Fire season preparation | That the NSW Rural Fire Service, in collaboration with the NSW National Parks and Wildlife Service, review and improve the system of bush fire management zones to ensure that greater priority is given to hazard reduction on land classified within land management zones. |
REC261-1502 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service consider the feasibility, on a case by case basis, of closing public roads through national parks on days with catastrophic fire danger rating, to mitigate the risk of bush fire ignition in national parks. |
REC261-1493 | 5 - Hazard reduction burns | That the NSW National Parks and Wildlife Service establish a regime of frequent mosaic burning within the Warrumbungle National Park, where conditions permit, to be monitored and evaluated via a formal fully funded research program. This program should then inform the Service’s approach to the wider national park estate. |
REC261-1500 | 10 - Infrastructure | That the NSW Government improve the protection of media and telecommunications towers around New South Wales by: |
REC261-1520 | 33 - Relief and recovery | That the Ministry for Police and Emergency Services urgently review its policies for the provision of disaster welfare services to ensure that in the event of a bush fire emergency and the declaration of a fire under section 44 of the Rural Fires Act 1997, adequate funding and services, especially recovery centres and mental health services, are provided for an adequate length of time, with gradual transition to normal service delivery when those services are no longer required. |
REC261-1499 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service, at the direction of the NSW Rural Fire Service, enhance the network of fire trails within national parks across New South Wales by: |
REC261-1515 | 4 - Fire season preparation | That the NSW National Parks and Wildlife Service: |
REC261-1498 | 4 - Fire season preparation | That the NSW Rural Fire Service review the decision not to construct additional fire trails in the Warrumbungle National Park following the Wambelong fire. |
REC261-1514 | 1 - Land-use and building regs | That the NSW National Parks and Wildlife Service adopt an interim fencing agreement in the immediate aftermath of a fire. This will enable emergency and interim works to commence, but features such as length, fencing components and site of the fence line are not binding. A final fencing agreement would be negotiated no earlier than six months following a major national park fire. |
REC261-1495 | 5 - Hazard reduction burns | That the NSW Rural Fire Service: |
REC261-1503 | 4 - Fire season preparation | That the NSW Rural Fire Service and the NSW National Parks and Wildlife Service investigate the cost and feasibility of installing infrared cameras at the Siding Springs Observatory and key sites in other national parks to facilitate fire spotting. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3664 | 20 - Role of police | The location of the command post for site control at the scene of any rail accident should be identified by NSW Police by a distinctive flashing light. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |