Rec-ID | Code | Recommendation |
---|---|---|
REC258-2542 | 16 - Training and behaviour | The Civil Aviation Safety Authority publishes and demonstrates the philosophy of ‘just culture’ whereby individuals involved in a reportable event are not punished for actions, omissions or decisions taken by them that are commensurate with their experience and training. However, actions of gross negligence, wilful violations and destructive acts should not be tolerated. |
REC258-2541 | 16 - Training and behaviour | The Civil Aviation Safety Authority finalises its Capability Framework and overhauls its training program to ensure identified areas of need are addressed, including: |
REC258-2539 | 35 - Business and Industry in relation to industry | The Civil Aviation Safety Authority changes its regulatory philosophy and, together with industry, builds an effective collaborative relationship on a foundation of mutual understanding and respect. |
REC258-2534 | 16 - Training and behaviour | The Civil Aviation Safety Authority develops a staff exchange program with industry. |
REC258-2548 | 17 - Assets and technology | The Civil Aviation Safety Authority shares the risk assessment outputs of Sky Sentinel, its computerised risk assessment system, with the applicable authorisation holder. |
Rec-ID | Code | Recommendation |
---|---|---|
REC257-1540 | 16 - Training and behaviour | Commanding Officer Defence Explosive Ordnance Training School, assisted by Joint Logistics Command Regional Explosive Ordnance Serices staff, conduct explosive ordnance accounting training for all instructional staff as a matter of priority and that such training be conducted for Defence Explosive Ordnance Training School staff on an annual basis. |
REC257-1536 | 16 - Training and behaviour | The Australian defence Force Explosive Ordnance Disposal course be reviewed by Manager Joint Training - Air Force, to ensure the assessments meet the learning outcomes specificed in the relevant Training Management Package. |
REC257-1544 | 17 - Assets and technology | Defence should not procure any firefighting vehicle for Marrangaroo Training Area without first consulting relevant personnel within the Rural Fire Service on an appropriate type of vehicle, and obtaining training for the personnel proposed to use it. Alternatively, Defence should explore contracted firefighitng support during periods of live-fire on Marrangaroo Training Area. |
REC257-1542 | 17 - Assets and technology | Firefighitng capability at Marrangaroo Training Area be upgraded so that Australian Defence Force members are not placed in situations of unacceptable risk. Specifically, those participating in range practices must have access to a firefighting vehicle close by and easily deployed, and capable of throwing a large quantity of water an appreciable distance into areas adjacent to the ranges, should a fire occur. |
REC257-1541 | 17 - Assets and technology | A Stryker unit, or an upgraded firefighting unit, be present at the range sentry point, remain manned and ready to deploy during range activites, with its driver in direct radio contact with the Range Safety Officer. Upon the range being declared clear by the Safety Officer inspecting the range after a demolition serial, the firefighting unit must proceed forward to the range wile the periphery of the range continues to be inspected by the Safety Officer, and remain on the range until the Safety officer declares that the area is clear of fire or that it is otherwise appropriate for the fireghting unit to leave the range area. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2888 | 35 - Business and Industry in relation to industry | Foster private sector service providers who can offer tailored services or broadcast high quality presentation of general purpose weather information |
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
REC207-2881 | 17 - Assets and technology | Extend ICT governance arrangements to all applications and subject in-house development to rigorous approval processes. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3329 | 17 - Assets and technology | Logistics management of well control equipment should be conducted in such a way as to operate as a check against deficient well control practices, for example, use of serial numbers to track availability, testing, and deployment of well control equipment. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3333 | 16 - Training and behaviour | Licensees and rig operators (and third party contractors involved in well control operations) should specifically assess, and document, the nature and extent of knowledge/skills of relevant personnel in relation to well control (including familiarity of personnel with agency‐specific requirements and procedures). Training needs and opportunities should be identified. This process should take place on engagement and at appropriate intervals. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3332 | 16 - Training and behaviour | A specific focus on well control training should be mandatory for key personnel involved in well control operations (including both on‐rig personnel and onshore personnel in supervisory capacities). |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3331 | 16 - Training and behaviour | Existing well control training programs should be reviewed by the industry, regulators and training providers, with a focus on well control accidents that have occurred (in Australia and overseas). |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3132 | 35 - Business and Industry in relation to industry | Coverage of the regime should be increased to cover the complete hydrocarbons production system from wells through to custody transfer point or reasonable physical/technical system boundary. If NOPSA is also to be responsible for Carbon Capture and Storage it needs to be resourced to ensure that this does not detract from NOPSA's current responsibilities. |
