REC314-3263 | 4 - Fire season preparation | Clarify and streamline processes and educate the community about their roles and responsibilities in managing native vegetation to improve hazard reduction on both public and private land. Provide additional resources to manage fuel in a shorter off fire season and develop a risk reduction target linked to prioritised objectives. |
REC314-3262 | 10 - Infrastructure | Invest in upgrading and integrating ICT platforms to eliminate manual data transfers, and ensure IT and radio communication interoperability across the agencies, together with a dedicated focus on the development of a coordinated risk intelligence capability to provide all stakeholders with a common operating picture and rapid damage assessments. |
REC314-3261 | 24 - Govt responsibility | Consider amending the Fire and Emergency Services Act 2005 to align SAFECOM Board operations with accepted governance standards with the Minister appointing an Independent Chair of the SAFECOM Board. The SAFECOM Chief Executive (CE) should report to the Board and maintain SAFECOM’s role at the direction of the Board. Alternatively, SAFECOM could be abolished, moving to a model of a Department of Fire and Emergency Services where the departmental head reports to the Minister but the value proposition of any such machinery of government change would need to be thoroughly examined. |
REC314-3272 | 10 - Infrastructure | Clarify business continuity and restoration of critical infrastructure in the planning and response phases to facilitate water replenishment, fireground remediation and access to businesses (including farming properties). |
REC314-3270 | 17 - Assets and technology | Review the use of aviation assets including facilities to operate them given the increased pressure from extended fire seasons on northern and southern hemisphere resources. Review line scanning capability with a view to providing real time data to the IMTs on where fires are burning using aviation assets as an intelligence tool rather than just a fire suppression capability. |
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2392 | 39 - Disaster Risk Management | TFS should engage in discussions with government about the construction of purpose-built State Control Centre facilities for emergency management in Tasmania. |
REC301-2385 | 25 - Inquiry, audit, lessons management and after action review | TFS should initiate a policy review (seeking support from government as appropriate) to clearly identify what body or agency is responsible for planning, carrying out and enforcing fuel management on private property at a township level. If current arrangements are unclear or ineffective, TFS should request government to consider making this a statutory responsibility of TFS and provide any additional funding required to support this function. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1261 | 28 - Personal responsibility | That heightened awareness and action is needed by communities when BoM issues flood watches and related warnings. Councils and SES need to facilitate this. |
REC297-1271 | 1 - Land-use and building regs | That the organisations responsible for construction, maintenance and ownership of bridges review their design guidelines and, if necessary, update them to specifically include consideration of debris and flood impacts on bridge design. A review of existing bridges by the responsible organisations could also be undertaken to highlight any potential issues. |
REC297-1251 | 9 - Community education | That all councils include an easily identifiable website link for the public to locate their Municipal Emergency Management Plan and community safety information. |
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1270 | 24 - Govt responsibility | That, in the event of a major emergency such as the June floods, a government department (DPAC or State Growth) be appointed to coordinate infrastructure repair, to the extent that funding allows, for the whole state. Individual entities will still have the right and responsibility to repair and maintain their own assets, but some central oversight and coordination is, in our view, likely to be beneficial. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1269 | 35 - Business and Industry in relation to industry | That Government engages with non-government organisations that may provide services during emergency events to clarify the terms and conditions for support through a written arrangement (MOU or similar). |
REC297-1257 | 35 - Business and Industry in relation to industry | That in the event that Hydro Tasmania decides to start cloud seeding again, water managers, represented by DPIPWE, work with Hydro Tasmania to ensure appropriate, best practice application of the guidelines issued by the Agricultural and Resource Management Council of Australia and New Zealand. |
REC297-1268 | 24 - Govt responsibility | That DPAC becomes the Management Authority for recovery in Tasmania. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1256 | 9 - Community education | That SES and Tasmania Fire Service share resources and align their community education programs and adopt an all-hazards approach to awareness. |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1272 | 1 - Land-use and building regs | That, to provide greater clarity for building development, design and approval within tolerable risk levels, the Tasmanian Planning Scheme, including a relevant Riverine Flood Hazard Code, is finalised and approved as soon as practicable. |
REC297-1255 | 24 - Govt responsibility | That Government establishes a central flood policy unit responsible for coordinating flood policy across all government agencies, including Government Businesses, and ensures that such a unit has a whole-of-government and community focus. |
