Rec-ID | Code | Recommendation |
---|---|---|
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1287 | 32 - Doctrine, standards, and reform | That the glossary of terms in the State Emergency Management Plan be reviewed to ensure all relevant language is included. All agencies need to ensure the use of clear communication and accurate use of terminology, including in describing the status of critical services e.g. Triple Zero (000), SA Government Radio Network, electrical and water supplies and infrastructure. |
REC295-1331 | 32 - Doctrine, standards, and reform | Task South Australian Fire and Emergency Services Commission with further developing the Emergency Alerts capability across government agencies including to: a) establish and maintain a centralised training program for emergency alert initial and refresher training. b) establish a pool of endorsed Emergency Alert personnel from across government agencies to enable control agencies to assist each other with the emergency alert function during emergencies. c) develop supporting processes to ensure that the capability supports: emergencies involving any hazard; consistent issuing of alerts and warnings; consistent messages; and effective communication and notification of alerts issued to relevant internal and external stakeholders |
REC295-1298 | 12 - EM agency and authority | That the State Emergency Service, in consultation with key stakeholders, identify and implement a robust system and procedures for prioritising, allocating and coordinating multiple tasks. |
REC295-1277 | 32 - Doctrine, standards, and reform | That the Department of Planning, Transport and Infrastructure review their Business Continuity Plan to: |
REC295-1314 | 32 - Doctrine, standards, and reform | That an Emergency Management Assurance Framework be established as soon as possible to support the emergency management arrangements and the State Emergency Management Plan. Consider establishing an Inspector General Emergency Management department or position. |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1330 | 32 - Doctrine, standards, and reform | Update the Public Information Functional Support Group Plan to include: a) standards, outputs, systems and processes required to be used by control agencies and the Public Information Functional Support Group during emergencies b) guidance on the public information cycle through the prevention, preparedness, response and recovery phases which includes the responsibilities and information requirements during different phases, and effective transition between phases c) establishing a public information intelligence cell within the Public Information Functional Service Group; and d) identifying tools or resources to monitor social media |
REC295-1295 | 32 - Doctrine, standards, and reform | That resources be provided to support the implementation of recommendations in the South Australian Levee Bank Management Issues Paper (DEWNR, 2015) including: a) development of relevant policy; and b) identification of responsibilities in relation to levee management and flood mitigation |
REC295-1335 | 12 - EM agency and authority | Explore alternative emergency management models including the alternative model proposed above to establish a South Australian Emergency Management Office and State Relief and Recovery Office within the South Australian Fire and Emergency Services Commission, to ensure that all the objects and guiding principles of the Emergency Management Act 2004, and State Emergency Management Plan are addressed efficiently and effectively. |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1311 | 32 - Doctrine, standards, and reform | That the State Emergency Management Plan be reviewed and updated including: a) a better description of the responsibilities of Hazard Leaders Page xx b) establish a mechanism for a hazard leader to identify systemic failures in coordination of their hazard, with a clear process to raise those issues with SEMC and seek a remedy c) establish resilience as a key heading in the plan, with clearly documented strategies and responsibilities; and d) consider the Schar/Mulroney submission and taking a ‘fresh eyes’ approach |
REC295-1282 | 32 - Doctrine, standards, and reform | That the Office for Digital Government, in close partnership with telecommunications companies (e.g. Telstra, Optus, Vodaphone), develop a Control Agency Plan for Information and Communication Technology including mobile communications. The plan should consider: |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1292 | 32 - Doctrine, standards, and reform | That, giving consideration to the previous recommendation, the Flood |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1310 | 32 - Doctrine, standards, and reform | That additional guidance be provided in the State Emergency Management Plan regarding the activation, structure and operation of Zone Emergency Support Teams. This should include: a) the reporting relationship between the Zone Emergency Support Teams, the State Emergency Centre and the State Coordinator b) briefing requirements between the State Coordinator (or their representative) and the Zone Emergency Support Teams when the State Emergency Centre is activated c) responsibilities for provision of local public information; and d) the appointment of public information officers in Zone Emergency Support Teams (where there is no incident management team (established) to provide information to local communities |
REC295-1281 | 32 - Doctrine, standards, and reform | In order to increase resilience and public safety during emergencies, the State Emergency Management Committee should request the Australia and New Zealand Emergency Management Committee to place on the agenda, and consider establishing a national position, on redundancies for mobile communications (including phone tower back-up power) and the National Broadband Network. |
