Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC301-2391 | 12 - EM agency and authority | TFS, PWS and STT should jointly carry out work to identify acceptable shift lengths and patterns – including requirements for rest days – for all personnel working on emergency operations. Once these have been identified, systems should be put in place to ensure that HR rostering practices follow these fatigue management guidelines. And senior staff should lead by example and ensure that they, as well as the people working under them, take adequate rest breaks. |
REC301-2390 | 12 - EM agency and authority | TFS, PWS and STT should jointly reach a decision on whether a winch capable remote area firefighting capability should be maintained in Tasmania; which agency or agencies should be responsible for that program; and how a winch capable remote area firefighting capability can be safely trained and kept current, to include consideration of the availability of winching aircraft. If the decision is taken not to maintain this capability in the state, TFS, PWS and STT should identify how the gap in capability that this represents should be filled in future fire seasons. |
REC301-2389 | 12 - EM agency and authority | The proposed Tasmania State Air Desk should have a finance officer attached to its staff. |
REC301-2385 | 25 - Inquiry, audit, lessons management and after action review | TFS should initiate a policy review (seeking support from government as appropriate) to clearly identify what body or agency is responsible for planning, carrying out and enforcing fuel management on private property at a township level. If current arrangements are unclear or ineffective, TFS should request government to consider making this a statutory responsibility of TFS and provide any additional funding required to support this function. |
Rec-ID | Code | Recommendation |
---|---|---|
REC297-1259 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the Forest Practice Code 2015 for relevance of its concepts to farming and other business activities near rivers, streams and naturally occurring dams and makes recommendations to Government accordingly. |
REC297-1273 | 25 - Inquiry, audit, lessons management and after action review | That the State Emergency Management Committee allocates resources to reviewing all findings and recommendations in the Productivity Commission Report No. 74 relevant to Tasmania and, for those identified as relevant, actions taken and, if none, why not. |
REC297-1258 | 25 - Inquiry, audit, lessons management and after action review | That DPIPWE examines the WMAwater report along with its own, analyses the differences, consults with the Forest Practices Authority and Environment Protection Authority, and proposes an appropriate course of action to Government. |
REC297-1265 | 13 - Mapping and data quality | That BoM and the Flood Warning Consultative Committee, in consultation with gauge owners, review flood gauges and develop a program to update data used to support hydrologic modelling. This should include reviewing gauge maintenance before and after floods. |
REC297-1254 | 13 - Mapping and data quality | That Government: |
REC297-1264 | 25 - Inquiry, audit, lessons management and after action review | That the Flood Warning Consultative Committee reviews flood classification levels in the Service Level Specifications with BoM specifically relating to flood level triggers on gauges. |
REC297-1253 | 13 - Mapping and data quality | That agencies undertaking flood studies adopt a standardised approach, based on Australia Handbook 7, maintain public ownership of underlying data sets to support future modelling, and ensure open access to these studies. |
REC297-1263 | 13 - Mapping and data quality | Subject to funding, that the Flood Warning Consultative Committee investigates the hydrological matters and advice received during this Review and detailed in this Report in Sections 4.1.9 and 4.1.11. |
REC297-1252 | 13 - Mapping and data quality | That SES uploads current flood studies and plans to the Common Operating Platform as a flood plan layer and that councils, subject to resolving licence restrictions, arrange to have appropriate access. |
REC297-1262 | 13 - Mapping and data quality | That the Flood Warning Consultative Committee considers the merits of delineating the Ouse River as a separate catchment from the Derwent River Basin. |
REC297-1250 | 22 - Role of local Gvt | That in flood-prone municipalities, the respective Municipal Committee develops or reviews flood-related sub-plans within a Municipal Emergency Management Plan at least every two years and submits each sub-plan to the Regional Controller for approval. In addition, that each Municipal Committee maintains a current flood plan, in a standardised format, which at least identifies: • flood-prone parts of their locality, particularly those where lives may be at risk; • required actions to be taken in the event of a flood threat, especially timely evacuation; • trigger points for taking required actions and how those trigger points will be monitored; and • how the community can access flood-plan information |