Rec-ID | Code | Recommendation |
---|---|---|
REC296-1352 | 10 - Infrastructure | A monthly testing regime needs to be developed that will allow the generator to be tested at full essential load capacity and to ensure that 4 hour monthly testing can be done every month. |
REC296-1357 | 10 - Infrastructure | Monthly test results need to be accurately recorded. |
REC296-1362 | 10 - Infrastructure | Carry out a detailed audit of the current Hospital essential loads to determine the current load requirements of the Hospital. |
REC296-1351 | 10 - Infrastructure | From the above assessment determine the existing generator load requirements and provide a new generator to meet those loads. |
REC296-1356 | 10 - Infrastructure | Accurate records need to be provided as to what is done for each service. |
REC296-1361 | 10 - Infrastructure | Prepare and carry out a testing regime and testing strategy and ensure testing of the generator is done every month for 4 hours over that month and under full Hospital load with test result recorded every 15 minutes. |
REC296-1350 | 10 - Infrastructure | Remove any loads that do not need to be on essential power. |
REC296-1355 | 10 - Infrastructure | Replacement of all original pipes and hoses not yet done. |
REC296-1360 | 10 - Infrastructure | Carry out regular load bank testing on the generator with a load bank large enough to fully load the generator to 110% which will clean out the engine and also identify whether the generator is capable of providing full load for a sustained length of time. |
REC296-1349 | 10 - Infrastructure | Conduct an assessment of the current essential loads and determine if there are loads that should not be on essential power. |
REC296-1354 | 10 - Infrastructure | Monthly and annual maintenance servicing needs to be scheduled for the generator to DPTI or CHSA schedule requirements. |
REC296-1359 | 10 - Infrastructure | Renegotiate the maintenance contract at the end of the current contract and have DPTI through AGFMA take on the maintenance contract. |
REC296-1353 | 10 - Infrastructure | Regular annual testing at 100% on a load bank needs to be scheduled into a maintenance schedule. |
REC296-1358 | 10 - Infrastructure | If the existing generator is capable of providing the current essential power requirements then the generator needs a major inspection and overhaul all items that may need to be replaced due to age and condition. This includes checking compression, oil pressure, coolant pumping and all other critical components and may actually require providing a temporary generator while the Hospital generator receives a major inspection and possible re build. A ball park figure to do this would be $50,000.00 plus cranage and transport to Detroit workshop probably another $10,000.00 then a temporary generator would need to be hired and installed which could run into $10’s of thousands of dollars depending on how long the engine was out of service. For the money that would be spent checking and rebuilding the existing engine it would be recommended to replace the generator with a new generator. |
REC296-1363 | 10 - Infrastructure | Due to the age of the generator, reliability and reparability risk due to age and the apparent under capacity of the generator it is recommend to replace the generator with a new generator and associated control system designed for the current load requirements and allowance for some future expansion. |
Rec-ID | Code | Recommendation |
---|---|---|
REC295-1300 | 17 - Assets and technology | That the State Emergency Service explores options for providing suitable personal protective clothing to personnel from supporting emergency services during major flooding events and sandbagging operations. |
REC295-1315 | 25 - Inquiry, audit, lessons management and after action review | That a review of the role and effectiveness of the State Emergency Management Committee (SEMC) including: the legislative functions; membership including the chair; roles and responsibilities; and, SEMC Advisory Groups be undertaken. |
REC295-1279 | 10 - Infrastructure | Install UPS on traffic lights on main Central Business District (CBD) and arterial roads to allow an effective movement of traffic during a loss of power. |
REC295-1320 | 17 - Assets and technology | Review existing electronic information systems used by emergency services organisations and other government agencies, and: a) establish a single incident information system across the Emergency Services Sector (MFS, CFS and SES), and b) identify opportunities to consolidate incident information systems of other agencies |
REC295-1299 | 17 - Assets and technology | That systems for Automatic Vehicle Location and personnel tracking be implemented within the emergency services sector. |
REC295-1312 | 24 - Govt responsibility | That the Department of Education and Child Development be included as a member of State Emergency Management Council and represented in the State Emergency Centre. |
REC295-1276 | 25 - Inquiry, audit, lessons management and after action review | That SA Health undertake a review of their emergency management arrangements. Health State Controllers should be consulted during this review and arrangements should be consistent throughout the department and across the State and compatible with State emergency management arrangements and information systems |
REC295-1319 | 24 - Govt responsibility | That a single emergency service multi-agency control centre be established with sufficient capacity and capability to deal with all types of emergency incidents in SA. Also consider Police and State Emergency Centre. |
