REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1313 | 16 - Training and behaviour | That regular training and exercising is conducted for all State Emergency Centre participants including Liaison Officers. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1303 | 16 - Training and behaviour | That the State Emergency Service be provided with resources to enable them to deliver swiftwater awareness training to all first responders including emergency services, SA Police and council crews. |
REC295-1334 | 33 - Relief and recovery | Conduct a review into South Australia’s arrangements for relief and recovery grant, Local Government Disaster Recovery Assistance Arrangements and Natural Disaster Relief and Recovery Arrangement claims, the review should include governance coordination and criteria for provision and processing of relief/recovery grants |
REC295-1275 | 33 - Relief and recovery | That SA Health, develop an emergency plan to manage an extended power outage or black system event which, in addition to the requirements outlined in recommendation 16: |
REC295-1294 | 13 - Mapping and data quality | That consideration and resources be given to support the implementation of recommendations in the report prepared on behalf of Department of Environment, Water and Natural Resources (Australian Water Environments, 2016), for flood warning classification of stream gauges and other locations. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1293 | 13 - Mapping and data quality | That the Flood Reform Task Group identify an appropriate mechanism for stakeholder agencies (including the State Emergency Service, Department of Environment and Natural Resources, Bureau of Meteorology and SA Water, as a minimum) to share data and information and develop plans and strategies for management of water levels in reservoirs and spill management during floods in South Australian water catchments |
REC295-1324 | 16 - Training and behaviour | Establish a State incident management and emergency management training capability which provides for: a) consistent training across the State b) personal development and endorsement processes for roles c) identification, recruitment and development of personnel from other government agencies; and d) incident management and State emergency centre functional role training and development across all sectors. e) skills maintenance including upskills, refresher training and exercises f)incident and strategic leadership training g) consistent training for inter-agency liaison officers at all levels |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1321 | 16 - Training and behaviour | Through the Emergency Management Workforce Project, identify and provide training and development for SA’s emergency management sector personnel (government agencies, and non-government agencies including volunteers). State Emergency Management Committee should consider supporting recommendations from stage two of the project when the project report is tabled. |
REC295-1284 | 16 - Training and behaviour | Deliver consistent and regular training in the use of the SA Government Radio Network to all users to maximise the efficiency and effectiveness of the network in times of emergency e.g. reduce the issues associated with network busy signals. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
Rec-ID | Code | Recommendation |
---|---|---|
REC250-0795 | 33 - Relief and recovery | Regional Development Victoria should implement the recommendations from the Department of Planning and Community Development's review of the Community Recovery Fund to improve the delivery of relief and recovery programs in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC217-1809 | 1 - Land-use and building regs | All priority public levees not currently the subject of approved schemes, will become subject to approved schemes under Division 5, Part 10 of the Water Act 1989. Such schemes will articulate an agreed set of terms, including: |
REC217-1815 | 1 - Land-use and building regs | A regular inspection and maintenance regime will be undertaken for all high priority levees managed by a public authority. All such levees will be inspected by the relevant public authority on an annual basis, and after a flood event. All levees will have a regular maintenance schedule. |
REC217-1831 | 1 - Land-use and building regs | Significant modification of waterways in urban or rural areas will only be considered after the completion of a flood risk management process, undertaken in consultation with members of the community. |
REC217-1808 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should provide a strategic framework for the management and ongoing maintenance of Victoria’s levees. The Victoria Flood Management Strategy will provide criteria for a consistent statewide approach to the prioritisation of the state’s levees for future management and investment: |
REC217-1813 | 1 - Land-use and building regs | The Department of Sustainability and Environment will develop guidelines for streamlining the permitting system for conducting works on levees for incorporation in the revised Victoria Flood Management Strategy, in order for maintenance on all levees to occur more quickly. The guidelines will outline circumstances in which exemptions from current approval processes are appropriate. Councils will be permitted to obtain exemptions within their planning schemes for: |
REC217-1826 | 39 - Disaster Risk Management | A revised Victoria Flood Management Strategy should identify and assign roles and responsibilities for the management and ongoing maintenance of Victoria’s waterways, for the purposes of flood protection and flood mitigation: |
REC217-1807 | 1 - Land-use and building regs | A revised Victoria Flood Management Strategy is needed and should clearly articulate the principles, roles and responsibilities for the ownership, management and ongoing maintenance of Victoria’s levees. Neither land tenure nor prior government involvement will dictate ownership of public levees: |
