REC319-4199 | 24 - Govt responsibility | Relief and recovery capability: The Inspector-General for Emergency Management recommends that Emergency Management Victoria and the entity referred to in Recommendation 13, or otherwise responsible government department – in collaboration with the relevant relief and recovery organisations: |
REC323-4291 | 12 - EM agency and authority | That the NSW Government consider abolishing Resilience NSW if it is unable to ensure: |
REC323-4292 | 12 - EM agency and authority | That the NSW Government consider a restructure of the NSW State Emergency Service with consideration to: realigning the focus of the organisation to harness local knowledge and networks; coordinating more closely with other rescue agencies to bolster its capacity to respond; and increasing salaried staff and resources, and driving volunteer recruitment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1823 | 24 - Govt responsibility | The Victorian Government should work with the New South Wales Government and the Murray Darling Basin Authority to establish an appropriate floodplain management committee and to develop a floodplain management strategy for the Murray River. The strategy will define priority regions for the development of floodplain management plans, address ways of improving the management of all levees on the Murray River, and seek agreement in relation to improved approvals processes, levee heights and maintenance regimes. |
REC217-1836 | 26 - Research | Flood studies will be undertaken to determine the flood extent on the basis of a greater than 1 in 100 ARI, where appropriate: |
REC217-1822 | 24 - Govt responsibility | The state government will work with Grampians Wimmera Mallee Water and stakeholders to determine ongoing ownership and associated responsibilities for redundant channel infrastructure in the Wimmera and the Mallee. |
REC217-1835 | 24 - Govt responsibility | Within the jurisdiction of Melbourne Water, it shares with local councils the responsibility to manage local drainage systems as outlined under the Water Act 1989 and the Local Government Act 1989 respectively: |
REC217-1819 | 22 - Role of local Gvt | In consultation with local communities, local councils will develop flood response plans as subplans to their current Municipal Emergency Management Plans. As part of the flood risk assessment process, these plans will be informed by the best available flood mapping and modelling, and will identify agreed activities to be undertaken during floods including, where appropriate, the construction of temporary levees. The condition of levees will be incorporated into such plans to enable improved emergency response. |
REC217-1827 | 24 - Govt responsibility | The role of flood risk management planning rests with CMAs and Melbourne Water (under the Water Act 1989), and is a shared responsibility with local government. Shared responsibilities for flood risk management planning and implementation will be consistently reflected in government policy. |
REC217-1846 | 24 - Govt responsibility | The state government should implement the recommendations of the Victorian Floods Review in relation to the creation of resilience committees and resilience plans, with responsible authorities. |
REC217-1825 | 22 - Role of local Gvt | When developing flood mitigation options in lowland areas, local governments should give consideration to the use of temporary levees as an alternative or addition to permanent structures. To maximise the use of these structures and limit flood damage, and aid affordability, consideration should be given by local governments to the sharing of temporary levees among different townships and different council areas. |
REC217-1843 | 24 - Govt responsibility | The state government implement the Victorian Floods Review recommendation 10 in relation to the datums used to describe river and stream heights. |
REC217-1824 | 24 - Govt responsibility | The Victorian Government to implement the recommendations of the Victorian Floods Review in relation to the development and implementation of appropriate flood mitigation and protection strategies for essential services. |
REC217-1839 | 24 - Govt responsibility | The state government accept recommendations 25 to 28, inclusive, of the Victorian Floods Review. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |
REC210-0641 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in model flood planning controls, councils should include assessment criteria in their planning schemes that require community infrastructure (including the types of community infrastructure which are identified in the Sustainable Planning Regulation 2009 and which the community needs to continue functioning, notwithstanding flood) to be located and designed to function effectively during and immediately after a flood of a specified level of risk. |
REC210-0698 | 22 - Role of local Gvt | Councils should consider implementing a property buy-back program in areas that are particularly vulnerable to regular flooding, as part of a broader floodplain management strategy, where possible obtaining funding from the Natural Disaster Resilience Program for this purpose. |
REC210-0713 | 24 - Govt responsibility | The Queensland Government should refine the criteria which must be considered in assessment of applications for relaxation of environmental authority conditions, by transitional environmental program or otherwise, in response to flood. |