REC295-1297 | 25 - Inquiry, audit, lessons management and after action review | Engage an independent business analyst to review the current call, receipt and dispatch process for emergency services i.e. the Metropolitan Fire Service, Country Fire Service and State Emergency Service, from the initial call for assistance through to response of emergency service resources, including the allocation and coordination of multiple taskings. |
REC295-1308 | 24 - Govt responsibility | That the Department of the Premier and Cabinet revise the ministerial documents relating to emergency management. |
REC295-1274 | 35 - Business and Industry in relation to industry | That relevant agencies, such as the Department of State Development, SA Police and emergency services, collaborate to establish an education campaign to encourage businesses in South Australia to develop Business Continuity Plans which, among other potential hazards such as flood and fire, also take into account the potential impact of an extended power outage. |
REC295-1318 | 24 - Govt responsibility | That the recommendation made following the Pinery bushfire, ‘to review control facilities at State, region and incident level’, be expanded to include all emergency services facilities that will be utilised for major incidents other than bushfire e.g. flood and earthquake and to also be extended into metropolitan areas, and implemented. |
REC295-1291 | 24 - Govt responsibility | That the Flood Reform Task Group, as proposed by the Department |
REC295-1306 | 9 - Community education | Develop practical policy outcomes to support resilience (e.g. the 72- hour model) and promote this broadly to community through media, awareness campaigns, policies etc. Research should be undertaken to gain insight into the types of messaging and activities that have the most impact on sustained behaviour change within the community before committing to a particular model. |
REC295-1317 | 25 - Inquiry, audit, lessons management and after action review | Review representation in the State Emergency Centre including: a) determining if there is a more suitable functional support group e.g. the Procurement Functional Support Group, to replace the Logistics Functional Support Group, and if so, Chief Procurement Officer, DPC, has responsibility for the management of this role within the State Emergency Centre. b) That when the State Crisis Centre is not operating from a physical location, a State Crisis Centre liaison officer is attached to the State Emergency Centre. |
REC295-1288 | 24 - Govt responsibility | That Attorney General’s Department explore options to overcome fatigue and welfare issues of SAGRN staff associated with emergency events of extended duration. |
REC295-1328 | 25 - Inquiry, audit, lessons management and after action review | Update the SEMP Part 3, Annex F ‘Debriefs’ to provide more guidance regarding the types of debriefs, when they are required to be undertaken and at what level and guidance for undertaking and recording debriefs, and implementing lessons identified. |
REC295-1302 | 28 - Personal responsibility | That the State Emergency Service together with the Local Government Association and Country Fire Service establish a plan for coordinated provision of sandbags to the public, including options for what is provided, where and when, and the process for effective communication of availability to the public. |
REC295-1316 | 24 - Govt responsibility | That the position of Deputy Director, Office for Digital Government is dedicated to the Office for Digital Government; and that people throughout DPC are identified and trained to perform appropriate roles within the State Crisis Centre |
REC295-1286 | 10 - Infrastructure | That the Attorney General’s Department consult with local government regarding potential for them to provide logistical support associated with backup power supply to SA Government Radio Network towers in the event of an emergency. |
REC295-1327 | 25 - Inquiry, audit, lessons management and after action review | Establish a lessons management capability across the SA emergency management sector to collect, analyse and track lessons identified during debriefs and reviews following events and other sources such as interstate and oversees reviews and inquiries. |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1184 | 24 - Govt responsibility | The Tasmanian fire agencies think more broadly about how staff who are already employed by Government could support the management of future emergencies. |
REC287-1188 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies commission a review into the efectiveness of aerial firefghting in the 2016 fires, in order to better understand and to document for future reference the cost-efectiveness of specifc fire suppression strategies and tactics in different vegetation types. The Review should include a comparative analysis of fire suppression options whether aerial or ground-based. |
REC287-1186 | 9 - Community education | The Tasmanian fire agencies review: • their pre-season engagement with groups such as (but not limited to) environmental groups who might beneft from a greater understanding of fire management tactics, in order to inform them of and receive feedback on intended approaches to firefghting and fire management the work of the Public Information Section at incident management, regional and State level, to develop an increased appreciation of what information management might be most appropriate to serve the public interest in understanding the progress of the incident and to identify ways of providing surge capacity to resource effective information management in protracted and signifcant incidents. |
