REC321-4201 | 10 - Infrastructure | We recommend that DELWP improves the Powerline Bushfire Safety Program's transparency by publicly reporting on activities, costs and risk-reduction outcomes. |
REC321-4202 | 10 - Infrastructure | We recommend that DELWP investigates incentives and advises government on options to accelerate burying and insulating the remaining high-voltage bare-wire powerlines in the 33 highest risk areas. |
Rec-ID | Code | Recommendation |
---|---|---|
REC264-1085 | 10 - Infrastructure | GDF Suez establish enhanced back-up power supply arrangements that do not depend wholly on mains power, to: • ensure that the Emergency Command Centre can continue to operate if mains power is lost; and • ensure that the reticulated fre services water system can operate with minimal disruption if mains power is lost. |
Rec-ID | Code | Recommendation |
---|---|---|
REC196-0233 | 16 - Training and behaviour | Further train Incident Controllers in the management of the Information Section and its roles. |
REC196-0232 | 16 - Training and behaviour | Increase the regularity of training for ICC Information Section staff and encourage pre-season drilling and trials in the use of OSOM and Emergency Alert particularly under critical capacity conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC195-0315 | 14 - Incident Mgt Teams | The Fire Services, as part of the regular review of Incident Management Teams – Readiness Arrangements, reassess current resource sustainability and identify opportunities for a more flexible application. |
REC195-0322 | 7 - Inter-agency communication | The Fire Services investigate the reported technical communication issues for this fire |
REC195-0314 | 16 - Training and behaviour | The Fire Services enhance and increase joint training and exercise programs at all levels of command and control, including the State Control Centre. (These programs need to enable volunteer participation.) |
REC195-0321 | 7 - Inter-agency communication | The Fire Services move towards a common and more disciplined approach to fireground communications. |
REC195-0310 | 16 - Training and behaviour | The Fire Services Commissioner ensures that there is a comprehensive understanding of the State Command and Control Arrangements for Bushfires in Victoria across the Fire Services. |
REC195-0319 | 7 - Inter-agency communication | The Fire Services introduce systems, procedures and operational training that promote information sharing and consistent situational awareness at every level, including to and from the fireground. This should include agencies such as police members on duty at roadblocks |
REC195-0335 | 10 - Infrastructure | Energy Safe Victoria ensures that the standards for vegetation clearance around power lines consider the impact of fire on electrical infrastructure and the risk of loss of electricity supply to the community. |
REC195-0317 | 14 - Incident Mgt Teams | The Fire Services ensure that an incident action plan (summary) is developed in accordance with the Standard Operating Procedure J3.03. |
REC195-0326 | 16 - Training and behaviour | The Fire Services recognise the specialised role of Information Sections and enhance training and resources accordingly. |
REC195-0316 | 14 - Incident Mgt Teams | The Fire Services continue to develop fire behaviour analysis and predictive science capability by ensuring the Fire Behaviour Analysis Team is appropriately resourced with accredited staff and available to provide services to the IMT. |
REC195-0323 | 14 - Incident Mgt Teams | Incident Controllers ensure that Emergency Management Teams consider, provide advice, and manage the broader consequences of actions, such as reopening roads, the resumption of public transport and school buses, and the welfare of those impacted by traffic management points. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0173 | 7 - Inter-agency communication | The Country Fire Authority review and improve its communications strategy as a matter of priority and develop a program for identifying and responding to black spots in radio coverage. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0175 | 16 - Training and behaviour | The Country Fire Authority and the Department of Sustainability and Environment require without exception that all relevant staff be trained in the need for Incident Controller approval to be obtained before a back-burn is lit. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0214 | 37 - Funding | The State replace the Fire Services Levy with a property-based levy and introduce concessions for low-income earners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC155-3470 | 37 - Funding | That the Victorian Government provide recurring funding for a significant increase in regionally-based, permanent, or long-tenured, fire management personnel dedicated to the prescribed burning program. The increase in personnel should be consistent with the level required to achieve an annual prescribed burning target of 385,000 hectares. |
REC155-3469 | 37 - Funding | That the Victorian Government establish a five year rolling fund which allows unused prescribed burning monies to be rolled over into future financial years for the purpose of subsequent prescribed burning activities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC124-3890 | 16 - Training and behaviour | Update education and training programs relating to prescribed burning to reflect revised organisational priorities including year round (365 day) fire management program: |
Rec-ID | Code | Recommendation |
---|---|---|
REC104-2259 | 16 - Training and behaviour | That the MFESB continue to give priority to appropriate bushfire training for its firefighters. |
REC104-2318 | 37 - Funding | When the research into prescribed burning and optimum fire protection described in Chapter 11, and the financial analysis of appropriate funding levels for prevention and suppression recommended in Chapter 15, are completed, DSE should develop a business case with Department of Treasury and Finance for assured funding to an agreed level over a three-year rolling cycle. |
REC104-2223 | 10 - Infrastructure | That Government review legislation for utilities operating within the State to ensure their involvement in regional fire preparedness and mitigation planning. |
REC104-2267 | 14 - Incident Mgt Teams | That DSE and CFA develop an agreed process for the effective transfer of control from one Incident Control Centre to another, including processes for communicating this change to fire ground supervisors and local communities. |
REC104-2243 | 37 - Funding | That Government reviews the funding for DSE for the 2004-2005 fire season to ensure that appropriate resources are available for fire prevention planning and preparedness. |
REC104-2274 | 7 - Inter-agency communication | That when Incident Management Teams implement significant changes to objectives and strategies, these are effectively communicated to firefighters, fire ground supervisors and affected communities, and are incorporated into the broader organisational planning. |