Rec-ID | Code | Recommendation |
---|---|---|
REC287-1188 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies commission a review into the efectiveness of aerial firefghting in the 2016 fires, in order to better understand and to document for future reference the cost-efectiveness of specifc fire suppression strategies and tactics in different vegetation types. The Review should include a comparative analysis of fire suppression options whether aerial or ground-based. |
REC287-1185 | 25 - Inquiry, audit, lessons management and after action review | The Tasmanian fire agencies take steps at a national level to share learnings from the 2016 fires about the administration of interstate assistance and support the codifcation of the workings, structure and reporting lines of an Interstate and International Liaison Unit for future complex deployments within Australia and New Zealand. |
Rec-ID | Code | Recommendation |
---|---|---|
REC247-0849 | 26 - Research | That Tasmania Fire Service supports the relevant authorities to continue developing methodologies to forecast and simulate fire risk. |
REC247-0907 | 33 - Relief and recovery | That the State Emergency Management Committee ensures that a program of debriefing on recovery issues is completed by all relevant agencies and organisations, and detailed plans and operating procedures are established ready for implementation. |
REC247-0866 | 26 - Research | That fire agencies continue to develop their predictive modelling capability for use in actively managing fires. |
REC247-0926 | 25 - Inquiry, audit, lessons management and after action review | That membership of the State Emergency Management Committee, and other processes to link in appropriate agencies and organisations to emergency management, be included in the recommended review of the emergency management arrangements. |
REC247-0892 | 17 - Assets and technology | That a review be conducted of the resource capacity and capability to provide effective and efficient emergency operations, including approved improvements. |
REC247-0903 | 25 - Inquiry, audit, lessons management and after action review | That the role of Red Cross in emergency management plans and procedures for the activation of Red Cross be reviewed. |
REC247-0860 | 13 - Mapping and data quality | That Tasmania Fire Service establishes suitable systems and practices for recording fire management objectives and tactics. |
REC247-0923 | 25 - Inquiry, audit, lessons management and after action review | That a process be established for the timely implementation of approved recommendations from the 2009 Victorian Bushfires Royal Commission. |
REC247-0880 | 17 - Assets and technology | That bushfire agencies develop, implement and maintain air operations procedures. |
REC247-0896 | 33 - Relief and recovery | That the state level structural arrangements for managing recovery operations are reviewed. |
REC247-0855 | 17 - Assets and technology | That a structure and facilities be established for the State Controller or other person managing multi-agency response and recovery operations. |
REC247-0921 | 26 - Research | That Tasmania Fire Service promotes a structured approach to research across Australia, to provide a shared understanding and the capacity to benchmark and judge performance. |
REC247-0879 | 17 - Assets and technology | That bushfire agencies develop procedures for the automatic activation of aircraft to fires at pre-determined trigger points on high fire risk days. |
REC247-0951 | 25 - Inquiry, audit, lessons management and after action review | That an independent means of monitoring and reporting on the implementation of approved recommendations is established. |
REC247-0895 | 6 - Insurance and legal liability | That action be taken as a priority to resolve any legal issues on mutual assistance arrangement for fire services. |
REC247-0851 | 13 - Mapping and data quality | That if a sound business case is developed, the Emergency Information Management and Sharing Project be supported. |
REC247-0910 | 33 - Relief and recovery | That suitable facilities are established from which to effectively control and coordinate immediate recovery operations. |
REC247-0878 | 17 - Assets and technology | That bushfire agencies evaluate the use and effectiveness of fixed wing water bombing aircraft. |
REC247-0941 | 25 - Inquiry, audit, lessons management and after action review | That the Strategic Fuel Management Plan includes measurable targets and they are actively monitored and reported on to the community. |
REC247-0894 | 17 - Assets and technology | That the police and other emergency service organisations discuss their resource issues for emergency operations with the Government. |
