Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC317-4093 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review those plans, and update where appropriate, to provide for coordination between states and territories in cross border areas and to provide cross-border access to evacuation centres. |
REC317-4070 | 10 - Infrastructure | Australian, state and territory governments should expedite the delivery of a Public Safety Mobile Broadband capability. |
REC317-4088 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
REC317-4092 | 11 - Evacuation and shelters | State and territory governments should ensure those responsible for evacuation planning periodically review these plans, and update them where appropriate, to account for the existence and standard of any evacuation centres and safer places (however described) in the community, including: |
REC317-4066 | 2 - Emergency powers | The Australian Government should make provision, in legislation, for a declaration of a state of national emergency. The declaration should include the following components: |
REC317-4099 | 8 - Communications and warnings | Australian, state and territory governments should continue to explore the feasibility of a national, all-hazard emergency warning app. |
REC317-4083 | 10 - Infrastructure | The Australian Government should work with state and territory governments and critical infrastructure operators to improve information flows during and in response to natural disasters: |
REC317-4091 | 11 - Evacuation and shelters | State and territory governments should provide further community education on the function and limitations of different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. This education should be nationally consistent. |
REC317-4098 | 8 - Communications and warnings | The Australian Government should facilitate state and territory governments working together to develop minimum national standards of information to be included in bushfire warnings apps. |
REC317-4082 | 10 - Infrastructure | The Australian Government, working with state and territory governments and critical infrastructure operators, should lead a process to: |
REC317-4090 | 11 - Evacuation and shelters | State and territory governments should, as a priority, adopt nationally consistent terminology and functions for the different sheltering facilities, including evacuation centres, Neighbourhood Safer Places, places of last resort and natural disaster shelters. |
REC317-4096 | 8 - Communications and warnings | State and territory governments should urgently deliver and implement thevall-hazard Australian Warning System. |
REC317-4081 | 18 - Access to fire ground | State and territory governments should provide information to the public on the closure and opening of roads. Information should be provided in real-time, or in advance based on predictions, where possible. |
REC317-4094 | 8 - Communications and warnings | State and territory governments should expedite the development and implementation of the Australian Fire Danger Rating System. It should ensure that there is national consistency in the visual display of the AFDRS and action to be taken in response to each rating. |
REC317-4080 | 18 - Access to fire ground | State and territory governments should include road closure and opening information on all roads within their borders on public apps. |
REC317-4120 | 16 - Training and behaviour | Australian, state and territory governments should establish a national mechanism for sharing of trained and qualified recovery personnel and best practice during and following natural disasters. |
REC317-4089 | 11 - Evacuation and shelters | State and territory governments should ensure that those responsible for evacuation planning periodically review those plans, and update them where appropriate, including in relation to: |
Rec-ID | Code | Recommendation |
---|---|---|
REC002-4009 | 16 - Training and behaviour | In gassy mines the Manager should be specially competent, and one possessing a thorough knowledge of the principles and practice of mining, the properties of gases, and systems of ventilation; and, above all, he must be prudent and cautious, yet resolute, possessing sound judgement. He must have absolute and supreme control over the whole operations, and of the men within the mine, to maintain rigid discipline, and be perfectly free and untrammelled by any outside influences. The competency of a manager should be certified by an examination before a specially-appointed Board. The Commission consider that better results may be obtained if such examinations be oral, and probably assume a more practical form than those hitherto conducted in Great Britain for the same object. |
Rec-ID | Code | Recommendation |
---|---|---|
REC210-0754 | 2 - Emergency powers | As part of the longer term review of the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam the Queensland Government should consider whether the dam operators should be able to extend the drawdown of the lake beyond seven days in order to reduce downstream bank slumping |
REC210-0766 | 16 - Training and behaviour | Wide Bay Water should, in addition to its usual wet season preparations and maintenance, undertake the following activities in advance of each wet season: Queensland Floods Commission of Inquiry | Final Report 29 Complete list of Final Report recommendations • conduct training for personnel on dam operation, including contingency plans for the situation in which one or more of the gates is inoperable • hold meetings of key personnel of Wide Bay Water involved in the operation of the dam during floods, which: – in addition to any other matters, inform staff about the current status of the gates, dam operation strategies and contingency plans for the situation in which one or more of the gates is inoperable – are recorded in minutes which document the information provided and are made available to all operational staff. |
REC210-0734 | 16 - Training and behaviour | Emergency Management Queensland should simplify the process by which SES members gain recognition for prior qualifications so that unnecessary duplication of training can be avoided. |
REC210-0761 | 2 - Emergency powers | The Queensland Government should consider whether to empower Seqwater, through the flood operations centre, to direct CS Energy to stop or delay releases from Splityard Creek Dam where a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. |