REC287-1185 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies take steps at a national level to share learnings from the 2016 fires about the administration of interstate assistance and support the codifcation of the workings, structure and reporting lines of an Interstate and International Liaison Unit for future complex deployments within Australia and New Zealand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC284-1369 | 10 - Infrastructure | Review all generator locations for arrangements for temporary generator installation, including design of modifications as required for electrical connections and spatial requirements at installation locations, to be documented in an emergency procedure. |
REC284-1374 | 10 - Infrastructure | Provide walls around critical electrical infrastructure within the main plant area to provide security and protection from catastrophic water system failures. |
REC284-1368 | 10 - Infrastructure | Improvements to installation to be implemented as follows: - Lighting within the generator enclosure and immediately adjacent to be emergency battery-backed type. - Improvements to the spatial layout within the main generator enclosure should be investigated, including allowance for the control panel door to open 180o (only 90o currently); moving the fuel pumps to a more accessible location, and ensuring clear access to the day tank for manual filling if required. - Improvements to communications facilities between critical areas, including fixed phone line connections between the main control room, main generator control panel in the P (energy) Building, and the generator enclosure, and allowing link to offsite specialist advice. - Where generator maintenance requires operations outdoors (not applicable to main generator, but applicable to others), a shelter over the relevant area should be provided to allow safe work during wet or hot weather. - Written emergency procedures to be prepared covering credible failure scenarios with step by step checklists and recommended actions. |
REC284-1373 | 10 - Infrastructure | Review generator installations details as noted in report and implement physical improvements where possible. |
REC284-1367 | 10 - Infrastructure | Add to generator test procedure a checklist at the end of testing which includes checking that all systems are back to normal positions and includes a requirement to leave the day tank full where there is a bulk tank/day tank arrangement. |
REC284-1372 | 10 - Infrastructure | As part of the electrical master plan update recommended above, a complete and consistent set of single line diagrams describing the electrical distribution network be prepared. Relevant diagrams to be laminated and displayed in the main substations. Labelling to all main electrical equipment be reviewed and updated in accordance with the final documents. |
REC284-1366 | 10 - Infrastructure | A detailed review of the fuel control and BMS systems (for all generators) be carried out and actions taken to: 1) Ensure that the fuel alarm system is operational and properly calibrated, and ensure that the alarms are connected to the BMS. 2) Ensure that the BMS transmits these alarms effectively to the maintenance staff. 3) If this review demonstrates risk of fuel control systems not adequately reporting alarms, consider an independent day tank level switch to be installed in each generator fuel tank, directly connected to the BMS. 4) Consider the feasibility of adding a “fuel system not in auto” or “fuel system fault/fail safe watchdog” or “pre-alarm identifying that the generator is about to shut down without intervention” feature to current systems – subject to details of each individual generator system. |
REC284-1371 | 10 - Infrastructure | Generator dual redundant starter systems should be considered. |
REC284-1365 | 10 - Infrastructure | The electrical master plan for the site should be updated to include planning for the scheduled replacement or refurbishment of those parts of the infrastructure that have not been renewed in the last 10 years. This planning to consider other upgrades or plans for the FMC overall. |
REC284-1370 | 10 - Infrastructure | Review control system for the main generator normal/essential changeover system and ensure that it has effective backup/manual or redundant operations, and suitable testing facilities. The Essential board that supplies the main generator power to Blocks A, B, C (except theatres), D, E (except certain critical engineering plant) (MD-1-4P-10E), is a potential single point of failure of a significant portion of the emergency power system and as part of the Master Plan update should be considered as a priority. |
Rec-ID | Code | Recommendation |
---|---|---|
REC273-1141 | 21 - Role of Commonwealth Government | SACFS and the BoM review current weather, fuel loads and curing rates to determine the most appropriate and accurate forecast is prepared, issued and validated against current conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0942 | 1 - Land-use and building regs | That the Government makes land use planning and building construction to prevent and mitigate bushfire risk a high priority and establishes a means to progress improvements in this area, such as a designated body or group, as soon as possible. |
REC247-0894 | 17 - Assets and technology | That the police and other emergency service organisations discuss their resource issues for emergency operations with the Government. |
REC247-0926 | 25 - Inquiry, audit, lessons management and after action review | That membership of the State Emergency Management Committee, and other processes to link in appropriate agencies and organisations to emergency management, be included in the recommended review of the emergency management arrangements. |
REC247-0878 | 17 - Assets and technology | That bushfire agencies evaluate the use and effectiveness of fixed wing water bombing aircraft. |