REC247-0850 | 13 - Mapping and data quality | That police and other emergency service agencies establish and maintain effective recording systems for emergency operations. |
REC247-0909 | 25 - Inquiry, audit, lessons management and after action review | That the plans for social recovery be reviewed, and plans and procedures are established ready for implementation. |
REC247-0873 | 25 - Inquiry, audit, lessons management and after action review | If it is considered more information is required on action to suppress the fires in Dunalley and why fire operations did not continue, the Department of Justice should conduct an independent examination of this matter. |
REC247-0927 | 25 - Inquiry, audit, lessons management and after action review | That an accountability process be established for managing improvement in the emergency management arrangements, including annual State of Readiness Reports by relevant departments and agencies and on the overall emergency management arrangements. |
REC247-0893 | 17 - Assets and technology | That further options to appropriately supplement the resources available for emergency management operations be examined. |
Rec-ID | Code | Recommendation |
---|---|---|
REC239-2670 | 12 - EM agency and authority | That prisoner transport and non-managerial roles within watch-houses should be a priority for contestability. |
REC239-2722 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service should introduce alternative means of response to automatic alarms such as small first response investigative crews e.g. two fire–fighters in a sedan (not responding under lights and siren). |
REC239-2763 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review includes a focus on the rank structure of both the Queensland Police Service and the proposed Fire and Emergency Services. |
REC239-2776 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review of the Queensland Police Service examine whether: |
REC239-2698 | 12 - EM agency and authority | That the Deputy Commissioner, Operations (of the proposed new Department of Fire and Emergency Services) should be responsible for ensuring the readiness of the disaster operations system, including the State Disaster Coordination Centre, enabling seamless transition to police control when required. |
REC239-2731 | 12 - EM agency and authority | That the CEO Portfolio Business and the Commissioner Queensland Fire and Rescue Service find a more appropriate method of accounting for part time and volunteer staff when considering the support required to raise, train and sustain this very large part of the workforce. |
REC239-2656 | 12 - EM agency and authority | That the Queensland Ambulance Service is maintained as a state-wide service into the future. |
REC239-2713 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the Deputy Commissioner of Regional Operations (Department of Fire and Emergency Services): |
REC239-2744 | 12 - EM agency and authority | That the revitalised PCYC Emergency Service Cadet Program continue to be supported by government. |
REC239-2669 | 12 - EM agency and authority | That specific business cases should be developed for contestability of correctional services in Queensland, including: |
REC239-2720 | 12 - EM agency and authority | That a reduced regional model for fire and emergency services be generally aligned to that of the Queensland Police Service with a district structure that accords with disaster districts. |
REC239-2760 | 12 - EM agency and authority | That a suitably qualified Chief Information Officer with whole of portfolio responsibility is appointed to oversight corporate support and capability development |
REC239-2775 | 17 - Assets and technology | That efforts by the courts, the Director of Public Prosecutions, the legal profession, Queensland Corrective Services and the Queensland Police Service to adopt technology for court processes should be supported through Government funding in so far as they create efficiencies, result in lower costs and produce better human rights outcomes. |
REC239-2688 | 22 - Role of local Gvt | That in establishing new disaster districts, the first guiding principle must be to align with local government boundaries and that divergence should only occur when there is a need to address a unique local circumstance. |
REC239-2730 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service actively progress initiatives for flexible employment including: |
REC239-2710 | 13 - Mapping and data quality | That all agencies participating in these activities should, as far as legally possible, share data sets whether or not the relevance is immediately obvious. |
REC239-2743 | 12 - EM agency and authority | That where practicable, the consideration for new or enhanced facilities include an assessment of the viability of creating a Rural Fire Service /SES common user facility. |
