Rec-ID | Code | Recommendation |
---|---|---|
REC316-4047 | 37 - Funding | Government consider an alternative funding arrangement for extraordinary costs borne by Government agencies in combating emergencies such as bushfires. |
REC316-4033 | 25 - Inquiry, audit, lessons management and after action review | The BFC Terms of Reference be reviewed to ensure they are contemporary and reflect learnings from this and recent bushfire seasons. |
REC316-4046 | 33 - Relief and recovery | Emergency Plan and Recovery sub-plans should be amended to better define recovery mechanisms and responsibilities, including hand over points to recovery authorities and community engagement for the delivery of long term recovery mechanisms. |
REC316-4018 | 25 - Inquiry, audit, lessons management and after action review | The five year review of the Emergencies Act examine amendments to better define the rationale for a State of Alert / State of Emergency whilst ensuring that the relevant Minister / Chief Minister still has sufficient discretion to make a declaration based on advice from relevant Government officials and committees. |
REC316-4045 | 42 - Culture and Heritage | WHoG desktop exercise should be conducted to test and support relocation and evacuation planning. |
REC316-4014 | 25 - Inquiry, audit, lessons management and after action review | That Justice and Community Safety Directorate (JACS) lead a working group from across relevant organisations to undertake the five year review of the Emergencies Act in conjunction with a wholistic review of the Emergency Plan and relevant sub-plans; and recommendations from this review, to the extent they are accepted by Government. Bringing together a small Taskforce of staff from across government for a set period would assist the working group in delivering the work needed to address these and other recommendations. |
REC316-4042 | 25 - Inquiry, audit, lessons management and after action review | ACT Government undertake a detailed legislative review to ensure that information regarding vulnerable community members can be appropriately accessed, provided and used during an emergency event. |
REC316-4041 | 9 - Community education | The ESA Community Education and Engagement program be adapted to include an expanded role for RFS volunteers and include a wider set of stakeholders who are more vulnerable to the impact of bushfire. A plan would require wider involvement across stakeholder organisations such as Directorates who have existing relationships with vulnerable groups. |
REC316-4048 | 37 - Funding | Government consider adopting a similar model to NSW for the management of emergency costs and reimbursements within ACT Government agencies. |
REC316-4038 | 25 - Inquiry, audit, lessons management and after action review | The CCIP be reviewed in conjunction with the review of the Emergency Plan and the two synchronised. A workable approach to delivering operational emergency communications and strategic WhoG communications is developed with simple and clear reporting arrangements. |
Rec-ID | Code | Recommendation |
---|---|---|
REC241-1033 | 37 - Funding | When a local Rural Fire Brigade requests an equipment and maintenance levy from a local government authority, that authority will either supply the brigade’s equipment and maintenance costs or raise the requested levy. The amount to be collected is to be agreed between the local Brigade and the local government authority. |
REC241-1032 | 37 - Funding | That the current Urban Fire Levy be changed to the Queensland Fire Levy. |
REC241-1030 | 25 - Inquiry, audit, lessons management and after action review | That Rural Fire Brigades only be required to conduct an audit of finances if the Brigades income exceeds $5,000 for a financial year. RFSQ District offices should investigate options for savings on the costs of auditing Brigades in their district through either an in-house or external provider. Legal Status of Brigades |
REC241-1016 | 6 - Insurance and legal liability | That a volunteer shall not be liable for any act or omission made in good faith provided it is not proven to be reckless, negligent or malicious. This protection is to be afforded in both Criminal and Common law. |
REC241-1035 | 37 - Funding | That the State Government contribution towards the purchase of operational vehicles is to be retained at 80 percent but that the District Inspector can recommend full Government subsidy of vehicles for Brigades experiencing financial hardship. |
REC241-0967 | 26 - Research | That a Rural Fire Research and Investigation Team be established to coordinate and communicate fire research knowledge, including fire behaviour as well as coordinate fire investigations and complaints for the state. |
