Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4006 | 17 - Assets and technology | The Commisison would not insist upon a barometer being provided at each mine. Experience has proved that this is a tardy index to atmospheric conditions. Serious changes in the atmospheric pressure occur and are felt before they are indicated by a barometer. |
Rec-ID | Code | Recommendation |
---|---|---|
REC288-1198 | 17 - Assets and technology | The Committee finds that on the evidence presented, that the Government should undertake a review of how firefighting equipment and gear in Tasmania can be better standardised with interstate equipment and gear to improve cross-jurisdiction resource utilisation. |
REC288-1195 | 5 - Hazard reduction burns | The Committee finds that on the evidence presented, that the Fuel Reduction Burn Program should be maintained and have its budget directly funded to ensure that the program continues and does not hinder other services or programs. |
Rec-ID | Code | Recommendation |
---|---|---|
REC267-1162 | 10 - Infrastructure | Telecommunications and Power Infrastructure |
REC267-1153 | 4 - Fire season preparation | Planning for Access to Potentially Isolated Communities |
Rec-ID | Code | Recommendation |
---|---|---|
REC246-0784 | 17 - Assets and technology | Recommendation 9 TFS should review the capacity of its Fire Information Line to handle very large scale events, and explore additional options for a surge capability for the Fire Information Line. |
Rec-ID | Code | Recommendation |
---|---|---|
REC245-2597 | 17 - Assets and technology | That the project team become independent from any of the entities involved in the Whole of Government network. |
REC245-2595 | 17 - Assets and technology | That stakeholders involved with the Whole of Government radio project re-engage positively to ensure a solution to the current impasse is achieved in the best interests of the stakeholders and the State as a whole. |
REC245-2594 | 17 - Assets and technology | That the network managers produce business cases for all major upgrades. |
REC245-2593 | 17 - Assets and technology | That network managers develop and document strategic plans for the management of their radio networks. |
REC245-2591 | 17 - Assets and technology | That until the outcome of the Whole of Government project is complete (and interoperability is achieved), emergency services should investigate and implement methods for further improving interoperability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC238-0815 | 1 - Land-use and building regs | Provide improved land use planning tools for managing flood prone land. |
REC238-0814 | 1 - Land-use and building regs | Develop a NSW Planning Policy and Guideline to improve land use planning practices on flood prone land. |
REC238-0808 | 1 - Land-use and building regs | Ensure future road infrastructure planning considers flood evacuation requirements throughout the Hawkesbury-Nepean floodplain. |
REC238-0801 | 1 - Land-use and building regs | Establish a dedicated group or body within an existing agency to provide a more integrated, coordinated and regional approach to land use, infrastructure and evacuation planning and flood modelling in the Hawkesbury-Nepean Valley. |
REC238-0800 | 1 - Land-use and building regs | Improve regional transport infrastructure to address current and projected flood evacuation capacity constraints and timelines. |
REC238-0816 | 1 - Land-use and building regs | Ensure appropriate consideration of flood risk in regional and subregional planning |
Rec-ID | Code | Recommendation |
---|---|---|
REC193-0227 | 5 - Hazard reduction burns | Local government councils implement a zoning approach to fuel management as recommended by COAG 2004. |
Rec-ID | Code | Recommendation |
---|---|---|
REC129-3622 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider building on influenza pandemic preparedness planning to develop broader contingency plans to address the emergence of other new, highly transmissible and/or severe infectious diseases. |
REC129-3628 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test the capability of its contact tracing system to deal with a public health emergency. |
REC129-3627 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and continue to develop and test its surveillance systems for early detection of infectious diseases. |
REC129-3626 | 39 - Disaster Risk Management | We recommend that NSW Health continue with its good work and consider a more structured and systematic approach to the planning and risk assessment of major infectious diseases to assist transparency and decision making. |
REC129-3624 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and formally establish and oversight a comprehensive program of training, testing and evaluation of plans at the state, area and facility level. |
REC129-3623 | 41 - Emergency Management exercises | We recommend that NSW Health continue with its good work and apply the lessons learnt from Exercise Cumpston to further improve preparedness for major infectious disease emergencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3978 | 4 - Fire season preparation | Where possible to build stone or brick fireplaces for the use of travellers, teamsters, and drovers on the camping areas that are mostly used and where there is a risk of fire. |
REC013_3976 | 4 - Fire season preparation | To burn camping areas at suitable water and camping reserves. |
REC013_3975 | 5 - Hazard reduction burns | To burn, where necessary, at least 33 feet where there is a risk of fire, on the outside of the railway fence, in conjunction with the railway employees. |
REC013_3974 | 1 - Land-use and building regs | To link up fallow paddocks and natural fire breaks by ploughing or burning breaks through private or public property, roads, &c. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |