Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC309-2478 | 25 - Inquiry, audit, lessons management and after action review | The progress of recovery for this event be reviewed incrementally over the next 2 to 3 years, with a formal, independent report provided on the effectiveness of the recovery after 3 years. |
REC309-2477 | 21 - Role of Commonwealth Government | The Department of Housing and Public Works should be included within Local Disaster Management Group evacuation centre planning and plans and assist with decision making around the relocation of evacuees from evacuation centres. |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4003 | 35 - Business and Industry in relation to industry | Where gas exists, and no provisions are made for its constant removal, no shots should be fired, and, where permitted in a gassy mine, shots should be fired only by a man specially appointed, and at such hours when the miners are not within the mine. All shots should be tamped by stone well damped, and only copper or wooden tools should be employed. As far as possible the use of explosives should be discouraged, and skilful mining encouraged. Danger-boards should be placed further from the faces whence gas issues (say), where practicable, 50 yards. |
REC002-4002 | 19 - Offences | Where safety-lamps are necessary - gas being present for (say) one month after being found in dangerous quantity - they should be securely locked by a man duly appointed, and tampering with them must be punishable by a simple and inexpensive process of law. |
REC002-4013 | 19 - Offences | Infringement of the regulations by either party should be followed by a summary form of justice, instituted before two Magistrates. |
REC002-4001 | 35 - Business and Industry in relation to industry | The Commission consider that in all mines where gas exists the course of the air should be directed to sweep along the working-faces; in mines worked by Pillar and Stall, bratticing must be resorted to to carry the gas from the face as it issues, and so prevent any accumulation of explosive gases or of gases inimical to life. In cases where gas exists it would be better that no bords should be broken off the back or return heading or supplied with air fouled by dangerous gases. The panel system of working by confining and localising districts, or some modification thereof, might be pursued with advantage. |
REC002-4010 | 35 - Business and Industry in relation to industry | The Commission do not approve of removing any responsibility from the management by increasing the power or number of the Inspectors. The visits of these officials should, so far as possible, be visits of surprise. |
REC002-4008 | 35 - Business and Industry in relation to industry | Where dust exists in quantity, and under conditions favourable for ignition, it should be periodically and sufficiently dampened by water |
REC002-4004 | 35 - Business and Industry in relation to industry | Where safety-lamps are used, and the obligation is laid upon the men to cleanse the same, all examinations, tests, and repairs to these should be done by the owners. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1291 | 24 - Govt responsibility | That the Flood Reform Task Group, as proposed by the Department |
REC295-1316 | 24 - Govt responsibility | That the position of Deputy Director, Office for Digital Government is dedicated to the Office for Digital Government; and that people throughout DPC are identified and trained to perform appropriate roles within the State Crisis Centre |
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
REC295-1288 | 24 - Govt responsibility | That Attorney General’s Department explore options to overcome fatigue and welfare issues of SAGRN staff associated with emergency events of extended duration. |
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
REC295-1274 | 35 - Business and Industry in relation to industry | That relevant agencies, such as the Department of State Development, SA Police and emergency services, collaborate to establish an education campaign to encourage businesses in South Australia to develop Business Continuity Plans which, among other potential hazards such as flood and fire, also take into account the potential impact of an extended power outage. |
REC295-1326 | 14 - Incident Mgt Teams | Establish a State-wide resourcing capability to support incident management teams, regional coordination centres, zone emergency centres, relief centres, recovery centres and State control centres. some of the features of such a capability should include: a) multi-agency, cross-government, State-wide pool of incident management and emergency management personnel building on the State incident management team concept currently facilitated by the Country Fire Service, and expanded to include all hazards, multiagency teams with a roster that provides year-round coverage b) a system that enables staff and volunteers from any agency to identify their availability for upcoming shifts c) a rostering system that enables one or more incident management teams, staging areas, regional coordination centres, State control centres and relief centres to develop, maintain and distribute rosters and structure charts in a more coordinated manner d) identifying areas of expertise for key incident and emergency management functions (e.g. public information, alerts and warning, media liaison, logistics and resource management) that would benefit from a coordinated and resource pooling approach and take steps to implement (consider the Mapping Functional Support Group model as a potential service delivery model). |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1312 | 24 - Govt responsibility | That the Department of Education and Child Development be included as a member of State Emergency Management Council and represented in the State Emergency Centre. |