REC241-1034 | 37 - Funding | That the State Government contribution towards the construction of Brigade sheds be changed from $10,000 to a maximum of 25 percent, subject to the approval of the Deputy Chief Officer, Rural Fire Service Queensland. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0699 | 6 - Insurance and legal liability | When a policy-holder makes a claim, the insurer should ascertain the policy-holder’s preferred method of contact and ensure that it is used (with other modes of communication if necessary) to keep the policyholder informed about the progress of the claim. However, important decisions regarding the claim – for example, determinations about the outcome of the claim and settlement sums – should always be confirmed in writing. |
REC210-0722 | 26 - Research | The Queensland Government should seek information about the size, features and condition of abandoned mines, including whether the mine or its surrounding environment were adversely affected by flood, from private landholders who have abandoned mines on their properties. |
REC210-0773 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should prioritise dam safety audits according to risk. The risk assessment should be informed by criteria including: • structure and materials used in construction • age of the dam • time since last inspection • occurrence of a flood event since last audit and the size of that flood event • population at risk if the dam were to fail • experience and capability of dam owner • dam owner compliance history • time since last audit. |
REC210-0737 | 25 - Inquiry, audit, lessons management and after action review | The Department of Environment and Resource Management should ensure that an independent and appropriately qualified person immediately starts the task of reviewing the March flood event report to ensure that the review is completed before the start of the 2012/2013 wet season. |
REC210-0602 | 26 - Research | A recent flood study should be available for use in floodplain management for every urban area in Queensland. Where no recent study exists, one should be initiated. |
REC210-0614 | 9 - Community education | Councils and the Queensland Government should display on their websites all flood mapping they have commissioned or adopted. |
REC210-0702 | 6 - Insurance and legal liability | The Insurance Council of Australia should consider an amendment to Part 3 of the code which requires insurers to notify policy-holders of the information on which they relied in assessing claims. |
REC210-0743 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should, in creating the new Wivenhoe and North Pine flood mitigation manuals, comprehensively consider: • the amount of discretion that is able to be exercised by the flood engineers and the senior flood engineers, and the description of the circumstances in which such discretion may be exercised • the circumstances in which it might be appropriate to release water in advance of an impending flood on the basis of forecasts from the Bureau of Meteorology • if strategies of the form of strategy W2 and W3 in Revision 7 are included in the revised manual, or any strategy defined as a ‘transition strategy’, when and how those strategies should be implemented • if the concept of ‘urban inundation’ is relevant to the operation of the dam, how it should be defined, and if the definition involves diverse concepts, how those concepts can be related back to the strategies, so that flood engineers can reach a clear understanding of their objectives and primary considerations • if the concept of ‘natural peak flow’ is relevant, how it should be defined. |
REC210-0689 | 9 - Community education | Councils should conduct education campaigns directed to ensuring that all residents and property owners in areas identified as being at risk of backflow flooding are aware of the circumstances in which backflow flooding can occur, the hazard it presents and what should be done if it occurs. |
REC210-0721 | 26 - Research | The Department of Employment, Economic Development and Innovation should assemble all information currently available to the abandoned mine land program into a single database. The Queensland Government should ensure, using whatever information is available, that the list of abandoned mines is as complete as possible. This should at least include a review of all information held by the Department of Environment and Resource Management and the Department of Employment, Economic Development and Innovation. |
REC210-0772 | 25 - Inquiry, audit, lessons management and after action review | Prior to each wet season, the Department of Environment and Resource Management should audit the compliance of each owner of a referable dam with the obligation to have an emergency action plan approved by the Queensland Government. |