REC239-2665 | 12 - EM agency and authority | That planning, especially for infrastructure, must take into account the service delivery model (e.g. the fact that prisoners have high level health needs). |
REC239-2719 | 12 - EM agency and authority | That the current Queensland Fire and Rescue Service model of functional management be expanded, shifting line management responsibility for community safety operations and professional development from Regional Assistant Commissioners to the State Commanders. Regional Assistant Commissioners become responsible for operations and coordination of departmental support within geographic locations and report to the Deputy Commissioner operations. |
REC239-2758 | 25 - Inquiry, audit, lessons management and after action review | That the Chief Executive Officer Portfolio Business leads an efficiency review of portfolio agencies beginning with the Queensland Police Service. |
REC239-2766 | 12 - EM agency and authority | Recommendation: |
REC239-2680 | 12 - EM agency and authority | That the fire service takes a broader view of its role as an emergency management organisation. |
REC239-2727 | 25 - Inquiry, audit, lessons management and after action review | That as part of its efficiency review, the Queensland Fire and Rescue Service instigate an independent review of commercial operations in terms of statutory obligations and current ‘full cost pricing’ methodology to ensure: |
REC239-2709 | 17 - Assets and technology | That the information and communication technology solution being developed to provide situational awareness, decision support, event management and that logs critical decisions receives urgent attention to ensure timely completion. |
REC239-2742 | 12 - EM agency and authority | That the recommendations of The Malone Review in relation to Criminal History checks, so far as supported, by the Review team in this report be progressed inclusive of SES issues. |
REC239-2664 | 17 - Assets and technology | That Queensland Corrective Service should increase the use of technology as an alternative to court appearances and ensure the provision of appropriate number and level of facilities under its control. |
REC239-2716 | 12 - EM agency and authority | That the remainder of the current Emergency Management structure transition to the Commissioner, Fire and Emergency Services for further consideration regarding the most appropriate reporting alignment giving due consideration to existing capacity. This should be done in consultation with the Commissioner, the Queensland Police Service to ensure proper collaboration with the Queensland Police Service Disaster Management Unit staff. |
REC239-2754 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business should overhaul portfolio information and communication technology and appoint a Chief Information Officer with appropriate qualifications and significant industry experience as a first priority. |
REC239-2677 | 12 - EM agency and authority | That biometric tools be leveraged for other demands (e.g. bail reporting). |
REC239-2725 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service community safety operations be joined in the efficiency review of the Queensland Police Service focussing on both the community safety outcomes achieved and the extent to which they support the Government’s economic priorities. |
REC239-2765 | 12 - EM agency and authority | That the Chief Executive Officer Portfolio Business promote innovation and drive cultural change in terms of business practice. |
REC239-2778 | 17 - Assets and technology | That as the Queensland Police Service moves to a digital platform the strategy around effective targeting and alternative ANPR models should form part of the design architecture considerations. |
REC239-2707 | 12 - EM agency and authority | That the Inspector General Emergency Management ensures that improvement strategies identified are acted upon and improvement strategies embedded within agencies as standard practice. |
REC239-2734 | 12 - EM agency and authority | That a new Deputy Commissioner position be created to manage volunteer emergency services including the Rural Fire Service and the State Emergency Service. |
REC239-2663 | 12 - EM agency and authority | That the Commissioner of Queensland Corrective Service report directly to the Director-General the Department of Justice and Attorney-General. |
REC239-2715 | 12 - EM agency and authority | That the Disaster Management Standards Branch element of Standards Improvement, transition to the Inspector General Emergency Management. |
REC239-2751 | 12 - EM agency and authority | That collaboration on new initiatives such as the co-responder model in Cairns continue and if successful, initiatives should be considered for state wide or service wide adoption. |
REC239-2672 | 12 - EM agency and authority | That Queensland Corrective Service conduct business analysis and planning to clearly identify its customers and its contribution to the Government’s priorities |