REC210-0753 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare formal work procedures for the review of flood event reports created under emergency action plans and flood mitigation manuals. These should include procedures for: • making enquiries with the owners of referable dams that have catchments that have been subject to heavy rainfall (or where there is other reason to believe the emergency action plan has been triggered) as to whether the emergency action plans have been triggered • reminding owners of referable dams that have had emergency action plans triggered of their obligation to submit a flood event report • upon receipt of a flood event report, reviewing it, identifying any dam safety or other issues or areas where insufficient detail has been provided, raising those matters with the dam owner or other affected party and identifying appropriate remedial steps 28 Queensland Floods Commission of Inquiry | Final Report Complete list of Final Report recommendations • raising any issues identified in the report that are beyond the expertise of the Department of Environment and Resource Management, or are likely to be of particular interest to another body, with the appropriate body • keeping a record of the process and results of the review of the flood event report • fixing an appropriate timeline for the completion of each of the above steps: the time required may depend on specific circumstances, but must allow for any potential safety issues to be identified and remedied efficiently. |
REC210-0605 | 22 - Role of local Gvt | As far as is practicable, councils should maintain up-to-date flood information |
REC210-0653 | 22 - Role of local Gvt | Councils (particularly Brisbane City Council) should consider including in their planning schemes more stringent standards for the design and construction of prescribed tidal work than those in the code for development applications for prescribed tidal work in the Coastal Protection and Management Regulation 2003. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0730 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop clear directives about: • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the communication and reporting that should take place between the SES and disaster managers, including in relation to task allocation and completion, once disaster management groups have been activated • the process for dealing with requests for assistance that exceed an SES unit’s capacity to respond them • the process for seeking extra support for an SES unit that has been overwhelmed by a disaster (whether by way of Emergency Management Queensland or the disaster management arrangements or both) • the role of SES liaison officers in communications with disaster managers about SES disaster operations • the role of incident controllers, and their teams, relative to those SES (or Emergency Management Queensland) personnel charged with the command of SES operations. |
REC210-0768 | 22 - Role of local Gvt | Toowoomba Regional Council should engage external consultants to carry out failure impact assessments on the detention basins along East Creek. |
REC210-0610 | 22 - Role of local Gvt | Councils in floodplain areas should, resources allowing, develop comprehensive floodplain management plans that accord as closely as practicable with best practice principles. |
REC210-0669 | 22 - Role of local Gvt | Councils should take care when imposing conditions to ensure that each condition has purpose; standardised conditions should not be included where they have no application to the development in question. |
REC210-0706 | 24 - Govt responsibility | The Department of Environment and Resource Management should prepare a list of relevant considerations to be taken into account in performing a risk assessment to decide which sites to inspect. Bureau of Meteorology forecasts should be one consideration. |
REC210-0742 | 24 - Govt responsibility | The Queensland Government should ensure that, when it considers options for the operational strategies to |
REC210-0632 | 22 - Role of local Gvt | If the Queensland Government does not include such a code in the model flood planning controls, councils should include in their planning schemes a flood overlay code that consolidates assessment criteria relating to flood. |
REC210-0688 | 22 - Role of local Gvt | All councils should periodically conduct risk assessments to identify areas at risk of backflow flooding. In respect of such areas, councils should consider how such risks can be lessened, including in that process consideration of the installation of backflow prevention devices. Backflow devices should not, however, be installed unless and until a full risk based assessment has been undertaken. |
REC210-0711 | 24 - Govt responsibility | Unless the Department of Environment and Resource Management has decided not to permit discharges, it should assist each mine operator in its application for an environmental authority to ensure, as far as possible, that each authority includes provisions for discharges during times of heavy rainfall and flood. |
REC210-0752 | 24 - Govt responsibility | Prior to approving a flood mitigation manual, the Queensland Government should be satisfied that its terms are expressed in a manner that allows a determination of compliance with it to be made by reference to objective standards. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0651 | 22 - Role of local Gvt | When approving applications for development which involve the manufacture or storage of hazardous materials, councils should not restrict the conditions imposed to ones which are solely reliant on human intervention to remove the materials in the event of flood. |