REC210-0736 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that proper support and oversight mechanisms are put in place around both the substantive and procedural aspects of drafting flood event reports. Seqwater should consider engaging consultants with expertise in the production of reports following significant events to advise on these mechanisms. Measures to be considered should include: • ensuring appropriate systems are in place to ensure the recollections of flood engineers and other parties are recorded immediately after the event, perhaps by engaging an external party to interview the flood engineers and other parties • ensuring that a methodology for writing the report is set out clearly in advance, in writing, and that the final report includes a statement of that methodology • putting in place systems to ensure that members of senior management have sufficient understanding of both the methodology and process by which the report is prepared to allow themselves to be satisfied that these are appropriate. |
REC210-0601 | 26 - Research | Ipswich City Council should determine whether the results, models and maps produced by the Brisbane River flood study are sufficient for its floodplain management. If they are not, Ipswich City Council should ensure appropriate work is done by way of data collection and creation and hydrologic and hydraulic modelling for use in its floodplain management. |
REC210-0609 | 26 - Research | The Queensland Government and Commonwealth Government should ensure the existence and maintenance of a repository of data of the type used in flood studies. The database should include the types of data which the expert panel specified as needed for a comprehensive flood study. Councils, Queensland and Commonwealth Government agencies and dam operators should be able to deposit and obtain access to data. |
REC210-0701 | 6 - Insurance and legal liability | Letters notifying policy-holders that their claims have been denied should, at a minimum, state the information upon which the insurer has relied in making the decision. These letters should also advise policy-holders that copies of the information will be made available upon request (in accordance with clause 3.4.3 of the General Insurance Code of Practice) and indicate how policy-holders can make a request. |
REC210-0741 | 26 - Research | The steering committee of the North Pine Dam Optimisation Study should consider whether it would be beneficial for the floodplain management investigation to be removed from the North Pine Dam Optimisation Study. |
REC210-0686 | 6 - Insurance and legal liability | SunWater and the Central Highlands Regional Council should determine the issues of ownership and responsibility for maintenance of the LN1 drain system in Emerald. |
REC210-0709 | 26 - Research | The Queensland Government should determine, as far as possible, the impact of mine discharges during the 2010/2011 wet season on freshwater and marine water quality and fauna and flora. |
REC210-0767 | 26 - Research | The Department of Environment and Resource Management should require Wide Bay Water, in advance of every wet season, to provide details of its expectation as to the operability of the crest gates if a flood occurs, until such time as all gates have been demonstrated to work as designed. |
REC210-0735 | 6 - Insurance and legal liability | The Crime and Misconduct Commission should investigate whether the conduct of Mr Tibaldi, Mr Ayre and Mr Malone relating to: • preparation of documents surrounding the January 2011 flood event, including the 17 January 2011 brief to the Minister, the 2 March 2011 flood event report, and statements provided to the Commission • oral testimony given to the Commission evidences offence/s against the Criminal Code, and/or official misconduct under the Crime and Misconduct Act 2001 committed by any, or all, of them. |
REC210-0600 | 26 - Research | Brisbane City Council, Ipswich City Council and Somerset Regional Council and the Queensland Government should ensure that, as soon as practicable, a flood study of the Brisbane River catchment is completed in accordance with the process determined by them under recommendation 2.5 and 2.6. The study should: |
REC210-0606 | 26 - Research | When commissioning a flood study, the body conducting the study should: • check whether others, such as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology, are doing work that may assist the flood study or whether any significant scientific developments are expected in the near future, and decide whether to delay the study • discuss the scope of work with the persons to perform the flood study as well as surrounding councils which are not involved in the study, dam operators, the Department of Environment and Resource Management, and the Bureau of Meteorology |
REC210-0700 | 6 - Insurance and legal liability | Insurers should review their existing systems and processes and implement any improvements necessary to ensure that accurate and complete records of conversations with policy-holders are made. |
REC210-0740 | 26 - Research | The steering committees of the Wivenhoe Dam and Somerset Dam Optimisation Study and the North Pine Dam Optimisation Study should consider removing the water supply security investigation from each study. |