REC247-0934 | 4 - Fire season preparation | That the State Fire Management Committee considers developing a structured, systemic and proactive bushfire hazard reduction program with municipal councils and Tasmania Fire Service; and advises the Government on any legislative or other changes required to implement such a program. |
REC247-0941 | 25 - Inquiry, audit, lessons management and after action review | That the Strategic Fuel Management Plan includes measurable targets and they are actively monitored and reported on to the community. |
REC247-0893 | 17 - Assets and technology | That further options to appropriately supplement the resources available for emergency management operations be examined. |
REC247-0923 | 25 - Inquiry, audit, lessons management and after action review | That a process be established for the timely implementation of approved recommendations from the 2009 Victorian Bushfires Royal Commission. |
REC247-0873 | 25 - Inquiry, audit, lessons management and after action review | If it is considered more information is required on action to suppress the fires in Dunalley and why fire operations did not continue, the Department of Justice should conduct an independent examination of this matter. |
REC247-0933 | 4 - Fire season preparation | That the Government considers whether a peak body should be established, with authority to effectively implement a bushfire mitigation plan. |
REC247-0939 | 5 - Hazard reduction burns | That Tasmania Fire Service conducts a review of the fire permit system in the Fire Service Act 1979, and implements change to improve the efficiency and effectiveness of the system by: • considering whether it is appropriate to authorise persons or organisations to conduct fuel reduction burning during a permit period • providing a better match between the period, area and fire risk • maintaining a timely and efficient process for issuing permits • naming the period in a way that draws attention to bushfire risk • establishing a reporting and accountability process. |
REC247-0892 | 17 - Assets and technology | That a review be conducted of the resource capacity and capability to provide effective and efficient emergency operations, including approved improvements. |
REC247-0951 | 25 - Inquiry, audit, lessons management and after action review | That an independent means of monitoring and reporting on the implementation of approved recommendations is established. |
REC247-0909 | 25 - Inquiry, audit, lessons management and after action review | That the plans for social recovery be reviewed, and plans and procedures are established ready for implementation. |
REC247-0855 | 17 - Assets and technology | That a structure and facilities be established for the State Controller or other person managing multi-agency response and recovery operations. |
REC247-0931 | 4 - Fire season preparation | That a specific risk prevention and mitigation advisory body be established for the State Emergency Management Committee. |
REC247-0938 | 5 - Hazard reduction burns | That Tasmania Fire Service or another suitable agency provides information to the community which shows, in simple form, the legislation applicable to approvals for lighting fires on private property and the various relationships between that legislation. |
REC247-0891 | 9 - Community education | That emergency management plans specifically include processes for effectively engaging with local communities and using community resources, including volunteers. |
REC247-0944 | 9 - Community education | That the State Emergency Management Committee develops and coordinates a whole-of-government community resilience strategy for emergencies in a form that can be practically implemented, as a priority. |
REC247-0904 | 10 - Infrastructure | That the Department of Infrastructure Energy and Resources consult Aurora Energy on the use of wooden poles for overhead infrastructure with a view to mitigating the risk in bushfires. |
REC247-0928 | 24 - Govt responsibility | That the Government take into account demographic change in its assessment of the consequences of climate change on emergency events. |
REC247-0937 | 19 - Offences | That the legislation and enforcement arrangements are reviewed to ensure there are suitable offences and penalties, investigation and enforcement capabilities, and a rigorous approach is taken to breaches of the law. |
REC247-0880 | 17 - Assets and technology | That bushfire agencies develop, implement and maintain air operations procedures. |
REC247-0943 | 9 - Community education | That a bushfire community education and information strategy be professionally developed and coordinated across the fire authorities by Tasmania Fire Service. |
REC247-0903 | 25 - Inquiry, audit, lessons management and after action review | That the role of Red Cross in emergency management plans and procedures for the activation of Red Cross be reviewed. |
REC247-0927 | 25 - Inquiry, audit, lessons management and after action review | That an accountability process be established for managing improvement in the emergency management arrangements, including annual State of Readiness Reports by relevant departments and agencies and on the overall emergency management arrangements. |
REC247-0879 | 17 - Assets and technology | That bushfire agencies develop procedures for the automatic activation of aircraft to fires at pre-determined trigger points on high fire risk days. |
REC247-0935 | 4 - Fire season preparation | That the State Emergency Management Committee includes in its planning, the development of contingency emergency management plans for areas of high risk due to local conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC244-2605 | 39 - Disaster Risk Management | A thorough consultative process be developed and implemented between the CFS and local government. This will determine how bushfire management planning can enable improved process and practice to mitigate bushfire risk, and ensure that fire permits are issued and complied with. |