REC295-1319 | 24 - Govt responsibility | That a single emergency service multi-agency control centre be established with sufficient capacity and capability to deal with all types of emergency incidents in SA. Also consider Police and State Emergency Centre. |
REC295-1285 | 7 - Inter-agency communication | Identify, document and communicate contingency arrangements and procedures for emergency services in the event SA Government Radio Network paging is turned off to conserve power, or other loss of paging capacity. |
REC295-1308 | 24 - Govt responsibility | That the Department of the Premier and Cabinet revise the ministerial documents relating to emergency management. |
REC295-1318 | 24 - Govt responsibility | That the recommendation made following the Pinery bushfire, ‘to review control facilities at State, region and incident level’, be expanded to include all emergency services facilities that will be utilised for major incidents other than bushfire e.g. flood and earthquake and to also be extended into metropolitan areas, and implemented. |
REC295-1283 | 7 - Inter-agency communication | Consider bringing other agencies onto the SA Government Radio Network, in particular, Department of Education and Child Development and local government, to support more effective coordination and provide a reliable communications contingency during emergencies. |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
Rec-ID | Code | Recommendation |
---|---|---|
REC281-1201 | 25 - Inquiry, audit, lessons management and after action review | Preventing Flood Related Fatalities: The NSW Government consider the recommendations from the Preventing Flood Related Fatalities Report when it is released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC272-1415 | 25 - Inquiry, audit, lessons management and after action review | An audit of all local government areas vulnerable to storm tide events is completed and opportunities identified to resolve gaps in evacuation zone planning to ensure consistency with the Queensland Evacuation Guidelines for Disaster Management Groups and neighbouring local government areas. |
REC272-1420 | 24 - Govt responsibility | The Department of Housing and Public Works should consider preparing an annual communique to asset owners of, and local governments with access to public cyclone shelters, outlining the maintenance and certification process and pre-season status. |
REC272-1418 | 24 - Govt responsibility | A state-wide engagement strategy is coordinated to ensure community messaging is consistent across all levels of Queensland’s disaster management arrangements. |
REC272-1416 | 24 - Govt responsibility | A state-wide strategy, including a common definition, is developed for identifying and engaging vulnerable people in emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
REC267-1151 | 24 - Govt responsibility | Government Communications Coordination |
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1157 | 35 - Business and Industry in relation to industry | Improvements to the Targeting of Government Support to Build Primary Industry Resilience |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2561 | 24 - Govt responsibility | The Australian Government amends regulations so that background checks and the requirement to hold an Aviation Security Identification Card are only required for unescorted access to Security Restricted Areas, not for general airside access. This approach would align with international practice. |
REC258-2530 | 24 - Govt responsibility | The Australian Government appoints an additional Australian Transport Safety Bureau Commissioner with aviation operational and safety management experience. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2526 | 24 - Govt responsibility | The Australian Government develops the State Safety Program into a strategic plan for Australia’s aviation safety system, under the leadership of the Aviation Policy Group, and uses it as the foundation for rationalising and improving coordination mechanisms. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC227-2852 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth and the Shire of Christmas Island take steps to ensure that the Ethel Beach boat ramp is significantly upgraded, that it should be provided with shelter in the form of a rock groyne or similar buffer and that provision should be made so that a person can walk beside the ramp on a stable footing; or If this is not considered likely to be effective in providing an appropriate means of deploying a rescue vessel in adverse conditions, such other action be taken as is necessary to ensure that there is a means of deploying a rescue vessel in adverse conditions. |
REC227-2857 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth ensure that there is a mooring buoy which will enable the mooring of SIEVs to take place and free up the Christmas Island response vessel for ongoing surveillance duties. |
REC227-2853 | 21 - Role of Commonwealth Government | I recommend that the Commonwealth liaise closely with representatives of the Christmas Island VMRS prior to purchasing or replacing any vessels for the VMRS in the future. |
Rec-ID | Code | Recommendation |
---|---|---|
REC208-0525 | 7 - Inter-agency communication | That the Office of Environment and Heritage amend its operating procedures for the Environment Line to ensure that there are clear obligations to pass on information relevant to other agencies, to those agencies in a timely manner. |