REC210-0695 | 10 - Infrastructure | The Queensland Government should consider implementing mandatory requirements to ensure that all conduits for the purpose of providing electrical supply below the applicable defined flood level are sealed to prevent floodwaters from entering them or flowing into them. |
REC210-0727 | 2 - Emergency powers | The Disaster Management Act 2003 should be amended to give the chief executive of the department administering the Act (or his or her delegate) the authority to appoint an officer of Emergency Management Queensland to direct SES operations in extraordinary circumstances |
REC210-0758 | 10 - Infrastructure | CS Energy should put in place contingency measures to ensure email and telephone communications at Wivenhoe Power Station are not entirely dependent on a network located off-site. |
REC210-0693 | 10 - Infrastructure | Electricity distributors should consider installing connection points for generators to provide electricity supply to non-flooded areas that have had their supply cut during floods. |
REC210-0724 | 28 - Personal responsibility | Councils should consider making available to business owners locality specific information that would assist them to develop evacuation plans for commercial premises, for example, any evacuation sub-plan created under Emergency Management Queensland’s disaster evacuation guidelines. |
REC210-0757 | 15 - Inter-service cooperation | The protocol should make provision for the use of telephone and/or radio where communication by email is not possible. Where necessary, CS Energy and Seqwater should make additional radio equipment available to relevant personnel. |
REC210-0692 | 10 - Infrastructure | The Queensland Government should consider measures to ensure that requirements are included in the designation of land for community infrastructure under the Sustainable Planning Act 2009 to ensure that critical infrastructure for operating works under the Electricity Act is built to remain operational during and immediately after a flood of a particular magnitude. That magnitude should be determined by an appropriate risk assessment. |
REC210-0723 | 28 - Personal responsibility | Councils should support and encourage business owners to develop private flood evacuation plans by providing the following to business owners in areas known to be affected by flood: • information about the benefits of evacuation plans • contact details of relevant council and emergency service personnel for inclusion in evacuation plans. |
REC210-0756 | 15 - Inter-service cooperation | CS Energy and Seqwater should agree upon and adhere to a formal communication protocol that requires CS Energy personnel to advise Seqwater, through the Flood Operations Centre, of water movements between Splityard Creek Dam and Wivenhoe Dam or Pryde Creek once a flood event is declared under the Manual of Operational Procedures for Flood Mitigation at Wivenhoe Dam and Somerset Dam. The protocol should ensure that a direct line of communication is established between CS Energy personnel physically located at the power station and the Flood Operations Centre. |
REC210-0679 | 28 - Personal responsibility | If the Queensland Development Code is amended to include provisions requiring homeowners to install sewage reflux valves, the Queensland Government should develop and make available to homeowners appropriate guidance material to assist them in meeting their responsibilities to maintain reflux valves. |
REC210-0775 | 16 - Training and behaviour | The Department of Environment and Resource Management should conduct periodic dam safety information and education sessions with emergency management personnel including those from Emergency Management Queensland, local and district disaster management groups and local councils. Priority should be given to sessions if the Bureau of Meteorology forecasts a wet season with a greater than 50 per cent chance of above median rainfall. |
Rec-ID | Code | Recommendation |
---|---|---|
REC181-0167 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment establish before the 2010–11 fire season: ■ a uniform, objective and transparent process based on the current DSE approach for the accreditation of level 3 Incident Controllers; ■ a performance review system for level 3 Incident Controllers; ■ a traineeship program for progression from level 2 to level 3 incident management team positions. |
REC181-0204 | 2 - Emergency powers | The State amend the Country Fire Authority Act 1958 to enable the Chief Officer to delegate the power to issue fire prevention notices. |
REC181-0155 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to evacuation, so that this option is planned, considered and implemented when it is likely to offer a higher level of protection than other contingency options. The approach should: ■ encourage individuals—especially vulnerable people—to relocate early; ■ include consideration of plans for assisted evacuation of vulnerable people; ■ include consideration of plans for assisted evacuation of vulnerable people. |
REC181-0174 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures for investigating safety incidents and ‘near-misses’ to ensure that all dangerous incidents, including back-burns, are fully investigated and that all relevant people are consulted and informed of the results. |
REC181-0179 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to review and modify their current practices, standards and procedures for the training and auditing of asset inspectors to ensure that registered training organisations provide adequate theoretical and practical training for asset inspectors. |
REC181-0165 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment: ■ amend their procedures to require that an incident action plan summary be completed within the first four hours of an incident being reported and be provided to the State Control Centre and, where established, to the relevant Area of Operations Control Centre; ■ adopt DSE’s incident action plan summary as the template to be used by all incident management teams and ensure that the template is included in the online IMT Tool Box; ■ provide regular training to IMT staff, highlighting the importance of information and reinforcing the support available from specialists within the State Control Centre. |