REC295-1325 | 12 - EM agency and authority | Review and reinstate the State Emergency Management Training Officer and State Emergency Management Planning Officer (capability development) positions to operate with a broad, strategic and leadership focus. |
REC295-1290 | 32 - Doctrine, standards, and reform | Continue development of the Damage Assessment Support Plan to: |
REC295-1333 | 32 - Doctrine, standards, and reform | Develop a State Relief and Recovery Plan as a distinct part of the State Emergency Management Plan which should include: a) potential locations for suitable facilities for relief and recovery centres which: are in locations safe from hazards such as flooding and bushfire; and, have appropriate access and suitable ablutions. b) formalisation of roles and capabilities of non-government organisations such as Red Cross |
REC295-1309 | 32 - Doctrine, standards, and reform | That members of Emergency Management Council ensure they are prepared to undertake their roles and responsibilities during emergency events, including establishing: a) contingencies for communication e.g. satellite phone b) access to relevant documents such as the State Emergency Management Plan, supporting plans, ministerial guidelines, agency plans and contacts in hard copy and/or portable device c) formalised arrangements for briefings (up and down), and d) arrangements for suitable representation e.g. relevant Chief Executive(s) or their deputy, at all Emergency Management Council meetings . |
REC295-1280 | 32 - Doctrine, standards, and reform | That a State Plan be developed for managing the consequences of a black system event or other major power outage. The plan should include: |
REC295-1323 | 32 - Doctrine, standards, and reform | Review and update the role, function, workload and focus of the groups/committees that contribute to incident management and emergency management capabilities including the State Emergency Management Training Committee, Interagency Incident Management Sub-Committee and the Central Exercise Writing Team. |
REC295-1289 | 32 - Doctrine, standards, and reform | That SA Police, emergency services, health facilities, utility providers and other key service providers, review their Business Continuity Plans giving consideration to factors such as: a) identification of: business critical needs; essential services power requirements; back-up power requirements for all facilities including State, regional and local facilities such as Police, SES, MFS and CFS stations; the need for any arrangements for back-up power to be included in contracts for design and or lease of Government premises b) contingencies for black system events and extended power outages c) regular back-up generator testing regime protocols, including testing under load and for long durations d) contingencies for communications when mobile, landline and/or radios are not operational e.g. satellite phones; and e) alternative State control centre facilities that are pre-identified, equipped and have procedures for moving to the alternative facility. |
REC295-1332 | 32 - Doctrine, standards, and reform | Develop a Disaster Waste Management Plan to form part of the State Emergency Management Plan which describe participating agencies and responsibilities for various aspects of waste management during and after emergencies. |
REC295-1301 | 32 - Doctrine, standards, and reform | Establish an ‘Interstate Deployment Support Plan’ for incoming interstate resources. The plan should outline responsibilities and arrangements for this function. Consider including this plan into the State emergency management arrangements. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1322 | 12 - EM agency and authority | Consider opportunities to identify synergies between the incident management systems used in SA being the, Australasian Interservice Incident Management System (AIIMS) and ICCS Plus. This might include joint training and exercising in roles that are common across both systems. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1829 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment should develop guidelines for streamlining the permitting system for works on waterways for incorporation in the revised Victoria Flood Management Strategy. An exemption process will be introduced, with particular application to identified reaches of rivers and streams that require ongoing vegetation management and maintenance: |
REC217-1828 | 32 - Doctrine, standards, and reform | The revised Victoria Flood Management Strategy should clearly articulate the policy guidelines for the management of vegetation and debris in Victorian waterways, for the purposes of flood protection and mitigation, taking into account the localised potential flooding effects of in‐stream vegetation in townships. |
REC217-1838 | 32 - Doctrine, standards, and reform | That statements of obligations, issued under the Water Industry Act 1994 for water authorities, be amended to include a provision whereby managing authorities must: |
REC217-1820 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop guidelines for the management of levees in emergencies, during and after a flood event, which can be incorporated into local flood response plans. The department will also provide, as part of these guidelines, a set of criteria for assessing the ongoing viability of ad hoc levees post‐flood. The Emergency Management Act 1986 will be amended to support the implementation of these guidelines. A more effective means for councils to remove illegal levees will also be examined by the Department of Sustainability and Environment. |
REC217-1837 | 32 - Doctrine, standards, and reform | The state government give consideration to enacting legislation to provide protection from legal liability for public authorities conducting works on priority levees in good faith, acting reasonably and responsibly in the public interest, and in accordance with standards agreed to under approved schemes. Public authorities should not be excluded from liability if they have acted negligently. |