REC239-2724 | 25 - Inquiry, audit, lessons management and after action review | That the Queensland Fire and Rescue Service undertake a review of all standing orders, incident directives and guidelines regarding response protocols with a view to reducing risk to staff and other road users associated with urgent duty driving. |
REC239-2764 | 25 - Inquiry, audit, lessons management and after action review | That the proposed efficiency review consider whether special service functions are core business, whether this practice is sustainable, and other options such as the use of casual employees. |
REC239-2777 | 25 - Inquiry, audit, lessons management and after action review | That the review of this Queensland Fire and Rescue Services business unit be done in conjunction with the efficiency review proposed for the Queensland Police Service. |
REC239-2706 | 12 - EM agency and authority | The establishment, management, support and education of the State Emergency Service (SES) become the responsibility of a Deputy Commissioner, Fire and Emergency Services and this person should also be responsible for Rural Fire Service Queensland. |
REC239-2733 | 12 - EM agency and authority | That the Queensland Fire and Rescue Service reduce the number of communication centres to two, with one being a primary site and the other site providing redundancy and business continuity functionality. |
REC239-2658 | 12 - EM agency and authority | That the Queensland Ambulance Service maintains its own identity to: |
REC239-2714 | 12 - EM agency and authority | That the following units of Emergency Management Queensland transition to the control of the position of Deputy Commissioner Rural Fire Service Queensland and State Emergency Services: |
REC239-2745 | 12 - EM agency and authority | That the Emergency Service Cadet Program take a full spectrum approach to emergency services |
Rec-ID | Code | Recommendation |
---|---|---|
REC165-0089 | 33 - Relief and recovery | The SDMG lead an initiative to deal at all levels with offers of assistance and donations from the general public in the event of disasters. |
REC165-0082 | 33 - Relief and recovery | Current procedures to activate disaster recovery funding arrangements be retained and processes be reinforced. |
Rec-ID | Code | Recommendation |
---|---|---|
REC140-3562 | 12 - EM agency and authority | A rapidly responsive helicopter and road retrieval capability to be developed out of RHH. |
REC140-3569 | 12 - EM agency and authority | A senior Tasmanian NETS representative be confirmed on the Tasmanian Medical Retrieval Services Committee. |
REC140-3556 | 17 - Assets and technology | The use of hospital transport vehicles to support retrieval operations be investigated. |
REC140-3561 | 17 - Assets and technology | Development of a helipad at Mersey Hospital. |
REC140-3566 | 12 - EM agency and authority | Launceston General and Burnie Hospital’s Emergency Departments require sufficient equipment, monitors and human resources to provide occasional safe local retrieval in their region. |
REC140-3560 | 17 - Assets and technology | RHH requires a helipad. Plans to rebuild RHH must include a helipad at its earliest stage of conception. |
REC140-3565 | 17 - Assets and technology | The TMRS medical equipment inventory requires an overhaul. The TMRS medical equipment should be located with the TMRS team. |
REC140-3573 | 13 - Mapping and data quality | Databases with a common minimum data set complete with incident monitoring should be established for TAS Air Ambulance, TMRS and NETS missions. |
REC140-3559 | 17 - Assets and technology | A service level agreement is negotiated with the Police department that will cover access, tasking, price, equipment and staffing. This will enable a more strategic use of the helicopter. |
REC140-3564 | 17 - Assets and technology | The medical equipment used in retrieval and air ambulance duties undertaken by helicopter and fixed wing must be standardised. |
REC140-3571 | 12 - EM agency and authority | A senior, experienced, clinically trained ambulance officer to be based in TAS Communications in Hobart for at least 14 hours a day. |
REC140-3558 | 6 - Insurance and legal liability | DHHS need to confirm adequate accident insurance coverage for staff working in retrieval medicine. Coverage specific to helicopter and fixed wing duties is required. |
REC140-3563 | 17 - Assets and technology | An additional secure emergency oxygen supply source to be located in the BK 117 helicopter. An internal supply is preferred. |
REC140-3570 | 12 - EM agency and authority | The fragmentation and duplication of fixed wing and helicopter clinical coordination should be eliminated through centralisation to TAS Communications. |
REC140-3557 | 12 - EM agency and authority | Royal Flying Doctor Service fixed wing to remain in Launceston for the duration of the current contract. |