REC244-2631 | 25 - Inquiry, audit, lessons management and after action review | Review Section 134 to ensure that it is not a deterrent to a group of farm fire units operating at an incident. |
REC244-2601 | 25 - Inquiry, audit, lessons management and after action review | That an independent review of the operational and geographic boundaries of the ESOs be conducted recognising the limitations of the current governance structures to adequately address such issues. Such a review needs to be performed periodically, but not less than every 8 years. |
REC244-2627 | 4 - Fire season preparation | Government in conjunction with the CFS identify the ownership of disused railway corridors which may pose a significant fire risk and ensure the agency or individual responsible for the land complies with legislative requirements. |
REC244-2600 | 25 - Inquiry, audit, lessons management and after action review | An external audit of shared services performed by SAFECOM and services now provided by the three ESOs which have the potential to be shared, be undertaken to determine the most efficient and cost effective way such services can be delivered to the sector. The three ESO Chiefs need to have input into this process. |
REC244-2620 | 25 - Inquiry, audit, lessons management and after action review | Review employment conditions under the F&ES Act to align with those under the Public Sector Act unless there is a compelling reason to the contrary. |
REC244-2617 | 25 - Inquiry, audit, lessons management and after action review | When judging major incidents in the future, consideration be given to Eburn and Dover’s proposal to establish processes with a statutory basis that sufficiently balance the community’s interests in ensuring that true lessons, including lessons of error or neglect, are identified, whilst also protecting members of the emergency services. Processes need to be developed for emergency services such as those used in aviation and medicine, to facilitate open and honest disclosure of errors. |
REC244-2606 | 22 - Role of local Gvt | The Act be amended to require the mandatory appointment of Authorised Officers by each rural council or council that has within its area a Designated Urban Bushfire Risk Area(s) with an option for the CFS Chief Officer to exempt council from this requirement (similar to Section 105B). |
Rec-ID | Code | Recommendation |
---|---|---|
REC151-3071 | 24 - Govt responsibility | The comprehensive prevention, preparedness, response and recovery (PPRR) approach to the management of bushfires as recommended by the Ministerial Review of Bushfire Management in South Australia is supported: its implementation should consider issues raised by councils and should also be considerate of the recommendations of the Wangary Coronial Inquest. |
REC151-3095 | 24 - Govt responsibility | SAFECOM re-evaluate and determine a more meaningful definition of fire districts. |
REC151-3092 | 19 - Offences | Expiation fees be reviewed so as to be consistent with the seriousness of the offences. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3575 | 24 - Govt responsibility | The preferred model for the Tasmanian Medical Retrieval Services is to have TMRS and NETS staff based in RHH. The fixed wing would remain based in Launceston (for the present) with the helicopter to remain based in Hobart. |
REC140-3560 | 17 - Assets and technology | RHH requires a helipad. Plans to rebuild RHH must include a helipad at its earliest stage of conception. |
REC140-3574 | 38 - Agency/Department Reporting | Formation of a subcommittee of the DHHS Tasmanian Medical Retrieval Services Committee to identify risk exposures, system problems and potential solutions. The subcommittee should review data, problem cases, system issues and generate a risk register. Meetings should occur at least quarterly. |
REC140-3559 | 17 - Assets and technology | A service level agreement is negotiated with the Police department that will cover access, tasking, price, equipment and staffing. This will enable a more strategic use of the helicopter. |
REC140-3565 | 17 - Assets and technology | The TMRS medical equipment inventory requires an overhaul. The TMRS medical equipment should be located with the TMRS team. |
REC140-3556 | 17 - Assets and technology | The use of hospital transport vehicles to support retrieval operations be investigated. |
REC140-3564 | 17 - Assets and technology | The medical equipment used in retrieval and air ambulance duties undertaken by helicopter and fixed wing must be standardised. |
REC140-3563 | 17 - Assets and technology | An additional secure emergency oxygen supply source to be located in the BK 117 helicopter. An internal supply is preferred. |
REC140-3561 | 17 - Assets and technology | Development of a helipad at Mersey Hospital. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3989 | 17 - Assets and technology | The Commission recommends that there be continuous supervision of every chamber in which electrical machinery is worked by currents of medium pressure. |
REC008-3987 | 17 - Assets and technology | The Commission recommends that systematic tests be made and recorded of apparatus and circuits as a precaution against fire and so that any gradual deterioration of the system may be detected. |
REC008-3986 | 17 - Assets and technology | The Commission recommends that every precaution be taken to keep water off electrical machinery. |
REC008-3985 | 17 - Assets and technology | The Commission recommends that conductors carrying currents at medium pressure should not be encased in wood in damp places. |