REC217-1834 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop clear policy for the coordinated management of rural drainage, clarifying the legal framework, and identifying authorities with responsibility for the management and ongoing maintenance of formal schemes, and their development: |
REC217-1830 | 32 - Doctrine, standards, and reform | The Department of Sustainability and Environment will develop a code of practice on the removal of vegetation around critical public assets, in consultation with councils, CMAs and asset managers. Regional Flood Strategies will support this code of practice as part of shared flood risk management planning. |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0454 | 32 - Doctrine, standards, and reform | the State Emergency Response Coordinator further develop the Strategic Emergency Management Assurance Team process by involving subject matter experts from relevant emergency management control agencies who are the subject of Strategic Emergency Management Assurance Team focus. |
REC199-0484 | 32 - Doctrine, standards, and reform | the state: • assess current risk and risk mitigation strategies for essential services, with a focus on ensuring that risks are appropriately identified at all levels of emergency planning; and • ensure that the responsible authority or owner/ operator of essential services put in place appropriate strategies to mitigate any risk to service continuity |
REC199-0461 | 32 - Doctrine, standards, and reform | the state ensure: • water rescue/swift water rescue definitions, roles and responsibilities are clarified and communicated to all stakeholders to ensure common understanding • appropriate training, equipment and support is provided to those required to perform water rescue/swift water rescue. Common training programs, standards and accreditation should be utilised wherever possible to increase potential for joined up operations and maximised capability • that based upon the experiences of these flood events, an appropriate level of water rescue capacity and capability is established and maintained • flood plans (all levels) and flood emergency response planning incorporate consideration of pre-positioning of appropriate water rescue capability in the event that such services should be required; and • that revised water rescue roles, responsibilities and arrangements are clearly defined in the Emergency Management Manual Victoria and such definitions are replicated in all individual agency planning and operational documents |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0443 | 32 - Doctrine, standards, and reform | the state reconfigure the Victorian Emergency Management Council and the supportive committee arrangements to ensure a comprehensive, accountable, effective and integrated approach to the development of emergency management arrangements is in place for Victoria. The process should also include consideration of the Security and Emergencies Committee and Central Government Response Committee roles, functions, reporting arrangements and relationships with other state level emergency management groups. Settled arrangements must be clearly articulated to ensure stakeholder understanding. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |
REC199-0442 | 32 - Doctrine, standards, and reform | the state appoint a state emergency controller who is ultimately accountable for all major emergencies. |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0459 | 32 - Doctrine, standards, and reform | the state undertake a complete review of emergency management legislation. This should include agencyspecific emergency management legislation and should focus on service interoperability and securing an ‘all hazards, all agencies’ capability |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0469 | 32 - Doctrine, standards, and reform | the state update the current fire specific guidelines and resources for evacuation planning to take an ‘all hazards’ approach |
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0457 | 32 - Doctrine, standards, and reform | the state: • revise the Emergency Management Team Practice Note to include a template to ensure an appropriate and consistent approach to Emergency Management Team operations • provide the revised Emergency Management Team Practice Note to all stakeholders to enable familiarisation; and • ensure that there is regular exercising of Emergency Management Teams with an `all hazards’ focus. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0467 | 32 - Doctrine, standards, and reform | the state review and align all policies and procedures for evacuation, such as the interim evacuation guidelines and the State Health Emergency Response Plan, to ensure consistency and to clarify roles and responsibilities. |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0456 | 32 - Doctrine, standards, and reform | the state: • ensure an ‘all hazards, all agencies’ approach to Incident Action Plan compilation is developed and implemented to enable the timely issue of functional Incident Action Plans. All agency incident action planning processes should be standardised to the fullest extent possible, including consideration of a library of pro-forma Incident Action Plans; and • develop and implement mechanisms to test and ensure that agencies possess satisfactory incident action planning capability and capacity for ‘all hazards’ at all levels of operations. |
REC199-0487 | 32 - Doctrine, standards, and reform | the state develop and incorporate into emergency management planning regimes plans based on geographic risk, such as sub-regional plans |
REC199-0464 | 32 - Doctrine, standards, and reform | the state develop and implement a strategy that maximises the flexibility and united capacity of the Country Fire Authority and Victoria State Emergency Service to respond to emergencies. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3438 | 32 - Doctrine, standards, and reform | That the port/channel managers coordinate marine emergency management planning in the port and are required to ensure that individual port stakeholder marine emergency management arrangements plans are integrated with the whole of port marine emergency management arrangements. |
REC158-3443 | 12 - EM agency and authority | That emergency services increase their capability/capacity to respond to marine emergencies by undertaking the necessary training, increasing their awareness of port and ship operations and ensuring knowledge of the roles/responsibilities of the relevant authorities and stakeholders. |
REC158-3426 | 32 - Doctrine, standards, and reform | That the nominated marine safety authority, in consultation with the Emergency Services Commissioner, senior emergency services personnel and relevant port stakeholders, is responsible for establishing appropriate performance standards, risk management guidelines and good practice guidelines for marine emergency management. |
REC158-3437 | 32 - Doctrine, standards, and reform | That port/channel managers coordinate marine emergency planning for the port and are required to ensure that marine emergency arrangements are integrated with whole of port emergency management plans. |
REC158-3442 | 12 - EM agency and authority | That emergency services continue to take the lead role in marine emergencies and operate under their respective legislation, the Emergency Management Act and the State’s emergency management arrangements. |
REC158-3425 | 32 - Doctrine, standards, and reform | Consequential or complementary amendments to the Emergency Management Act are required to ensure that: |
REC158-3436 | 32 - Doctrine, standards, and reform | That Harbour Masters are the designated principle marine specialists within the port and work directly with emergency services to provide advice and the interface with the marine legislative powers, to manage a marine emergency. |
REC158-3441 | 32 - Doctrine, standards, and reform | That, where practical, risk assessments, emergency planning, training and exercising are integrated to minimise duplication of effort. |
REC158-3424 | 32 - Doctrine, standards, and reform | That legislation is prepared by the Department of Transport to ensure marine emergency management arrangements are clarified and provide: |
REC158-3435 | 32 - Doctrine, standards, and reform | That Harbour Masters have the appropriate powers, authority, accountability, skills, responsibility and indemnity to provide a coordinated response of marine resources in support of emergency services, except where the nominated marine safety authority is the control agency for a marine pollution or marine casualty emergency. |
REC158-3440 | 32 - Doctrine, standards, and reform | That the Water Division Emergency Response Plan is amended, by the Water Division emergency response coordinator, to provide a framework to coordinate a marine response that crosses declared port water boundaries and requires resource coordination and prioritisation. |
REC158-3434 | 32 - Doctrine, standards, and reform | That the accountability relationship between Harbour Masters and the Director of Marine Safety is strengthened in the relevant legislation. |
REC158-3439 | 32 - Doctrine, standards, and reform | That the port marine emergency management arrangements are integrated with the Victorian Water Division Emergency Response Plan. |
REC158-3453 | 32 - Doctrine, standards, and reform | That, where applicable, consideration is given to legislative amendment that will enable the findings of this report to be applied to areas inside State waters but outside commercial port waters. |
REC158-3427 | 32 - Doctrine, standards, and reform | That the standards and guidelines determined by the nominated marine safety authority require port/channel managers to conduct a marine emergency risk assessment using AS/NZ 4360:2004 Risk Management and, in addition, must require port/channel managers to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC125-3900 | 12 - EM agency and authority | That agencies integrate condition information into their asset management decision-making practices and use it as the basis for validating asset valuations and depreciation calculations. |
REC125-3895 | 32 - Doctrine, standards, and reform | That all agencies develop drainage asset management plans, consistent with best practice, and that these incorporate: |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3995 | 32 - Doctrine, standards, and reform | That the standard double arrester, fitted to the locomotives during the summer months, be subjected to more careful daily inspection before and after each journey during such months, in addition to the present periodical examination by the locomotive foreman and boiler inspector; and that any omission of this duty on the part of the running staff be severely punished. |
REC004-3993 | 32 - Doctrine, standards, and reform | That in any case where there is primá facie evidence of a fire, creating damage to the extent of $100 or upwards in value, having been caused by the escape of particles of lighted matter from a locomotive engine, or by the action of railway employes in burning off grass or other inflammable material along any line of railway, a Special Board of Inquiry shall investigate and report on the subject, such Board to consist of a Police Magistrate as Chairman, with a railway officer and a competent person chosen from outside the State service as members. |
REC004-4000 | 32 - Doctrine, standards, and reform | That section 22 of the Police Offences Act 1890 be amended, to enable the burning of grass and debris along the railway lines in the summer season to be carried out at an earlier hour than two o'clock in the afternoon, when, in the judgement of the railway inspectors, it is safe and necessary to do so. |
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |