Rec-ID | Code | Recommendation |
---|---|---|
REC317-4066 | 2 - Emergency powers | The Australian Government should make provision, in legislation, for a declaration of a state of national emergency. The declaration should include the following components: |
REC317-4089 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4094 | 8 - Communications and warnings | State and territory governments should expedite the development and implementation of the Australian Fire Danger Rating System. It should ensure that there is national consistency in the visual display of the AFDRS and action to be taken in response to each rating. |
REC317-4064 | 32 - Doctrine, standards, and reform | Australian, state and territory governments should work together to develop consistent data standards to measure disaster impact. |
REC317-4088 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4093 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review those plans, and update where appropriate, to provide for coordination between states and territories in cross border areas and to provide cross-border access to evacuation centres. |
REC317-4055 | 32 - Doctrine, standards, and reform | The Australian Government should revise the COMDISPLAN thresholds to provide that a request for Australian Government assistance, including Defence assistance, is able to be made by a state or territory government when: |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4092 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review these plans, and update them where appropriate, to account for the existence and standard of any evacuation centres and safer places (however described) in the community, including: |
REC317-4099 | 8 - Communications and warnings | Australian, state and territory governments should continue to explore the feasibility of a national, all-hazard emergency warning app. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4091 | 11 - Evacuation and shelters | State and territory governments should provide further community education on the function and limitations of different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. This education should be nationally consistent. |
REC317-4098 | 8 - Communications and warnings | The Australian Government should facilitate state and territory governments working together to develop minimum national standards of information to be included in bushfire warnings apps. |
REC317-4072 | 32 - Doctrine, standards, and reform | The Australian Government should consider whether employment protections under the Fair Work Act 2009 (Cth) are sufficient to ensure that fire and emergency services volunteers will not be discriminated against, disadvantaged or dismissed for reasons associated with their volunteer service during natural disasters. |
REC317-4090 | 11 - Evacuation and shelters | State and territory governments should, as a priority, adopt nationally consistent terminology and functions for the different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. |
REC317-4096 | 8 - Communications and warnings | State and territory governments should urgently deliver and implement thevall-hazard Australian Warning System. |
Rec-ID | Code | Recommendation |
---|---|---|
REC290-1214 | 14 - Incident Mgt Teams | Flexible pre‐formed multi‐ agency IMTs |
REC290-1213 | 34 - Local knowledge | Structures to incorporate local knowledge and situational awareness into the fire response |
REC290-1211 | 32 - Doctrine, standards, and reform | Review of institutional arrangements in the fire sector |
REC290-1210 | 15 - Inter-service cooperation | Co‐designed arrangements that support a unified response to fire |
REC290-1209 | 15 - Inter-service cooperation | Coordinated and targeted mitigation of fire risk |
REC290-1218 | 7 - Inter-agency communication | Cross-agency resource management system |
Rec-ID | Code | Recommendation |
---|---|---|
REC277-1165 | 32 - Doctrine, standards, and reform | Clarify the role of the ROC and SOC and their reporting relationships: The ROC and SOC have important coordination roles under the State Emergency Management Arrangements to support both the incident and the broader region and state. Clarifying the role of the ROC and SOC, their reporting relationships, and how the command structures of other agencies are integrated, will have three main benefits: the ROC and SOC can perform their functions effectively • no inconsistencies, gaps or duplication in the activities of the IMT, ROC and SOC • transparency of incident management |
REC277-1164 | 14 - Incident Mgt Teams | Establish multi-agency preformed IMTs: An effective IMT for large and complex fire incidents requires the capacity and expertise of multiple agencies. Establishing multi-agency preformed IMTs will have three main benefits: adequate IMT resources can be deployed with ease • strong working relationships will be built between IMT members • common approaches to incident management and fire response can be embedded. |
REC277-1166 | 7 - Inter-agency communication | Develop an integrated inter-agency resource management system: Large and complex fire incidents require resources from multiple agencies. Developing an integrated inter-agency resource management system will have three main benefits: identifying potential resources will be more straightforward • the status and location of resource deployments can be tracked • planning of deployments can take into account all relevant information |
Rec-ID | Code | Recommendation |
---|---|---|
REC265-1109 | 14 - Incident Mgt Teams | Future appointments to the role of Incident Controller should be limited to one for the entire duration of the incident, with nominated Deputy Incident Controllers to assist or ‘take charge’ in the Incident Controller’s absence. This measure will provide for a single point of responsibility and control for the incident and assist with any subsequent review or enquiry. If it is not possible to implement this proposal for liability reasons, the number of Incident Controllers should nevertheless be reduced to the minimum. |
REC265-1118 | 8 - Communications and warnings | Consideration should be given to an automatic ‘Advice’ notice being issued as soon as a fire is reported in a pre- determined high risk area such as the Darling Scarp on days when adverse fire weather conditions are forecast. |
REC265-1107 | 32 - Doctrine, standards, and reform | Standard Operating Procedure 1 (Mobilisation Zone 2, Perth Hills area) should be reviewed to ensure that appropriate escalation triggers and levels of operational readiness are in place for future periods when severe fire weather conditions are forecast. |
REC265-1114 | 32 - Doctrine, standards, and reform | Procedures should be reviewed to address the risks associated with response aircraft all working from one forward operating base, including the need for a designated fire protection unit to be available in the event of an aircraftrelated fire or other emergency incident |
REC265-1106 | 15 - Inter-service cooperation | In addition to regular meetings of the DFES/DPaW Interagency Bushfire Management Committee, the two organisations should use joint exercises to identify agreed firefighting approaches for common or likely scenarios. |
REC265-1113 | 32 - Doctrine, standards, and reform | The role of the Ground Controller should be reaffirmed in operational doctrine and reinforced in Incident Management Team training. During incidents involving aircraft the appointment of a Ground Controller should be confirmed by the Incident Controller |
REC265-1124 | 32 - Doctrine, standards, and reform | EMP 4.4 and Westplan – Recovery Coordination should be amended to: clarify the wording around handing over control of the incident from the Controlling Agency to local government and the transition from response to recovery; include principles and criteria that will assist the Controlling Agency and local government to determine the best time to effect a hand over of control of the incident; make explicit the roles and responsibilities of the parties involved in the handover of control of the incident; specify the information required in the needs and impact assessments provided to local government by the Controlling Agency so that local government is given sufficient information to take control of incidents; clarify the roles, responsibilities and the title of the State Recovery Controller and ensure that the appropriate wording is reflected in Westplans and State Emergency Management Policies; Hazard Management Agencies, combat and support agencies and local governments need to fully inform themselves of the role of the State Recovery Controller and implement a more effective approach to communicating |
REC265-1105 | 15 - Inter-service cooperation | The Executive Teams of both DFES and DPaW should meet quarterly to review and agree joint improvements relating to issues of interoperability, complementarity and the alignment of firefighting doctrine. The establishment of a unified command in joint State Operations Centre, Regional Operations Centre and Incident Management Teams should be pursued as an overarching goal. |
REC265-1111 | 15 - Inter-service cooperation | All agencies engaged in bushfire response should develop expeditious procedures for the mobilisation of resources in support of other agencies. See discussion in Section 7.1. |
REC265-1122 | 18 - Access to fire ground | DFES, in consultation with bushfire volunteers should develop a procedure for the controlled entry and exit of volunteers to the fire ground |
REC265-1100 | 32 - Doctrine, standards, and reform | The forthcoming review by SEMC of SEMP 4.4 Recovery Coordination and Westplan – Recovery Coordination and SEMP 4.1 Incident Management should include consideration of: |
REC265-1110 | 32 - Doctrine, standards, and reform | Whenever a Bush Fires Act 1954 section 13 transfer of control is invoked, the Incident level of an event should also be reviewed and any changes documented. |
REC265-1121 | 18 - Access to fire ground | A Restricted Access Permit system for the entry/ re-entry of residents, based on the one developed for the Parkerville Stoneville Mt Helena Bushfire should be finalised. |
Rec-ID | Code | Recommendation |
---|---|---|
REC254-1586 | 15 - Inter-service cooperation | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
REC254-1585 | 14 - Incident Mgt Teams | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC254-1584 | 32 - Doctrine, standards, and reform | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
REC254-1580 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
REC254-1588 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
REC254-1587 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC233-1604 | 8 - Communications and warnings | Governments and other stakeholders consider reviewing their existing emergency management arrangements to ensure public communications are clear and the public is kept informed of the incident response. |
REC233-1603 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy (DBCDE) to work with the Triple Zero Awareness Work Group through Australian Communications and Media Authority's (ACMA) Emergency Service Advisory Committee to review Triple Zero awareness messages with regard to telecommunications outages. |
REC233-1592 | 8 - Communications and warnings | Department of Broadband, Communications and the Digital Economy will work with the Communications Sector Group within the Trusted Information Sharing Network to develop best practice guidance for owners of critical communications infrastructure regarding public messaging during a prolonged telecommunications outage covering: |
Rec-ID | Code | Recommendation |
---|---|---|
REC226-0553 | 5 - Hazard reduction burns | Rolling risk assessment conducted during ignition of prescribed burns should identify whether an escape is likely to develop into a Level 3 incident. As soon as possible after it has been identified that the escape cannot be contained, the incident should be declared a Level 3. |
REC226-0572 | 14 - Incident Mgt Teams | Contingency planning before the fire may have supported the IMT in recognising and seizing strategic opportunities earlier. |
REC226-0592 | 11 - Evacuation and shelters | Decisions on evacuations need to be made early enough for people to be fully informed, prepared and to move to a place of greater safety. Failure to conduct good planning can create situations where loss of life can occur |
REC226-0558 | 14 - Incident Mgt Teams | Predetermined locations for Level 3 IMTs should be reviewed and adequately resourced with necessary communications and IT capacity. |
REC226-0578 | 15 - Inter-service cooperation | There would be benefit in progressively aligning the geographic boundaries of each of the agencies and seeking to co-locate their headquarters within those boundaries. |
REC226-0543 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. |
REC226-0564 | 14 - Incident Mgt Teams | The expected scenario, with a view to the worst-case scenario should provide the basis for an IAP. |
REC226-0586 | 14 - Incident Mgt Teams | At Level 3, the available fire management expertise should be applied overwhelmingly to the fire management aspects of emergency management, possibly in incident control, and certainly in situations planning and operations roles. |
REC226-0552 | 7 - Inter-agency communication | Communications planning for geographic regions with recognised black spots and specific communications challenges should be prepared in advance of an emergency in order to support the IMT Communications Planning Officer |
REC226-0570 | 14 - Incident Mgt Teams | Logistics and resource officers in IMTs need to collaborate and establish full awareness and control over the available resources. |
REC226-0591 | 8 - Communications and warnings | Radio bulletins need to be up to date and time stamped. Where social media is used the messages need to be up to date and accurate. Websites need to be up to date and accurate. |
REC226-0557 | 14 - Incident Mgt Teams | An intensive exercise/training program should be developed and maintained across agencies to identify and establish a pool of current Incident Controllers who are capable of managing a Level 3 incident. |
REC226-0577 | 7 - Inter-agency communication | A system of vehicle tracking should be fitted to all fire appliances and linked to the common operating picture. Good communications planning is essential for good command and control. |
REC226-0542 | 5 - Hazard reduction burns | A risk management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. This risk assessment should be dynamic in line with the four day and seven day weather forecast. |
REC226-0563 | 14 - Incident Mgt Teams | Procedures to relocate IMTs need to be established in doctrine and exercised to ensure continuity of control. |
REC226-0585 | 14 - Incident Mgt Teams | DEC’s fire management expertise should be augmented by multi-agency IMTs that incorporate the expertise of other agencies and in fast developing situations the appropriate decisions will need to be made early. |
REC226-0551 | 14 - Incident Mgt Teams | As presently implemented, the AIIMS planning role is under-developed and provides insufficient support to the Incident Controller. |
REC226-0569 | 32 - Doctrine, standards, and reform | Section 13 arrangements need to be clarified across key agencies. |
REC226-0590 | 8 - Communications and warnings | Expand the exploitation of social media, including graphical content for state alerts and warnings. Consider increasing the graphical content of web-based warnings. |
REC226-0556 | 14 - Incident Mgt Teams | Within the AIIMS IMT doctrine the roles of the Incident Controller and Deputy Incident Controllers should be defined and well-practiced. |
REC226-0575 | 14 - Incident Mgt Teams | In multi-agency responses the culture, training and equipment characteristics of each of the agencies should be considered in their employment. |
REC226-0562 | 14 - Incident Mgt Teams | Opportunities be sought to utilise local government representatives in other areas of the IMT particularly in public information or other community related functions. |
REC226-0584 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command and not through agency chains of command |
REC226-0550 | 14 - Incident Mgt Teams | Greater investment in training on specific functions within the AIIMS structure will improve the support provided to the Incident Controller. |
REC226-0567 | 14 - Incident Mgt Teams | IMTs need to establish early and effective liaison with Local Governments. |
REC226-0589 | 8 - Communications and warnings | The process for initiating and releasing State Alert messages requires review. |
REC226-0555 | 14 - Incident Mgt Teams | The state should identify the number of fully trained, experienced and accredited Level 3 Incident Controllers required to be available at any time and establish a process for identification of suitable personnel, ongoing training and accreditation. |
