Rec-ID | Code | Recommendation | |
---|---|---|---|
REC323-4280 | 37 - Funding | That the NSW Government work with local governments to identify alternative routes to vulnerable roads, and that the NSW and Australian Governments fund the construction of these important routes to improve evacuation and access options in times of disaster. |
|
REC323-4266 | 1 - Land-use and building regs | That the NSW Government review the provision of temporary and long term housing options provided to those affected by the February-March 2022 floods, with a view to: • ensuring a range of options are identified and embedded within emergency and recovery plans, so that solutions can be implemented as soon as possible after a natural disaster • ensuring that housing options meet individual and community needs • removing planning impediments that prevent those from accessing more safe and secure housing in times of crisis. |
|
REC323-4281 | 37 - Funding | That the NSW Government allocate funding to the improvement of the Pitt Town Evacuation Route and other key possible evacuation routes in Sydney's northwest. |
|
REC323-4267 | 1 - Land-use and building regs | That the NSW Government consider investing in supporting relocations, land swaps and providing fair and adequate compensation for landowners who wish to relocate from severely flood-impacted areas. |
|
REC323-4282 | 16 - Training and behaviour | That the NSW Government invest in the required personnel, training and vessels to ensure that all agencies involved in flood rescue can be mobilised to their fullest potential. |
|
REC323-4270 | 37 - Funding | That the NSW Government consider entering into a service agreement with an organisation that has the resources and capacity to manage donations and activate quickly during natural disasters. |
|
REC323-4257 | 1 - Land-use and building regs | That the NSW Government work with local government, industry and sustainable planning experts, including the Government Architect, on policy initiatives in the New South Wales planning system that will help deliver more resilient and sustainable homes, buildings and places. |
|
REC323-4291 | 12 - EM agency and authority | That the NSW Government consider abolishing Resilience NSW if it is unable to ensure: |
|
REC323-4272 | 37 - Funding | That the NSW Government ensure that flood affected individuals can continue to access financial assistance for as long as there is demonstrated need. |
|
REC323-4258 | 39 - Disaster Risk Management | That the NSW Government significantly increase its investment in flood mitigation and preparation, including its support of local governments to do the same, by: • increasing ongoing, long term funding and access to technical guidance and assistance for local councils • ensuring that land-use planning and development takes a risk-based approach. |
|
REC323-4292 | 12 - EM agency and authority | That the NSW Government consider a restructure of the NSW State Emergency Service with consideration to: realigning the focus of the organisation to harness local knowledge and networks; coordinating more closely with other rescue agencies to bolster its capacity to respond; and increasing salaried staff and resources, and driving volunteer recruitment. |
|
REC323-4279 | 37 - Funding |
|
|
REC323-4261 | 37 - Funding | That the NSW Government advocate through the National Cabinet to widen eligibility under the Disaster Funding Recovery Arrangements to allow local councils to build back better. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1205 | 16 - Training and behaviour | Department of Premier and Cabinet Regional Coordinators: Continue to build the capability of the Department of Premier and Cabinet Regional Coordinator role in recovery operations by providing: · on the ground support for Regional Coordinators during recovery operations by REMOs or OEM Recovery Team · training and developmental opportunities for Regional Coordinators to prepare them for working in the disaster recovery environment. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1154 | 36 - Volunteers | Coordination of Volunteer Support |
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0798 | 32 - Doctrine, standards, and reform | Optimise the configuration of a raised Warragamba Dam for flood mitigation of the full range of flood events and water supply, with due consideration of upstream impacts. |
REC238-0814 | 1 - Land-use and building regs | Develop a NSW Planning Policy and Guideline to improve land use planning practices on flood prone land. |
REC238-0797 | 32 - Doctrine, standards, and reform | Determine the appropriateness and the steps required to allow the reduction of full supply level by up to five metres and/or the implementation of alternative gate operation at Warragamba Dam for the mitigation of minor to moderate flood events in the short-term. |
REC238-0808 | 1 - Land-use and building regs | Ensure future road infrastructure planning considers flood evacuation requirements throughout the Hawkesbury-Nepean floodplain. |
REC238-0803 | 32 - Doctrine, standards, and reform | Ensure effective flood gauging arrangements in the Hawkesbury-Nepean Valley |
REC238-0801 | 1 - Land-use and building regs | Establish a dedicated group or body within an existing agency to provide a more integrated, coordinated and regional approach to land use, infrastructure and evacuation planning and flood modelling in the Hawkesbury-Nepean Valley. |
REC238-0816 | 1 - Land-use and building regs | Ensure appropriate consideration of flood risk in regional and subregional planning |
REC238-0800 | 1 - Land-use and building regs | Improve regional transport infrastructure to address current and projected flood evacuation capacity constraints and timelines. |
REC238-0815 | 1 - Land-use and building regs | Provide improved land use planning tools for managing flood prone land. |