Rec-ID | Code | Recommendation |
---|---|---|
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0796 | 25 - Inquiry, audit, lessons management and after action review | The Department of Premier and Cabinet should lead: x the development of an evaluation framework, based on work undertaken to date by the Department of Human Services, to be used in assessing the impact of relief and recovery programs in the recent floods and in future disaster events x an evaluation of the impact of relief and recovery programs in the recent floods, using this framework. |
REC250-0790 | 25 - Inquiry, audit, lessons management and after action review | The Department of Justice should review the current model for rapid impact assessment to improve the quality of the information collected. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1816 | 21 - Role of Commonwealth Government | That the Department of Sustainability and Environment continue to invest in the auditing of Victoria’s levee systems, both public and private, so that the Victoria Flood Database contains reliable and up to date data, including information on levees’ location, height, condition and ongoing viability for flood protection. |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1840 | 25 - Inquiry, audit, lessons management and after action review | The state government implement the Victorian Floods Review recommendation 8, to review the flood gauging network. As part of the review, consideration should also be given to the use of portable telemetered river gauges, and to the replacement of manual gauges with telemetered gauges over time and where appropriate. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0403 | 21 - Role of Commonwealth Government | the state and commonwealth undertake a review into the appropriate institutional arrangements for the forecasting and predictions function currently undertaken by Melbourne Water for the Port Phillip and Westernport region. |
REC199-0482 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to develop and undertake the regular audit of emergency management plans at all levels. |
REC199-0411 | 21 - Role of Commonwealth Government | the Bureau of Meteorology undertake a review of its radar coverage in the context of flash and riverine flood warnings for Victoria, with a particular focus on known gap areas such as the Horsham/Nhill region. |
REC199-0428 | 25 - Inquiry, audit, lessons management and after action review | the state clarify which agency is responsible for collecting post-flood extent and related data. This should include: • the development of guidelines to ensure consistent standards are applied to post-flood data collection; and • an appropriate process to ensure funding availability for such activities. |
REC199-0401 | 25 - Inquiry, audit, lessons management and after action review | the state task the Emergency Services Commissioner with the responsibility to establish an effective audit regime of the total flood warning system. |
REC199-0477 | 21 - Role of Commonwealth Government | the state review the potential for National Registration and Inquiry System 6 to provide a single point of information collection to both register individuals and plan the delivery of recovery services. If the review determines National Registration and Inquiry System 6 is unable to fulfil this function, the state should work with the commonwealth and other states to implement the necessary changes to National Registration and Inquiry System 6. If National Registration and Inquiry System 6 is unable to be developed as a single information collection system: the state should develop and implement a single point of information collection system, including how information obtained from outreach activities can be incorporated into this system and how such information may be linked into the Rapid Impact Assessment process. |
REC199-0409 | 21 - Role of Commonwealth Government | the Bureau of Meteorology should present water levels in both local datum and Australian Height Datum (gauge zero) for all its published information and warnings |
REC199-0423 | 21 - Role of Commonwealth Government | the Bureau of Meteorology expand its volunteer amateur weather watch groups to enhance its weather and flood information gathering procedures. |
REC199-0470 | 21 - Role of Commonwealth Government | the commonwealth consider including (as part of its review of standards for aged care services) requirements for: • robust ‘all hazards’ evacuation plans that include current after-hour contact details of people who are able to make authoritative decisions during an emergency; and • rehearsal of those plans. |
REC199-0407 | 25 - Inquiry, audit, lessons management and after action review | the state: • undertake a strategic review to identify areas at risk from flash or riverine flooding. Shortcomings in the flood gauging networks identified in the review should then be the focus of remedial action • seek to address as a priority any notable gaps in the total flood warning system as apparent in the 2010–11 floods (including south west Victoria, Wimmera and north central region) by enhancing mapping, gauging and education programs; and • seek a commitment from the Bureau of Meteorology to ensure any new gauges installed are utilised to enhance flood prediction capability and coverage. |
REC199-0419 | 21 - Role of Commonwealth Government | the Bureau of Meteorology provide Incident Control Centres with real-time access to flood data held by the Bureau of Meteorology. This will require Bureau of Meteorology staff making themselves available to respond to enquiries from Incident Control Centres during a flood event. |
REC199-0450 | 25 - Inquiry, audit, lessons management and after action review | the state ensure that appropriate record management processes are developed and implemented and that these processes also provide record accountability for multi-agency operations. Agency processes should be standardised to the fullest extent possible |
REC199-0405 | 21 - Role of Commonwealth Government | the state and the Bureau of Meteorology liaise to ensure the existence of appropriate quality control processes for gauges and contingency measures in the event that gauges are damaged during flood events. |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0445 | 25 - Inquiry, audit, lessons management and after action review | the state develop and implement operational performance standards for each state agency involved in emergency management response and recovery and that: • each agency be assessed by the Emergency Services Commissioner periodically against these performance standards for both capability and capacity; and • where performance against these standards for either capability or capacity cannot be demonstrated by any agency – appropriate advice is communicated to the relevant Minister, departmental/agency head and State Emergency Response Coordinator; and – an action plan is developed and implemented to address the relevant capability or capacity deficiency in both the short and longer term. |
REC199-0404 | 21 - Role of Commonwealth Government | the state engage with the Bureau of Meteorology to establish a joint initiative to review existing flash flood warning systems in Victoria and identify where additional systems are needed, with a particular focus on urban centres with a history of flash flooding. This review should seek to achieve outcomes similar to those implemented in NSW. Subject to those outcomes being implemented, the state should determine which agency is responsible for flash flood warnings. |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0412 | 21 - Role of Commonwealth Government | the Bureau of Meteorology adjust its flood prediction models to incorporate water storage conditions (to enable it to issue more timely and useful flood predictions for communities based downstream of water storages). |
Rec-ID | Code | Recommendation |
---|---|---|
REC156-3494 | 10 - Infrastructure | Energy Safe Victoria finalise the development of the passport system to improve interstate mutual aid arrangements allowing operator access to qualified interstate power restoration personnel. |
REC156-3487 | 10 - Infrastructure | Electricity distribution businesses develop and implement alternative arrangements for monitoring fallen powerlines. |
REC156-3500 | 10 - Infrastructure | The Emergency Services Telecommunications Authority, in partnership with Telstra, consider technological solutions to streamline the handover process for Triple Zero calls. |
REC156-3496 | 21 - Role of Commonwealth Government | The Bureau of Meteorology contact list for severe weather warning be strategically managed in consultation with Emergency Service Organisations, to identify critical contacts. The Bureau of Meteorology must ensure the detail for these critical contacts remains up to date. |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3898 | 25 - Inquiry, audit, lessons management and after action review | That agencies develop a detailed improvement plan and commit resources to its implementation. |