REC226-0574 | 14 - Incident Mgt Teams | Clear direction to divisional and sector commanders and a common communications platform enables maximum return to be gained from the application of tactical resources and this rests on good incident action planning, and good command and control. |
REC226-0561 | 34 - Local knowledge | Suitably experienced local representatives should be engaged to provide advice to the IMT in all Level 2 and Level 3 incidents at the earliest opportunity. |
REC226-0580 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
REC226-0548 | 15 - Inter-service cooperation | Inter-agency cooperation to manage fire precincts in a tenure-blind fashion is necessary for effective fire suppression. |
REC226-0566 | 14 - Incident Mgt Teams | Incident Controllers should be supported by a planning function that combines experienced weather forecasters, fire behaviour experts and local knowledge. |
REC226-0588 | 8 - Communications and warnings | Timely alerts and updates to the community are essential. |
REC226-0554 | 14 - Incident Mgt Teams | For incidents of this complexity, effective control in the critical phase (first 24-36 hours of the fire) requires an appropriately resourced IMT. |
REC226-0573 | 14 - Incident Mgt Teams | Strategic direction seeks to identify and resource those areas of tactical action that offer the greatest advantage. |
REC226-0560 | 15 - Inter-service cooperation | There would be value in progressively aligning the geographical boundaries of emergency management agencies and co-locating where possible within regions and districts. |
REC226-0579 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to better manage fire- fighting resources across the state. |
REC226-0544 | 5 - Hazard reduction burns | Prescribed burns which meet the ‘red flag’ criteria should have mandated risk Establish risk management criteria for management criteria imposed. |
REC226-0565 | 14 - Incident Mgt Teams | Contingency planning is a critical function in the early stages of an escalating incident, and should provide the foundation of an IAP. |
REC226-0587 | 14 - Incident Mgt Teams | To be effective, multi-agency IMTs will need to be exercised regularly and supported by sound and comprehensive doctrine. |
Rec-ID | Code | Recommendation |
---|---|---|
REC225-0536 | 32 - Doctrine, standards, and reform | DFES and Local Government Bushfire Brigades ensure that only those with the required AIIMS competence have the authority to manage Level 1 incidents, noting they may not be Fire Control Officers. |
REC225-0535 | 2 - Emergency powers | DFES or DEC (depending on land tenure) is mandated to take over control of emergency incidents from Local Government once they have been declared Level 2 incidents. WESTPLAN BUSHFIRE and legislation to be amended accordingly. |
REC225-0534 | 32 - Doctrine, standards, and reform | Once Recommendation 1 has been actioned, all agencies give greater priority to the promulgation of Red Flag warnings in order to enhance situational awareness on the fireground. |
REC225-0539 | 32 - Doctrine, standards, and reform | WA fire agencies adopt a common set of standing orders, operational procedures, training and competencies for rural firefighting that are produced in hard copy, leading to integrated multi-agency training, IMTs, Regional and State coordination/control centres. |
REC225-0531 | 32 - Doctrine, standards, and reform | Critical operational procedures such as ‘Red Flag Warnings’, on a common fireground need to be consistent across DFES, DEC and Local Government. In particular, the operational procedure of Red Flag Warnings needs to be adopted by all WA fire agencies. |
REC225-0538 | 14 - Incident Mgt Teams | WA adopts a culture of joint IMTs in future. At Regional and State levels, DFES and DEC maintain standing contributions. |
REC225-0537 | 7 - Inter-agency communication | Future coordination/support/control of integrated emergency management across all agencies in Albany needs to be merged and located in a single joint facility. This issue needs to be reviewed statewide. |
Rec-ID | Code | Recommendation |
---|---|---|
REC203-0289 | 18 - Access to fire ground | There needs to be a better appreciation of the role of Vehicle Control Points (VCPs) and how they are managed in bushfire emergencies by all key agencies and the community |
REC203-0306 | 8 - Communications and warnings | Local emergency management committees and planning should identify modes of community contact |
REC203-0278 | 5 - Hazard reduction burns | Prescriptions should mandate consideration of measures to retire risk. |
REC203-0294 | 14 - Incident Mgt Teams | Opportunities should be sought to embed other local government representatives in other areas of the IMT particularly in public information. |
REC203-0283 | 5 - Hazard reduction burns | Core ignition, particularly of red flag burns, should be informed by the 4 & 7 day forecasts (including a longer term perspective over 3 to 4 months) |
REC203-0300 | 14 - Incident Mgt Teams | Reporting and control should be through the incident chain of command, and not through agency chain of command. |
REC203-0288 | 15 - Inter-service cooperation | The State Duty Officer from DEC and the State Duty Director, FES A need to confer whenever a Level 2 or 3 incident is declared to satisfy themselves that they have appropriate incident management structures and resources across the state are at an appropriate level of preparedness. |
REC203-0305 | 8 - Communications and warnings | The agencies need to develop techniques to ensure accuracy of information across all media. |
REC203-0277 | 5 - Hazard reduction burns | A risk-management approach is needed which considers risks both inside the prescribed burn and the risks that will need to be managed if the fire escapes. The risk assessment should be organised and in line with the four and seven day weather. |