REC104-2258 | 14 - Incident Mgt Teams | That, wherever possible, Incident Management Team members from DSE, CFA and MFESB who are likely to be deployed together to manage fire, should train and exercise together. |
REC104-2308 | 37 - Funding | That Government funding for Community Development Officers engaged in community support and rebuilding incorporates flexible resources to enable the purchase of services from a range of providers to ensure choice for those requiring support. |
REC104-2264 | 16 - Training and behaviour | That CFA and DSE provide media training to all Level 2 and Level 3 Incident Controllers. |
REC104-2242 | 37 - Funding | That the financial arrangements incorporate full cost recovery for prescribed burning to be undertaken over a number of weekends utilising Project Firefighters, CFA volunteers and MFESB members. |
REC104-2273 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader be given flexibility to alter tactics to take advantage of changed conditions on the fire ground. |
REC104-2250 | 41 - Emergency Management exercises | That DSE and CFA work in cooperation with the Municipal Emergency Response Coordinators to develop and conduct joint exercises that practise the skills and test procedures for operations of the Municipal Emergency Coordination Centre, Municipal Recovery Centre and Incident Control Centres. |
REC104-2294 | 16 - Training and behaviour | That training and competency programs for Incident Controllers should include aircraft firefighting capability training. |
REC104-2263 | 16 - Training and behaviour | That the person appointed by DSE or CFA as Incident Controller for any incident should have formal qualifications and accreditation in the Incident Control System, be fully aware of the Victorian emergency management arrangements and have access to local fire prevention and response planning, including the Municipal Fire Management Plan |
REC104-2241 | 37 - Funding | That the financial models incorporate changes in public land use, particularly ‘Our Forests Our Future’, and the subsequent changes in fire management priorities. |
REC104-2272 | 14 - Incident Mgt Teams | That personnel assigned the roles of Division Commander, Sector Commander and Strike Team Leader on the fire ground are actively encouraged to provide input into the selection of strategies and tactics. |
REC104-2249 | 16 - Training and behaviour | That DSE and CFA ensure that: |
REC104-2280 | 14 - Incident Mgt Teams | That DSE and CFA ensure that: |
REC104-2262 | 14 - Incident Mgt Teams | That the practice of appointing Deputy Planning Officer, Deputy Operations Officer and Deputy Logistics Officer in an Incident Management Team be abandoned. This recommendation acknowledges the benefits of retaining a Deputy Incident Controller from the support agency (in accordance with section 4.2.6 of the Emergency Management Manual Victoria), to ensure that the command structure of that agency is preserved. |
REC104-2335 | 41 - Emergency Management exercises | That the fire agencies develop a program to significantly increase the amount of joint training and exercises undertaken. |
REC104-2240 | 37 - Funding | That Government supports the immediate development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2271 | 14 - Incident Mgt Teams | That DSE and CFA ensure that agreed strategy and tactics, and the rationale, be communicated to personnel involved in the fire fight and be included in briefings for fire line personnel. |
REC104-2245 | 37 - Funding | That DSE includes the cost of tracks, as above, in the development of financial models to analyse and determine the appropriate level of investment in fire management planning, preparedness and suppression on public land. |
REC104-2279 | 14 - Incident Mgt Teams | That operational briefings in multi-agency fires should, wherever possible, be joint briefings of all agencies involved. |
REC104-2260 | 16 - Training and behaviour | That VICSES, with the support of the CFA, includes basic fire safety training as one of the competencies for the VICSES Volunteers. |
REC104-2327 | 16 - Training and behaviour | That all fire agencies include a formal mentoring scheme as part of their workforce development programs; and that consideration be given to the use of suitably competent and experienced individuals (such as retired staff), to act as coaches or mentors with inexperienced Incident Controllers. |
REC104-2235 | 16 - Training and behaviour | That DSE and CFA review selection and training programs for Incident Controllers and Incident Management Team members to ensure that they include all necessary competencies in recognition that technical skills are only one component of the required attributes. |
REC104-2269 | 14 - Incident Mgt Teams | That the fire agencies ensure that Incident Action Plans developed by Incident Management Teams are consistent with, and built on, the agreed Fire Control Priorities. |
REC104-2244 | 37 - Funding | That DSE assesses the environmental and monetary cost of establishment and rehabilitation of temporary tracks, per 100 km, constructed during firefighting operations, and compare this with the recurrent costs of a program of maintaining existing tracks. |
REC104-2275 | 14 - Incident Mgt Teams | That the ‘Incident Objectives’ established for any response should reflect the endorsed Statewide ‘Fire Control Priorities’, and the relevant Municipal Fire Management Plan. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3948 | 16 - Training and behaviour | It is recommended that workers and volunteers generally be instructed in accordance with a pre-arranged plan, as to what they should do in future times of emergency. Since the fighting of fires is for the greater part a matter of voluntary action, some estimate could perhaps be made, after investigation, of the numbers of men in each department who would be willing to volunteer. It would be necessary that each department should become a component part of an over-riding scheme and that it and its members should be fully instructed in the matter of whistle or siren warnings, places of assembly, reception of messages from the director of proceedings, use of equipment, and the various details which would necessarily be parts of an effective scheme. The training need not be onerous. If given once or twice at the beginning of possible danger periods, it would make for some degree of order and efficiency instead of a probable state of confusion. |
REC016_3945 | 16 - Training and behaviour | It is recommended that a large proportion of men employed in and about the open-cut be systematically trained in the use of equipment and in the tactical disposition of it. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
Rec-ID | Code | Recommendation |
---|---|---|
REC015_3959 | 37 - Funding | It is recommended that an annual grant be made to the Association for distribution among the brigades for the purposes of purchase of equipment of which the brigades are in urgent need. |