REC210-0720 | 24 - Govt responsibility | The Queensland Government should determine which of its agencies should take responsibility for the management of all existing and new abandoned mine sites in Queensland. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0668 | 22 - Role of local Gvt | Councils should review their assessment processes to ensure that: • the person with primary responsibility for the assessment of the development application considers what expert input is required • where a development application is subject to comment by a number of professionals, the responsibilities and accountability of each contributor are clear • where flood-related information is referred to an expert for advice, the expert is required to comment on the extent of compliance by reference to each relevant assessment criteria and identify and explain any inability to comment. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0729 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directive when it is developed. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0630 | 22 - Role of local Gvt | If the Queensland Government does not include a requirement for such an overlay map in the model flood planning controls, councils should include a flood overlay map in their planning schemes. The map should identify the areas of a council region: • that are known not to be affected by flood • that are affected by flood and on which councils impose planning controls (there may be subsets in each area to which different planning controls attach) • for which there is no flood information available to council. |
REC210-0687 | 22 - Role of local Gvt | The Bundaberg Regional Council should investigate the adequacy of the drain and take reasonable steps to ensure the Moore Park area is effectively served. |
REC210-0710 | 24 - Govt responsibility | The Department of Environment and Resource Management should assist mine operators in their applications for amended environmental authorities to ensure, as far as possible, that each environmental authority contains a tailored version of Table 4 of the model conditions. The Department of Environment and Resource Management should provide to mining companies its monitoring data and its suggested values for Table 4 on the basis of an assessment of the catchment which takes into account the cumulative effect of different operators’ releases. |
REC210-0751 | 24 - Govt responsibility | The Queensland Government should continue to assess and review the adequacy of work procedures DS 5.1 and 5.3, having regard to the need for flood mitigation manuals to reflect the will of the executive. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0650 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require that: a. the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) take place above a certain flood level, determined following an appropriate risk based assessment, or b. structures on land susceptible to flooding and used for the manufacture or storage of bulk hazardous materials (as defined in State Planning Policy 1/03) be designed to prevent the intrusion of floodwaters |
REC210-0718 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant an emergency direction. |
REC210-0765 | 24 - Govt responsibility | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam, the Queensland Government should consider the impact of possible upgrades of bridges downstream of Wivenhoe Dam on different operating strategies for the dam. |
REC210-0608 | 22 - Role of local Gvt | Elected representatives from all agencies involved in a flood study should be informed of recommendations made for future work, and determine, on a risk basis, whether that further work is to be completed. |
REC210-0667 | 22 - Role of local Gvt | If the Queensland Government does not include such a policy in the model flood planning controls, councils should include a planning scheme policy in their planning schemes that sets out the information to be provided in development applications in relation to stormwater and flooding. The policy should specify: • the type of models and maps to be provided • the substantive information required to be shown in the development application • how the assumptions and methodologies used in preparing the models and maps should be presented • the form in which the information on stormwater and flooding is to be presented in the application. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0728 | 12 - EM agency and authority | Emergency Management Queensland, in consultation with councils, should develop a directive that makes clear the authority of an officer of that agency to command a major SES operation. This could be expected to occur when a deployment of additional SES members is made to a region because the response needed is beyond the capacity of its local units. The directive should make clear the powers of the officer and his or her reporting responsibilities to disaster managers in these circumstances. Emergency Management Queensland must also ensure that any officer who assumes such a role has adequate training and skills in the conduct of disaster operations. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0774 | 24 - Govt responsibility | The Department of Environment and Resource Management and Emergency Management Queensland should ensure that each has copies of current emergency action plans for all dams in Queensland. |