REC203-0293 | 34 - Local knowledge | Suitably experienced personnel with local knowledge should be connected to the Operations and Planning section in all Level 3 incidents in the vicinity of substantial settlements. |
REC203-0282 | 5 - Hazard reduction burns | The burn prescription should capture the fuel characteristics and potential rate of spread for those areas outside the burn that will likely be critical during the initial attack on any escaping fire. |
REC203-0299 | 15 - Inter-service cooperation | The state should converge on a single communications platform for all emergency management and support agencies. |
REC203-0287 | 15 - Inter-service cooperation | On a regional basis there would be value in closer working relationship between DEC crews and VBFBs to build mutual trust and confidence. This could be done by opportunity engagement of VBFBs in DEC fire management or through exercises. |
REC203-0304 | 8 - Communications and warnings | Further community education may be needed on how to interpret messages. |
REC203-0276 | 5 - Hazard reduction burns | There should be clearly established criteria for burns which are specially challenging, and these criteria need to extend beyond the intended boundaries of the prescribed burn. The criteria should be clarified and adopted as agency S OPs. |
REC203-0292 | 18 - Access to fire ground | There is a need for community education on how road-blocks and VCPs operate in the event of an emergency. |
REC203-0281 | 5 - Hazard reduction burns | Prescriptions need to be interpreted by experienced and knowledgeable personnel to ensure risk is fully understood. It is important that the background and justification for these decisions are captured at each stage and are visible to all levels in WA fire management hierarchy. |
REC203-0298 | 15 - Inter-service cooperation | The state should progressively align on a shared platform, such as WebEO C , to establish a Common Operating Picture (COP). |
REC203-0286 | 5 - Hazard reduction burns | Decisions taken on the basis of this risk assessment need to be captured and distributed across district and state. |
REC203-0303 | 8 - Communications and warnings | A high level review of alerts, warnings and messaging is needed to match community expectations with what is practical and achievable. |
REC203-0291 | 18 - Access to fire ground | Local knowledge should be accessed to inform the placement and operation of VCPs. |
REC203-0280 | 5 - Hazard reduction burns | Contingency plans for escaping burns should be prepared in advance. |
REC203-0297 | 32 - Doctrine, standards, and reform | The role of district and local emergency management committees should be reviewed to ensure they are appropriately engaged in the active management of emergencies across the PPR R continuum |
REC203-0285 | 5 - Hazard reduction burns | A rolling risk assessment is required which captures the risks of the burn escaping and provides adequate resources. |
REC203-0302 | 8 - Communications and warnings | Web sites need to be kept updated. |
REC203-0290 | 18 - Access to fire ground | VCPs are one of the instruments by which the Incident Controller manages the emergency. VCPs without communications cannot be fully effective in their role. Determine and implement an appropriate communications platform for emergency management |
REC203-0307 | 11 - Evacuation and shelters | When people are being moved away from their homes it’s important that they move to a place of greater safety and that their movement is relatively assured. |
REC203-0279 | 5 - Hazard reduction burns | Once a burn is ignited, it needs to be the subject of continuing risk assessment and appropriate mitigation. |
REC203-0296 | 32 - Doctrine, standards, and reform | Legislative change may be needed to enable FES A to manage fire-fighting resources across the state. |
REC203-0284 | 5 - Hazard reduction burns | DEC should investigate embedding an experienced forecaster in the state operations centre. |
REC203-0301 | 15 - Inter-service cooperation | Early in an incident, close and effective liaison needs to be established with local government agencies. |
Rec-ID | Code | Recommendation |
---|---|---|
REC173-0100 | 32 - Doctrine, standards, and reform | The prioritising of the critical amendments to the Bush Fires Act 1954 recommended by the Community Development and Justice Standing Committee that relate to fire management, ie: a. Fire and Emergency Services Authority (FESA)‘s ability to assume control of a fire in specific circumstances b. Amendments to the definition of property c. Providing FESA with the authority to declare a total fire ban |
REC173-0102 | 32 - Doctrine, standards, and reform | That further amendments be made to the Bush Fires Act 1954 be drafted to provide fire response agencies with the necessary authorisation and statutory protection to respond to a fire on private property, or land that Local Government, Department of Environment and Conservation (DEC) or FESA is responsible for, until such time as the responsible agency is able to attend and take control. The amendments to be drafted, in conjunction with the urgent progression of critical amendments as recommended by the Community Development and Justice Standing Committee. |
Rec-ID | Code | Recommendation |
---|---|---|
REC172-0033 | 8 - Communications and warnings | Public meetings are to be encouraged for all Level 3 incidents that affect, or have the potential to affect communities. |
REC172-0006 | 14 - Incident Mgt Teams | Prior to the bushfire season, potential IMG members, many of whom are members of the Local Emergency Management Committee (LEMC) should be made aware of, and possibly exercise, their role as an IMG member. |
REC172-0038 | 34 - Local knowledge | The ISU should be provided with a person with local knowledge at Level 3 incidents. |
REC172-0011 | 18 - Access to fire ground | At Level 3 incidents the position of ‘Traffic Operations Officer’ –be established and filled by a WAPOL officer. A role description for this position is required and should be included in the “Guidelines for the Operations of Road Closures During Bushfires 2008”. This officer is to be supported by a suitably qualified officer from MRWA that is capable of developing Traffic Management Plans that address risk and are cognisant of considerations associated with road type, appropriate speed limitations, signage requirements, traffic volumes, detours for local traffic and heavy haulage etc. This role should report to the IC and have strong links to the Operations Section, Planning Section (particularly the Situation Unit) and the Information Unit. |
REC172-0016 | 18 - Access to fire ground | Full briefings of traffic management personnel should be provided prior to dispatch to work areas – why road closed, what their authority level is, level of current risk etc |
REC172-0032 | 8 - Communications and warnings | A review of community messages, their construction and component parts, the process to activate them and the technology required to deliver the messages by digital and non-digital media should be undertaken. The desired outcome is to define standard messages, procedures, tools and technologies that can be utilised by all HMA’s in Western Australia. |
REC172-0005 | 14 - Incident Mgt Teams | Potential IMG membership should be identified in local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA. |
REC172-0037 | 8 - Communications and warnings | ABC Radio should be a participant in IMG and/or OAMG. LEMC and DEMC should plan for this involvement in Local and District Emergency Management Plans. |
REC172-0010 | 14 - Incident Mgt Teams | The responsibilities and obligations for an OAM and OAMG (when established) needs to clarified and codified in Westplan Bushfire with regard to • Provision of information to participating organisations about the progress and potential of an incident; • Dealing with information disseminated to the public; and • Sourcing, coordinating and prioritising resources required by incidents within the Operations Area. There is lack of clarity in current arrangements concerning the role of the agency undertaking control operations e.g. DEC or a local govt and the transfer of these responsibilities to an OAMG when established. |
REC172-0015 | 8 - Communications and warnings | Provision of timely, accurate and regular information to the community via electronic media (radio and internet) is a recognised function of the Information Unit in liaison with the Traffic Operations Officer. The aim of this arrangement is to facilitate appropriate behaviour in the travelling public and local community concerning access limitations and disruptions to the fire ground and surrounding areas. |
REC172-0043 | 7 - Inter-agency communication | There needs to be a system that allows laptop computers brought to an incident to be configured at the start of the season and allow them to be easily activated to the correct configuration when they arrive at the incident. |
REC172-0022 | 15 - Inter-service cooperation | The declaration of a potential Level 3 incident should be notified to FESA who can facilitate an early warning to CFCO’s in the Shire and surrounding LGA’s. |
REC172-0004 | 14 - Incident Mgt Teams | A formal IMG meeting should be convened as early as possible at initiating incidents with potential. At the very least early advice to potential IMG members should be made that a meeting is likely to be convened. The initial IMG should include all IMG representatives to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0036 | 8 - Communications and warnings | Wherever possible the ISU should be co-located with Operations and Logistics Sections to ensure effective communications and the ICC in which they operate should be located in the affected community. |
REC172-0009 | 14 - Incident Mgt Teams | When an OAMG is established, a formal declaration of its establishment needs to be transmitted to all organisation/agencies involved. The declaration should clearly establish the reporting arrangements for Incident Controllers to the OAM as described in Westplan Bushfire. |
REC172-0042 | 7 - Inter-agency communication | Portable, reliable mobile repeaters are required to provide radio communications into areas not covered by existing repeater networks. These repeaters need the capacity to be linked. |
REC172-0014 | 18 - Access to fire ground | The Interagency Guidelines for Road closure needs to be reviewed to incorporate a mechanism to identify bone-fide local landholders to facilitate their movement in and out of cordoned areas in sympathy with the Stay and Defend requirements. |
REC172-0021 | 32 - Doctrine, standards, and reform | Unassigned resources arriving at incidents should be encouraged to make themselves known and to undertake alternate duties. |
REC172-0003 | 32 - Doctrine, standards, and reform | All incidents where the HMA delegates the authority to manage suppression operations to another agency on its behalf, should be achieved via a written delegation setting out the scope, limitations and duration of the delegation. |
REC172-0035 | 14 - Incident Mgt Teams | At Level 3 incidents the Information Services Unit should be adequately resourced with information technology and at least 6 persons, all of whom are very experienced and capable in dealing with the information demands of a Level 3 incident. |