REC208-0527 | 35 - Business and Industry in relation to industry | That the Office of Environment and Heritage require Orica to engage and fund appropriate independent experts to oversee any modifications to the plant in the next major maintenance overhaul of the plant in 2016 and in any upgrades to the plant prior to that date. |
REC208-0526 | 25 - Inquiry, audit, lessons management and after action review | That OEH’s testing procedures for determining the impact of pollution incidents incorporate additional requirements for the checking and verification of results before those results are released. |
Rec-ID | Code | Recommendation |
---|---|---|
REC189-2913 | 21 - Role of Commonwealth Government | In developing and improving its policies and practices for stakeholder engagement, NOPSA should ensure that: |
REC189-2910 | 21 - Role of Commonwealth Government | NOPSA should: |
REC189-2908 | 21 - Role of Commonwealth Government | To ensure that NOPSEMA is in a strong position to perform its functions effectively: |
REC189-2906 | 21 - Role of Commonwealth Government | In order to improve the effectiveness of National Offshore Petroleum Safety and Environmental Management Authority (NOPSEMA), with similar benefits for State or Territory regulators, attention should be given to the following actions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3448 | 24 - Govt responsibility | That the Director of Marine Safety works with the Australian Maritime Safety Authority to ensure that State and port emergency arrangements interface appropriately with the National Maritime Emergency Response Arrangements. |
REC158-3433 | 24 - Govt responsibility | That Harbour Masters are employed by a government body and remain geographically located at the port. |
REC158-3454 | 24 - Govt responsibility | That the Department of Transport ensures that key stakeholders are engaged during the implementation of the approved Review recommendations. |
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3142 | 19 - Offences | NOPSA should use encouragement as the primary tool of enforcing compliance provided willingness to improve is exhibited by the players. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3143 | 21 - Role of Commonwealth Government | The role of the advisory Board, namely to give advice to Ministers and NOPSA when asked, should be made clear to Board members and all stakeholders. The Board and NOPSA should consider the need for a clear description of who does what based on the legislated responsibilities of the NOPSA CEO. |
Rec-ID | Code | Recommendation |
---|---|---|
REC137-3533 | 21 - Role of Commonwealth Government | Accordingly I recommend that the Federal Minister for Transport, consider engaging an external consultant to assess whether high level intervention is warranted. |
Rec-ID | Code | Recommendation |
---|---|---|
REC121-3710 | 39 - Disaster Risk Management | The ITSRR should have permanent access to the RailCorp intranet. |
REC121-3653 | 10 - Infrastructure | The RMC should be equipped by RailCorp with a transcriber system, or mimic board, or such other system as is necessary to enable identification of the precise location at any time of any train on the RailCorp network. |
REC121-3742 | 19 - Offences | The risk of abuse of internal passenger emergency door releases should be further reduced by introducing significant penalties for any improper use of such an emergency facility. It should be a criminal offence for anyone to use or tamper improperly with an emergency escape facility in a train. |
REC121-3673 | 41 - Emergency Management exercises | Regular field training exercises should be conducted by RailCorp with the emergency services to ensure that the incident command system and rail displan are able to be fully implemented as quickly as possible and are reviewed and improved. |
REC121-3687 | 10 - Infrastructure | There must be compatibility of communications systems throughout the rail network. It is essential that all train drivers, train controllers, signallers, train guards and supervisors of trackside work gangs in New South Wales be able to communicate using the same technology. |
REC121-3767 | 24 - Govt responsibility | All accredited rail organisations should be required to re-apply every three years to ITSRR for accreditation. |
REC121-3700 | 39 - Disaster Risk Management | Maintenance plans on all trains should be revised annually. |
REC121-3652 | 14 - Incident Mgt Teams | A designated staff member at the RMC should act as the rail emergency management co-ordinator. He or she should be the sole point of contact at the RMC with other rail personnel involved in the rail accident and emergency services personnel during the rescue phase of the emergency response. |
REC121-3726 | 25 - Inquiry, audit, lessons management and after action review | The OTSI should continue to conduct rail accident investigations on behalf of ITSRR and report directly to the Chief Executive of ITSRR. |
REC121-3666 | 14 - Incident Mgt Teams | The rail commander should have complete authority to direct and control any rail employees attending the site of a rail accident, in accordance with directions given or arrangements put in place by the site controller, until the rescue phase of the emergency response to the rail accident has been completed. |
REC121-3684 | 39 - Disaster Risk Management | The ITSRR should conduct its own risk assessment in relation to the risk of any such high consequence, low probability accident and, if necessary, direct RailCorp to conduct a further risk assessment to reduce the level of residual risk to a level ITSRR regards as acceptable. |
REC121-3765 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct field audits to satisfy itself that all accredited rail organisations conduct their activities in accordance with the safety management system on the basis of which each was accredited. |
REC121-3695 | 10 - Infrastructure | There should be interoperability of communications equipment between all trains operating on the New South Wales rail network. |
REC121-3651 | 10 - Infrastructure | A dedicated telephone line should be established by RailCorp between the RMC and any Emergency Services Control Centre for use during any emergency. |
REC121-3721 | 24 - Govt responsibility | The ITSRR should ensure that OTSI, as a division of ITSRR, co-operates and assists the ATSB in the conduct of any independent investigation by the ATSB of any rail accident or incident in New South Wales. |
REC121-3665 | 14 - Incident Mgt Teams | The role of the rail commander should be to provide support and assistance to the site controller and emergency services personnel until the rescue phase of the emergency response to any rail accident is completed. |
REC121-3758 | 25 - Inquiry, audit, lessons management and after action review | Following completion of any external audit, a corrective action plan to remedy any identified safety deficiencies should be developed by RailCorp, implemented and followed up within the business groups affected, to ensure appropriate and timely completion of the action plan, by a formal examination of the effectiveness of the controls put in place. Senior management personnel should certify that the corrective action plan has been implemented and is effective. Senior management personnel should be accountable for any such certification. |
REC121-3683 | 39 - Disaster Risk Management | RailCorp should undertake risk assessments of each of its activities as follows: |
REC121-3694 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should conduct random audits of accredited rail organisations for compliance with communications protocols. |
REC121-3720 | 24 - Govt responsibility | The New South Wales Government should make the necessary arrangements with the Australian Government, including any necessary legislation, for the Australian Transport Safety Bureau (ATSB) to have the power to investigate all rail accidents occurring on the New South Wales rail network the investigation of which may advance the knowledge of the causes of rail accidents in Australia. |
REC121-3663 | 14 - Incident Mgt Teams | The incident command system should clearly identify the roles of the rail commander, site controller, police commander and commanders of the other emergency services, and the way in which each is to work together during the recovery phase of any rail accident. |
REC121-3757 | 25 - Inquiry, audit, lessons management and after action review | RailCorp should conduct internal and external safety audits to evaluate the adequacy of its safety management system and to ensure that any risk control measures are effective. |
REC121-3678 | 35 - Business and Industry in relation to industry | All railway owners and operators should have a quality assurance program for the design and construction of rolling stock and regular review of construction to ensure that the rolling stock satisfies the original functional performance specifications. |
REC121-3693 | 25 - Inquiry, audit, lessons management and after action review | ITSRR should ensure that, as a condition of accreditation, each of these recommendations is carried into effect and should audit against them to enforce compliance. |
REC121-3713 | 25 - Inquiry, audit, lessons management and after action review | Recommendations one to seven of the final report of the Special Commission of Inquiry into the Glenbrook Rail Accident should be fully implemented, save that the random auditing referred to in recommendations five and seven should be carried out by ITSRR. |
REC121-3657 | 10 - Infrastructure | All signal telephones must be maintained by RailCorp in proper working order. |
REC121-3753 | 25 - Inquiry, audit, lessons management and after action review | The RailCorp Board should establish independent external safety auditing processes to regularly audit and report to the Board on the implementation of an integrated safety management system by RailCorp and on safety performance generally. |
REC121-3676 | 14 - Incident Mgt Teams | A direct line of communication should be established between the RMC and Emergency Services Operations Control Centre by a “tie line” or otherwise, so as to ensure that in the case of a serious rail accident there is an open line of communication between the officer in charge of the management of the incident at the RMC and the various emergency response services. |
REC121-3691 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR should audit the RMC to ensure communications protocols are being followed. The sanction for non-compliance with communications protocols should be identical to that in the aviation industry and involve immediate removal from duty. Any RailCorp employee not following communications protocols should be required to undertake further training. If, following return to duties after such training, the officer continues to fail to comply with communications protocols, that officer is not to be employed in communications related work. |
REC121-3768 | 25 - Inquiry, audit, lessons management and after action review | The ITSRR, when considering a re-application for accreditation, should conduct a field audit of the organisation to ensure that it is carrying on its activities in accordance with the basis upon which it seeks accreditation. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |
REC004-3998 | 19 - Offences | That a by-law be made forbidding, under a heavy penalty, any persons travelling in such trains to throw lighted tobacco, cigars, cigarettes, pipe ashes, matches, or other inflammable matter on the railway line or right-of-way, or in any part of a railway carriage except the receptacles duly provided for the purpose. |