REC217-1812 | 1 - Land-use and building regs | Streamlined processes to enable access to levees for the purposes of conducting works, including maintenance, must be implemented. Where a levee is managed by a public authority as part of a formal scheme, and is sited on either private land, or on a mixture of public and private land, access to private land for works will be negotiated as part of any scheme agreement. Where a levee is sited on public land, but is not managed by a public authority, local beneficiaries willing to conduct maintenance will be given access to do so, provided: |
REC217-1821 | 1 - Land-use and building regs | Where flood investigations show positive and cost effective outcomes, infrastructure providers, such as VicRoads, will consider enhancing their infrastructure to act as levees. Any development of this nature will require collaboration with, and the approval of, the relevant floodplain authorities. |
REC217-1811 | 1 - Land-use and building regs | Responsible authorities will identify low priority levees for potential removal, and have them removed when funding becomes available. |
REC217-1818 | 1 - Land-use and building regs | The Department of Sustainability and Environment to review ownership of Grampians Wimmera Mallee Water’s Yarriambiack Creek levee, with a view to the appointment of a more suitable public managing authority/authorities. |
REC217-1810 | 1 - Land-use and building regs | Where a levee has been identified as low priority, and beneficiaries are not willing to contribute to its maintenance, public authorities will inform levee beneficiaries that they will not fund the repair of their levee following a flood event. |
REC217-1817 | 1 - Land-use and building regs | The current technical guidelines for the construction of levee systems will be reviewed. A revised Levee Design, Construction and Maintenance technical guidelines will include guidelines for the construction of both priority public levees, and private levees on private land, such as ring levees, which protect key assets. These guidelines will be made available to all rural councils, who will make landowners constructing new levees on their property aware of the principles and specifications contained in the guidelines and encourage construction based on them. |
REC217-1832 | 1 - Land-use and building regs | The revised Victoria Flood Management Strategy should clearly identify authorities and assign responsibilities for stream blockage and debris removal in waterways posing a high risk to public infrastructure both during and after a flood: |
Rec-ID | Code | Recommendation |
---|---|---|
REC216-2868 | 14 - Incident Mgt Teams | Agency incident management preparedness: a more comprehensive approach to planning, including the number of personnel, their training and better use of on-the-ground intelligence in the affected areas that enables immediate and strategic decision-making to be concurrent processes. |
REC216-2867 | 14 - Incident Mgt Teams | Agency incident management preparedness: refining IT tools to process the intelligence. |
REC216-2866 | 14 - Incident Mgt Teams | Agency incident management preparedness: provide clarity and certainty in specific roles and responsibilities for each agency. |
Rec-ID | Code | Recommendation |
---|---|---|
REC199-0413 | 14 - Incident Mgt Teams | the state clarify the role of intelligence cell staff (for example, hydrologists and/or Catchment Management Authority) who are utilised in Incident Control Centres during flood events |
REC199-0478 | 33 - Relief and recovery | the state amend the current protocol governing National Registration and Inquiry System information collection and sharing to: • clarify the role of councils and Centrelink during and after emergencies • ensure the amended protocol is written in plain English and easily understood; and • coordinate, in conjunction with the state and federal privacy commissioners, the development of a new National Registration and Inquiry System information sharing protocol in line with the proposed National Registration and Inquiry System 6 and state or federal privacy legislation. |
REC199-0429 | 13 - Mapping and data quality | the state take into account any outcomes from the Commonwealth Government’s flood mapping reviews in the continual development of the Victorian flood database and to incorporate into the database flood data currently held by Melbourne Water. |
REC199-0489 | 33 - Relief and recovery | the state implement arrangements to improve the support provided to local government on disaster financing before, during and after emergency events. |
REC199-0463 | 16 - Training and behaviour | the state: • ensure an appropriate regime of regular emergency management training and exercising is introduced. This must be ‘all hazards’ and multi-agency focused and include all relevant stakeholders • designate an accountable officer to hold ongoing responsibility for conducting such exercises; and • designate the Emergency Services Commissioner as holding ongoing responsibility for auditing and reviewing this training and exercising. |
REC199-0408 | 13 - Mapping and data quality | the state, in consultation with Bureau of Meteorology and Melbourne Water, take the necessary action to ensure that all flood warnings issued are linked to the geographical location of the gauge the data was derived from. |
REC199-0476 | 6 - Insurance and legal liability | the Department of Planning and Community Development examine strategies to address and clarify insurance coverage of community volunteers in emergency events |
REC199-0420 | 13 - Mapping and data quality | the state establish standards for flood mapping to ensure they are kept contemporary and meet the purposes of landuse risk planning and emergency response. In doing so, maps should extend where appropriate to include Probable Maximum Flood, over a range of Annual Exceedence Probability levels and be explicitly linked to a stream gauge. |