REC172-0008 | 14 - Incident Mgt Teams | Potential OAMG membership should be identified in DEMC protocols and local hazard management plans. The information needs to be kept current. The contact details for each member should be recorded. These plans and contact details need to be available to any IMT mobilised to deal with an incident within the jurisdiction. This means access to this information via internet and storage and maintenance at a centralised facility managed by FESA.] |
REC172-0040 | 8 - Communications and warnings | The information templates used by the ISU in developing public information boards need to be standardised and posted on the DEC Fire Management Services webpage to allow access and use by the ISU. A standard across government would add significantly to their acceptance and use by the public as a reliable source of information. |
REC172-0013 | 18 - Access to fire ground | In preparing traffic management plans consideration should be given to which VCP’s are critical and need to be resourced with uniformed Police Officers and which VCP’s can be manned with civilian contractors. |
REC172-0018 | 32 - Doctrine, standards, and reform | The Interagency Guidelines need to be amended to reflect what is operationally possible with regard to risk management rather than what is required to achieve an absence of risk. |
REC172-0002 | 32 - Doctrine, standards, and reform | The Emergency Management Act 2005 is amended to provide a mechanism for one HMA to transfer responsibility to another HMA and ensure that both HMA’s are provided the powers and protection necessary under that Act. |
REC172-0034 | 8 - Communications and warnings | A centralised emergency services website should be established that the public can access for reliable and up to date information on any incident. The website must be capable of reliably servicing a very high traffic load and be easily updated by HMA’s. |
REC172-0007 | 14 - Incident Mgt Teams | A formal OAMG meeting should be convened as early as possible for incidents with the potential to be Level 3 incidents. At the very least early advice to potential OAMG members should be made on days that exhibit extreme fire weather and other high ignition risk factors that a meeting is likely to be convened. The initial OAMG should include all OAMG representatives identified by LEMAC and DEMAC for each area to ensure comprehensive briefing, agency specific situational awareness and issue identification. |
REC172-0039 | 18 - Access to fire ground | Dedicated information packages should be made available to personnel operating Vehicle Control Points at the shift briefing. |
REC172-0012 | 18 - Access to fire ground | Main Roads Western Australia, Police and LGA’s be encouraged via State emergency arrangements to establish a distributed cache of “hard” road barriers for deployment to major incidents |
REC172-0017 | 18 - Access to fire ground | Information packs to be provided to road traffic personnel to assist with enquiries by public or provision to members of public and landholders who are defending homes/stock etc |
REC172-0001 | 32 - Doctrine, standards, and reform | The Emergency Management Regulations 2006 be urgently amended to determine a HMA(s) for bushfire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC148-3159 | 32 - Doctrine, standards, and reform | That the import conditions for horses specify that there be available for inspection at the port of loading and produced on the horse’s arrival in Australia, certification (including in electronic form) that the horse has been vaccinated, has had a blood sample taken during pre-export quarantine, and has passed a suitable detection test, currently either a quantitative PCR or an antigen-capture ELISA test for influenza A. |
REC148-3174 | 32 - Doctrine, standards, and reform | That the operating procedures require, as a condition of entry for all non- AQIS personnel to a quarantine station, that each person report any suspected breach (by that or any other person) of quarantine procedures in the quarantine station and that a person may be excluded from entry to a quarantine station in the event of a breach of such procedures by that person or in the event of a failure of that person to report any suspected breach. |
REC148-3150 | 32 - Doctrine, standards, and reform | That the position of Inspector General of Horse Importation: |
REC148-3158 | 32 - Doctrine, standards, and reform | That the import conditions for horses specify, based on advice from Biosecurity Australia that is reviewed at least annually, the vaccines for equine influenza to be administered to horses before they are exported, taking account of the countries or regions from which the horses are exported. If there are commercially available vaccines that contain representatives of currently circulating strains, the import conditions should specify that the horses be vaccinated using that vaccine or one of those vaccines. Otherwise, the conditions should specify the vaccine or vaccines that may be used, based on the advice of Biosecurity Australia. |
REC148-3173 | 32 - Doctrine, standards, and reform | That the operating procedures require that the duties of any people responsible for maintaining 24 hour security at a quarantine station (whether they be AQIS officers or private contractors) are recorded in writing and that those people have received training in relation to biosecurity risks sufficient to instil an appreciation of such acts or circumstances as might give rise to biosecurity risks. |
REC148-3183 | 32 - Doctrine, standards, and reform | That the Quarantine Act 1908 be reviewed in order to identify amendments necessary to ensure that the Act clearly and adequately confers all relevant powers to ensure the biosecurity of horse importation and quarantine and to give effect to these recommendations. |