REC149-3146 | 35 - Business and Industry in relation to industry | NOPSA should consider establishing a small forum for consultation consisting of representatives of relevant stakeholders. The representatives should have standing, with authority to participate in decision making and take on commitment on behalf of their stakeholder group. |
REC149-3131 | 35 - Business and Industry in relation to industry | The exploration/production operator making all major decisions related to petroleum activities (i.e. selection of rig, well design and selection of service companies) should be made responsible for demonstrating to the regulator that drilling operations can be conducted safely. Where the drilling contractor owns the rig and conducts the day-to-day management of safety on the rig, this duty can be described in a rig specific Safety Case that is owned by the drilling contractor. This rig specific Safety Case does not have to be submitted for every well/well operation. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
REC149-3137 | 16 - Training and behaviour | As professional competency is one of the key pillars of any Safety Case, commitment to training for current and future needs remains a fundamental requirement for achieving best practice outcomes in safety. Industry should be encouraged to build on its training commitment now being made to achieve a competent and fully accredited workforce over the next five years. |
REC149-3136 | 16 - Training and behaviour | There is a need for industry in consultation with NOPSA to establish a priority programme of accredited education modules in the Safety Case regime targeting stakeholders in the regime at their respective levels to improve the understanding of the Safety Case and correspondent responsibilities. |
REC149-3133 | 35 - Business and Industry in relation to industry | Because some issues related to emergency response are beyond any single operator and usually occur outside the title area, there is a need for the representatives of the offshore industry to work together with other governments, interested and involved parties to develop the strategies to be utilised and the emergency planning model that will satisfy the requirements of all parties. |
Rec-ID | Code | Recommendation |
---|---|---|
REC126-1980 | 16 - Training and behaviour | That public land management agencies ensure that their senior personnel have appropriate experience in fire management and are provided with adequate resources and suitable experienced and trained staff to effectively implement fire management programs |
REC126-2007 | 34 - Local knowledge | That the views and concerns expressed by the ACT Sustainable Rural Lands Group be taken into account when implementing the recommendations in this report |
REC126-1955 | 16 - Training and behaviour | That training of all personnel involved with emergency services be under constant review |
REC126-1970 | 35 - Business and Industry in relation to industry | That the Emergency Services Agency reconsider and revise the arrangement that exists between the ACT Fire Brigade and Canberra airport in relation to the provision of assistance |
REC126-2004 | 35 - Business and Industry in relation to industry | That the ACT Government and ActewAGL jointly develop and implement protocols that will create a procedure whereby each of the water and sewerage, electricity and gas distribution networks, or parts thereof, can safely and promptly be manipulated, controlled, shut off, isolated or disconnected under emergency conditions. |
REC126-1950 | 39 - Disaster Risk Management | That the Emergency Services Agency adopt a more rigorous risk management approach to incident management and prediction – with particular emphasis on the development of improved community information strategies and protocols |
REC126-1969 | 16 - Training and behaviour | That a review be conducted of the adequacy of training and the numbers of firefighters experienced in performing effective, safe large-scale back-burning operations |
REC126-1988 | 39 - Disaster Risk Management | That protocols and arrangements between the ACT and NSW require that each jurisdiction be fully involved in examining and planning for the threat posed by any fire likely to affect one or other jurisdiction and in coordinating the response to that fire |
REC126-1968 | 16 - Training and behaviour | That land managers ensure their staff are properly trained in the effective use of large bulldozers at wildfires and that staff are available to be assigned to supervise bulldozer operations |
REC126-1986 | 39 - Disaster Risk Management | That the ACT and NSW authorities conduct a comprehensive risk analysis based on the most up to date knowledge relating to fire behaviour and spread in order to establish the degree of risk to each others' jurisdiction from fires ignitting in the other jurisdiction and to ensure that both jurisdictions remain fully informed and participate in risk assessments, the development of suppression strategies, and the development and dissemination of community information messages or warnings |
REC126-1967 | 40 - Equipment and consumables | That the Emergency Services Agency give priority to ensuring it has guaranteed access to an adequate number and type of bulldozers, as well as experienced operators, during the fire season, for immediate deployment as required |
REC126-1983 | 16 - Training and behaviour | That the Australian Federal Police and the Emergency Services Agency ensure that personnel in their respective organisations are fully briefed on the agreed policy on evacuations |
REC126-2008 | 34 - Local knowledge | That, if he is willing to participate, Mr John Lowe be made a member of the implementation taskforce to which I refer in recommendation 70 |
REC126-1957 | 16 - Training and behaviour | That the Emergency Services Agency review the level of understanding among firefighting personnel of the latest information available nationally and internationally about wildfire behaviour and suppression and provide additional training if warranted |