REC210-0680 | 9 - Community education | Queensland Urban Utilities, and other distributor-retailers and councils, that have identified a practice of stormwater drains being connected to sewerage infrastructure, should conduct a program of education to raise public awareness that this practice is illegal and impedes the operation of the sewerage infrastructure. |
REC210-0705 | 26 - Research | Any mine operator of a site at high risk of flood should obtain the best forecast information available (seasonal and short term) for the region in which the mine is located. |
REC210-0762 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should consider commissioning an investigation into the extent of cracking below the level of the upper gallery of Somerset Dam and the impact of any such cracking on the dam’s stability and, in turn, its operation. |
REC210-0732 | 37 - Funding | Emergency Management Queensland should develop and implement a new formula for the distribution of its recurrent SES subsidy, which takes into account relevant factors including the size of a local SES contingent and the population, area and natural hazard risk profile of the local government area concerned. |
REC210-0599 | 26 - Research | The steering committee of the Wivenhoe Dam and Somerset Dam Optimisation Study should consider whether it would be more effective for the floodplain management investigation to be removed from the Wivenhoe Dam and Somerset Dam Optimisation Study. |
REC210-0604 | 9 - Community education | By reference to the order of priority determined in accordance with recommendation 2.5, the Queensland Government and councils should together ensure that the council responsible for each urban area in Queensland has access to current flood study information. This will include determining: a. a process or processes by which the flood studies will be completed, including the involvement of the Queensland Government and relevant councils b. how, and from whom, the necessary technical and financial resources will be obtained c. a reasonable timeframe by which all flood studies required will be completed. |
REC210-0739 | 26 - Research | The Queensland Government should resolve the discrepancy in recorded peak river height for the January 2011 flood of the Brisbane River between the Brisbane City and Port Office gauges. |
REC210-0678 | 26 - Research | Queensland Urban Utilities should make the results of its trials on the use of caps for overflow relief gully grates available to other authorities responsible for sewerage infrastructure. Consideration should be given by those authorities as to how the results can be used to improve the flood resilience of their sewerage networks. |
REC210-0704 | 26 - Research | Mine operators should obtain all public seasonal forecasts issued by the Bureau of Meteorology relevant to the regions in which their operations are located. |
REC210-0747 | 6 - Insurance and legal liability | Seqwater should ensure a legal review of the Wivenhoe manual and the North Pine manual is completed before the manual is submitted for approval. |
REC210-0726 | 25 - Inquiry, audit, lessons management and after action review | The Queensland Fire and Rescue Service should require that each region records in writing the results of its risk assessment undertaken as part of its annual review of its special operations functional plan. |
REC210-0738 | 25 - Inquiry, audit, lessons management and after action review | Seqwater should ensure that any future peer review process: • is co-ordinated by someone independent of those who wrote the report • entails the provision of all relevant information to the peer reviewers • permits sufficient time for the review • documents all contact between those whose actions are under review and the reviewers. |
REC210-0603 | 9 - Community education | The Queensland Government, in consultation with councils, should determine which urban areas in Queensland do not have access to flood information from a current flood study. The Queensland Government should rank those areas in order of priority in accordance with their need for updated flood information by reference to factors including: a. population b. sophistication of land use planning and emergency management measures already in place in those areas c. currency of any flood risk information available to the council d. approximate frequency of damaging floods in the area according to the historical record |
REC210-0615 | 9 - Community education | Flood maps, and property specific flooding information intended for use by the general public, should be readily interpretable and should, where necessary, be accompanied by a comprehensible explanatory note. |
REC210-0703 | 6 - Insurance and legal liability | The Insurance Council of Australia should amend clause 3.4.3 of the General Insurance Code of Practice so that it requires insurers to inform policy-holders of their right to request a review of an insurer’s decision to refuse to provide access to information on which it relied in assessing claims. |
REC210-0744 | 26 - Research | The conditions for the use of a particular strategy in all flood mitigation manuals should reflect objective standards. |