REC148-3157 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that the operations and procedures at the pre-export quarantine premises may from time to time, be inspected and audited by or on behalf of the Australian Government. |
REC148-3172 | 32 - Doctrine, standards, and reform | That the operating procedures require that the manager of a quarantine station be responsible for ensuring that a written report on compliance with procedures is prepared and reviewed daily and that any non-compliance and corrective action are recorded. |
REC148-3180 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that each horse be tested for equine influenza as close as practicable before the end of the quarantine period and that a negative result for that test be available before the horse may be released from quarantine. Until more sensitive and specific detection tests become available, an agent detection test for influenza A - either a quantitative PCR test or an antigen-capture ELISA test - should be used for that purpose. |
REC148-3156 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that the horse be tested for equine influenza at a time as close as practicable to the end of the pre- export quarantine period. Until more sensitive and specific detection tests become available, an agent test for influenza A—either a quantitative PCR or an antigen-capture ELISA test—should be used. |
REC148-3171 | 32 - Doctrine, standards, and reform | That the operating procedures require that there be identified a person who has overall responsibility for the various clearance procedures and biosecurity tasks to be performed in the course of unloading horses at an airport and transferring them to a quarantine station. |
REC148-3179 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that the nasopharyngeal swabs taken within 24 hours of arrival and five days after the last horse arrives in post-arrival quarantine be divided and the swabs made subject to a quantitative PCR test and a ‘rapid’ immuno-assay test to detect influenza A. The operating procedures should also require that these additional tests be conducted. |
REC148-3155 | 32 - Doctrine, standards, and reform | That the import conditions for horses include that a blood sample be taken while a horse is in pre-export quarantine. Part of the sample is to be retained in the country of export and another part of that sample is to be transported to Australia, preferably with the horse. Both parts are to be retained for at least three months. |
REC148-3160 | 32 - Doctrine, standards, and reform | That, before a horse is loaded on to an aircraft or vessel for carriage to Australia, AQIS verify that there exists such certification as is required by its import conditions up to the time the horse arrives at the airport of departure and that the horse complies with those conditions. This could be done by facsimile or electronic communication with AQIS officers in Australia. |
REC148-3176 | 32 - Doctrine, standards, and reform | That there be prepared operating procedures or a manual that: |
REC148-3153 | 32 - Doctrine, standards, and reform | That premises be used for pre-export quarantine only if they have been approved by the officer responsible for the importation of horses and only if they have adequate biosecurity precautions that are the subject of documented procedures that can be audited. The import conditions for horses shall include a requirement that pre-export quarantine premises have been so approved. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4143 | 5 - Hazard reduction burns | It be made clear to all fire control officers that the conditions for burning prescribed in the Bush Fires Act are minimal only, and that it is their duty to prescribe such further conditions as will ensure that should unfavourable weather conditions un-expectedly develop a situation would not arise which the local bush fire control organisation could not reasonably be expected to handle. |
REC019-4142 | 5 - Hazard reduction burns | Landowners desiring to carry out developmental burns be required to inform the local authority sufficiently early to enable that body to direct them or request the local bush fire brigade to carry out protective burning around the area before the prohibited season starts. |
REC019-4136 | 34 - Local knowledge | The Bush Fires Board appoint a Regional Committee of Board members co-opt local members for each climatic region of the State to study the bush fire control problems of the region and advise the Board so that inter alia adequate attention may be given by the Board to co-ordinating the beginning and termination of the prohibited burning times in adjoining districts and to any advisable variations of these duties according to seasonal conditions each year. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |
REC019-4152 | 5 - Hazard reduction burns | The Forests Department make every endeavour to improve and extend the practice of control burning to ensure that the forests receive the maximum protection practicable consistent with silvicultural requirements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3991 | 32 - Doctrine, standards, and reform | The Commission recommends that the provisios of section 185 of the "Mining Act 1905" relating to exits from coal mines be extended to metalliferous mines employing more than 20 men in any one shift. |
REC008-3988 | 40 - Equipment and consumables | The Commission recommends that buckets of sand or other apparatus for extinguishing fire be kept in any chamber where high powered electricity is used. |