Rec-ID | Code | Recommendation |
---|---|---|
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
REC309-2471 | 17 - Assets and technology | As part of the annual Emergency Action Plan review for the Ross River Dam, consideration should be given to the potential impacts of operating the gate outside automatic mode and whether this event has provided any new information and learnings which can be incorporated into the Emergency Action Plan. This should occur prior to the 2019/20 wet season. |
Rec-ID | Code | Recommendation |
---|---|---|
REC308-2449 | 25 - Inquiry, audit, lessons management and after action review | Queensland should implement and maintain a system-wide lesson management program. |
REC308-2465 | 29 - Operational Health and Safety | Fatigue management strategies and guidance should be improved to ensure sustainable staffing practices are incorporated into disaster management planning. |
REC308-2451 | 17 - Assets and technology | Queensland should examine the feasibility of the installation of storm tide markers in prominent public places and the exploration of new technology to highlight storm tide risk to the community and its visitors. |
REC308-2450 | 17 - Assets and technology | The operation and maintenance of flood gauges should be developed and planned for on a catchment basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1202 | 13 - Mapping and data quality | Impact Assessment Data Collection: The Office of Emergency Management continues to progress the Impact Assessment Data Collection Project and: · incorporate recovery schema in Rapid Impact Assessments · review procedures for collection of Rapid Impact Assessment Data · review and combine current templates into one, single template for Impact Assessment Reports that is used by all agencies · further develop Impact Assessment Guidelines for agency personnel undertaking impact assessments |
REC281-1201 | 25 - Inquiry, audit, lessons management and after action review | Preventing Flood Related Fatalities: The NSW Government consider the recommendations from the Preventing Flood Related Fatalities Report when it is released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1152 | 13 - Mapping and data quality | Impact Assessment Data Sharing Project |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1590 | 25 - Inquiry, audit, lessons management and after action review | Department of Broadband, Communications and the Digital Economy seek regular updates from Telstra on the implementation of the recommendations of its inquiry into the Warrnambool exchange fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC215-1879 | 25 - Inquiry, audit, lessons management and after action review | Regulators can help to achieve improved outcomes by auditing compliance with the BPEM guidelines on a regular basis |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3506 | 26 - Research | The Office of the Emergency Services Commissioner facilitate further research into technologies that will reduce the need for the public to speak to an operator during an emergency as a component of the proposed emergency warning and alert system and Victorian Emergency Information Line. |
REC156-3496 | 21 - Role of Commonwealth Government | The Bureau of Meteorology contact list for severe weather warning be strategically managed in consultation with Emergency Service Organisations, to identify critical contacts. The Bureau of Meteorology must ensure the detail for these critical contacts remains up to date. |