REC210-0620 | 24 - Govt responsibility | The Queensland Government should determine whether existing guidelines are sufficient for councils to understand best practice in the performance of flood studies and the production of flood maps. If a lack of current guidelines is identified, the government should create and circulate guidance material for councils. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0748 | 24 - Govt responsibility | The Queensland Government should consider whether North Pine Dam should be operated as a flood mitigation dam when it considers possible operating strategies and full supply levels as part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at North Pine Dam. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0648 | 22 - Role of local Gvt | Councils should ensure that, when applications for environmentally relevant activities are approved by a council, the details of those activities, including their nature and location, are provided to the Department of Environment and Resource Management. |
REC210-0716 | 24 - Govt responsibility | The Queensland Government should make public the procedural guide used by Department of Environment and Resource Management officers to decide whether to grant a transitional environmental program. |
REC210-0764 | 24 - Govt responsibility | The Department of Transport and Main Roads, in conjunction with Brisbane City Council and Somerset Regional Council, should investigate options for the upgrade of Brisbane River crossings between Wivenhoe Dam and Colleges Crossing and undertake a cost-benefit analysis of these to determine the outcome which best serves the public interest. |
REC210-0607 | 22 - Role of local Gvt | Elected representatives from councils should be informed of the results of each flood study relevant to the council’s region, and consider the ramifications of the study for land planning and emergency management. |
REC210-0663 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes that address: • the prospect of isolation or hindered evacuation • the impact of isolation or hindered evacuation. |
REC210-0725 | 12 - EM agency and authority | The fire service should ensure that station officers are familiar with the procedure for contacting management when requesting the calling in of additional staff; and, in particular, that they have available to them the names and current telephone numbers of the officers to be contacted in the first instance, with alternative contact details in the event that those officers prove unavailable. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0771 | 24 - Govt responsibility | The Queensland Government should, in consultation with the Department of Environment and Resource Management and Emergency Management Queensland, determine which agency is appropriate to review and approve emergency action plans for referable dams. |
REC210-0619 | 24 - Govt responsibility | In the event that the review does not adequately account for Queensland conditions, the Queensland Government should produce a document that provides appropriate guidelines for floodplain management in the Queensland context. |
REC210-0671 | 22 - Role of local Gvt | Councils should consider providing advice to development applicants during pre-lodgement meetings, and at the time of receiving a development application, about the way in which the development will be assessed for flood risk and what flood information council will be relying on to make this assessment. |
REC210-0708 | 35 - Business and Industry in relation to industry | The Queensland Government should work collaboratively with the Commonwealth Government and mine operators to ensure co-ordinated and effective monitoring of salts, metals and other contaminants in marine environments that may be affected by mine discharges. |
REC210-0745 | 24 - Govt responsibility | The Queensland Government should ensure that all flood mitigation manuals include the requirement that those operating the dam during flood events hold current registrations as professional engineers. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0643 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should include assessment criteria in their planning schemes that require the impact of flood on commercial property to be minimised. |
REC210-0715 | 24 - Govt responsibility | The Queensland Government should prepare a procedural guide for officers deciding whether to grant a relaxation of environmental authority conditions, by transitional environmental program or otherwise, with guidance as to: • the meaning of each criterion • examples of the types of things that may be relevant to each criterion • the priority, if any, to be afforded to different criteria. |