REC199-0488 | 33 - Relief and recovery | the Department of Human Services develop proactive strategies to provide information and assistance for people applying for emergency grants. |
REC199-0462 | 16 - Training and behaviour | the state introduce a joint emergency management leadership training program that will deliver critical core competencies for all levels of management of major emergencies. Future appointments to senior operational emergency management positions should require successful accreditation at the appropriate level. |
REC199-0475 | 16 - Training and behaviour | the Department of Planning and Community Development review the volunteer register and examine additional options to support councils in volunteer management, including the development of tools and staffing support. |
REC199-0417 | 13 - Mapping and data quality | the state ensure that regional and local flood plans incorporate all available flood mapping and intelligence, including assessments of levees and flood consequence information. |
REC199-0485 | 1 - Land-use and building regs | the state: • adopt a strategy to expedite incorporation of updated flood mapping or modelling into planning schemes • reconsider in what circumstances the ‘1 in 100 year event’ is the appropriate design event • actively support the Australian Building Code Board in its development of a new national standard for residential buildings in flood prone areas. Until such time as any new standard is incorporated into Victorian law, provide advice to householders about appropriate building materials for flood prone areas and ways that houses can be designed or adapted to mitigate flood risk; and • retain the ability of a Catchment Management Authority to require a council to refuse a planning permit or impose particular conditions when the Catchment Management Authority considers the flooding risk to be unacceptable. |
REC199-0460 | 6 - Insurance and legal liability | the state formalise and continue the Emergency Response Legal Advisers Forum. |
REC199-0474 | 33 - Relief and recovery | the state, in respect of the Rapid Impact Assessment process: • resolve which agency/ies has policy and operational responsibility for this process • define the purpose of Rapid Impact Assessment; and • review the process, in light of the 2010–11 floods, to examine options to improve the efficiency of the collection of information. |
REC199-0415 | 16 - Training and behaviour | the state ensure that all personnel who are likely to become involved in incident management teams for floods receive basic flood awareness training prior to such involvement. |
REC199-0480 | 33 - Relief and recovery | the state clarify the transition to recovery arrangements including the processes for approving and funding of essential works after transition to recovery has been formalised. |
REC199-0448 | 16 - Training and behaviour | the state ensure that sector wide familiarity and understanding of the various systems for incident management is developed and maintained. Primarily, this should be achieved through multi-agency emergency management training and exercising involving usage of the various agency incident management systems. |
REC199-0491 | 33 - Relief and recovery | the state: • ensure that the concerns raised by Victorians regarding the Natural Disaster Relief and Recovery Arrangements are provided to the national review, including the issues of: – betterment (what it means and how it is applied); and – the 51 per cent income rule for eligibility of businesses for grants. • establish a single point of information (such as the single web portal referred to in recommendation 33) on all emergency related financial assistance available to individuals, businesses and local government. The means of accessing this information should be widely circulated in the community. |
REC199-0473 | 33 - Relief and recovery | the state make available to the public a clear guide of who is responsible for: • clean-up and recovery of various types of infrastructure that straddle the public/private boundary; and • the policies agencies will follow in determining whether to repair infrastructure under their control. |
REC199-0414 | 16 - Training and behaviour | the state ensure that all personnel who, because of their particular flood expertise, are likely to be potential participants in an Incident Control Centre are familiar with the requirements of the Australasian Inter-service Incident Management System structure |
REC199-0479 | 33 - Relief and recovery | the state review the way early outreach occurs and implement changes that will ensure that there is a consistency of approach regardless of which agency undertakes the service. |
REC199-0441 | 4 - Fire season preparation | the state undertake further trials to explore the opportunity for greater use of social media as a credible source of information to and from the public during an emergency |
REC199-0490 | 33 - Relief and recovery | the state finalise the 2008 review of Victoria’s municipal assistance. This should include addressing: • the provision of upfront funding for local councils for repair of community assets • packages for early relief and recovery to be included in both the Natural Disaster Funding Arrangements and the Natural Disaster Relief and Recovery Arrangements, including outreach packages; and • the process of reimbursement of local councils after floods. |
REC199-0472 | 33 - Relief and recovery | the state review the legislation and policies that set out clean-up and recovery responsibilities for infrastructure such as crossovers, culverts, drains, bridges and waterways, including consideration of: • whether the entities who are given obligations or powers to undertake clean-up works have the capacity to do so; and • the appropriateness of having different legal regimes for what is essentially the same piece of infrastructure. If the review reveals that the current responsibility matrix is inadequate, the state develop an action plan to address the identified shortcomings. |