REC210-0763 | 35 - Business and Industry in relation to industry | Seqwater should ensure that the Somerset Dam gallery is not susceptible to flooding during overtopping events. |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0655 | 22 - Role of local Gvt | If the Queensland Government does not include such assessment criteria in the model flood planning controls, councils should consider including assessment criteria in their planning schemes which require that works in a floodplain: • do not reduce on-site flood storage capacity • counteract any changes the works will cause to flood behaviour of all floods up to and including the acceptable defined flood event by measures taken within the subject site (for example, use of compensatory works, detention basins or other engineering mechanisms), and • do not change the flood characteristics outside the subject site in ways that result in: – loss of flood storage – loss of/changes to flow paths – acceleration or retardation of flows, or – any reduction in flood warning times elsewhere on the floodplain. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0731 | 12 - EM agency and authority | Emergency Management Queensland should ensure its staff, SES members and disaster managers are familiar with the directives it develops in relation to these matters. |
REC210-0769 | 22 - Role of local Gvt | Toowoomba Regional Council and the Department of Environment and Resource Management should continue to co-operate to assess the referable dam status of existing detention basins and any future detention basins constructed in the West Creek and East Creek catchment areas. |
REC210-0618 | 24 - Govt responsibility | The Queensland Government should endeavour to ensure that Queensland conditions are appropriately considered in the National Flood Risk Advisory Group’s review of best practice principles. |
REC210-0670 | 22 - Role of local Gvt | Councils should not rely on a condition requiring an evacuation plan as the sole basis for approving a development susceptible to flooding. |
REC210-0707 | 24 - Govt responsibility | The Department of Environment and Resource Management should conduct risk assessments in time for site inspections, and the implementation of solutions to problems identified at inspections, to take place before 1 November of each year. |
Rec-ID | Code | Recommendation |
---|---|---|
REC204-1911 | 24 - Govt responsibility | As part of the review of its due diligence processes, Tourism WA should ensure that: |
REC204-1909 | 35 - Business and Industry in relation to industry | Eventscorp should ensure that organisers of events its sponsors are directed to all appropriate authorities and stakeholders to ensure the responsible, safe and efficient planning and conduct of the event. |
REC204-1915 | 24 - Govt responsibility | The Department of Regional Development and Lands should ensure that event organisers and government agencies responsible for sponsoring and approving events have a greater level of awareness about the requirements of section 91 licences under the Land Administration Act 1977 (WA). |
Rec-ID | Code | Recommendation |
---|---|---|
REC166-3003 | 12 - EM agency and authority | That the Tasmania Fire Service provide additional training in power disconnection and improvements in communication between Tasmania Fire Service and Aurora: |
REC166-2999 | 35 - Business and Industry in relation to industry | That Aurora ensure that regular audits are conducted of all electrical systems of all commercial buildings to confirm that they comply with modern standards. |
Rec-ID | Code | Recommendation |
---|---|---|
REC061-3243 | 12 - EM agency and authority | The Committee recommends that one standard model of fire cover be developed for Victoria as a matter of urgency. |
REC061-3256 | 12 - EM agency and authority | The Committee recommends that a new Board be appointed, consisting of nine members nominated by the Minister for Police and Emergency Services and including the Chief Executive Officer who shall not be Chairman. |
REC061-3415 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
REC061-3242 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3255 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board remain a statutory authority. |
REC061-3411 | 12 - EM agency and authority | The Committee recommends that collocation shall occur unless it can be demonstrated to the satisfaction of the Minister that it is inappropriate. |
REC061-3241 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board continue to exist. |
REC061-3254 | 12 - EM agency and authority | The Committee recommends that: |
REC061-3409 | 12 - EM agency and authority | The Committee recommends that one standard model of fire cover be developed for Victoria as a matter of urgency. |
REC061-3421 | 12 - EM agency and authority | The Committee recommends that a new Board be appointed, consisting of nine members nominated by the Minister for Police and Emergency Services and including the Chief Executive Officer who shall not be Chairman. |
REC061-3250 | 24 - Govt responsibility | The Committee recommends that the Bureau of Emergency Services Telecommunications Centre extend its services as a commercial venture to smaller government agencies who could not develop such a dedicated system. |
REC061-3408 | 24 - Govt responsibility | It is inappropriate for an emergency services provider to develop its own standards, core objectives and functions. The Committee recommends that these be the responsibility of the Minister for Police and Emergency Services. |
REC061-3420 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board remain a statutory authority. |
REC061-3245 | 12 - EM agency and authority | The Committee recommends that collocation shall occur unless it can be demonstrated to the satisfaction of the Minister that it is inappropriate. |
REC061-3407 | 12 - EM agency and authority | The Committee recommends that the Metropolitan Fire Brigades Board continue to exist. |
REC061-3419 | 12 - EM agency and authority | The Committee recommends that: |