REC181-0185 | 20 - Role of police | Victoria Police continue to pursue a coordinated statewide approach to arson prevention and regularly review its approach to ensure that it contains the following elements: ■ high-level commitment from senior police; ■ a research program aimed at refining arson prevention and detection strategies; ■ centralised coordination that includes comprehensive training, periodic evaluation of arson prevention strategies and programs, and promotion of best-practice prevention approaches; ■ a requirement that all fire-prone police service areas have arson prevention plans and programs, according to their level of risk. |
REC181-0173 | 7 - Inter-agency communication | The Country Fire Authority review and improve its communications strategy as a matter of priority and develop a program for identifying and responding to black spots in radio coverage. |
REC181-0178 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to change their asset inspection standards and procedures to require that all SWER lines and all 22-kilovolt feeders in areas of high bushfire risk are inspected at least every three years. |
REC181-0184 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to strengthen Energy Safe Victoria’s mandate in relation to the prevention and mitigation of electricity-caused bushfires and to require it to fulfil that mandate. |
REC181-0151 | 11 - Evacuation and shelters | The State revise its bushfire safety policy. While adopting the national Prepare. Act. Survive. framework in Victoria, the policy should do the following: ■ enhance the role of warnings—including providing for timely and informative advice about the predicted passage of a fire and the actions to be taken by people in areas potentially in its path; ■ emphasise that all fires are different in ways that require an awareness of fire conditions, local circumstances and personal capacity; ■ recognise that the heightened risk on the worst days demands a different response; ■ retain those elements of the existing bushfire policy that have proved effective; ■ strengthen the range of options available in the face of fire, including community refuges, bushfire shelters and evacuation; ■ ensure that local solutions are tailored and known to communities through local bushfire planning; ■ improve advice on the nature of fire and house defendability, taking account of broader landscape risks. |
REC181-0172 | 15 - Inter-service cooperation | The Country Fire Authority and the Department of Sustainability and Environment standardise their operating systems and information and communications technologies with the aim of achieving greater efficiency and interoperability between agencies. |
REC181-0159 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment prescribe and audit the minimum number and nature of level 3 joint training exercises in which incident management team staff (including volunteers) are required to participate. |
REC181-0177 | 10 - Infrastructure | The State amend the Regulations under Victoria’s Electricity Safety Act 1998 and otherwise take such steps as may be required to give effect to the following: ■ the progressive replacement of all SWER (single-wire earth return) power lines in Victoria with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk. The replacement program should be completed in the areas of highest bushfire risk within 10 years and should continue in areas of lower bushfire risk as the lines reach the end of their engineering lives; ■ the progressive replacement of all 22-kilovolt distribution feeders with aerial bundled cable, underground cabling or other technology that delivers greatly reduced bushfire risk as the feeders reach the end of their engineering lives. Priority should be given to distribution feeders in the areas of highest bushfire risk. |
REC181-0183 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ fit spreaders to any lines with a history of clashing or the potential to do so; ■ fit or retrofit all spans that are more than 300 metres long with vibration dampers as soon as is reasonably practicable. |
REC181-0169 | 18 - Access to fire ground | The Country Fire Authority provide to all CFA volunteers an identification card or similar to facilitate their passage through roadblocks established in accordance with the 2009 Guidelines for the Operation of Traffic Management Points during Wildfires. |
REC181-0176 | 29 - Operational Health and Safety | The Country Fire Authority and the Department of Sustainability and Environment adopt the title ‘safety officer’ (as opposed to ‘safety adviser’) and require without exception that a safety officer be appointed to every level 3 incident management team. |
REC181-0154 | 11 - Evacuation and shelters | The State introduce a comprehensive approach to shelter options that includes the following: ■ developing standards for community refuges as a matter of priority and replacing the 2005 Fire Refuges in Victoria: Policy and Practice; ■ designating community refuges—particularly in areas of very high risk—where other bushfire safety options are limited; ■ working with municipal councils to ensure that appropriate criteria are used for bushfire shelters, so that people are not discouraged from using a bushfire shelter if there is no better option available; ■ acknowledging personal shelters around their homes as a fallback option for individuals. |
REC181-0182 | 10 - Infrastructure | The State (through Energy Safe Victoria) require distribution businesses to do the following: ■ disable the reclose function on the automatic circuit reclosers on all SWER lines for the six weeks of greatest risk in every fire season; ■ adjust the reclose function on the automatic circuit reclosers on all 22-kilovolt feeders on all total fire ban days to permit only one reclose attempt before lockout. |
REC181-0168 | 14 - Incident Mgt Teams | The Country Fire Authority and the Department of Sustainability and Environment amend their procedures to require that a suitably experienced, qualified and competent person be appointed as Incident Controller, regardless of the control agency for the fire. |
REC181-0175 | 16 - Training and behaviour | The Country Fire Authority and the Department of Sustainability and Environment require without exception that all relevant staff be trained in the need for Incident Controller approval to be obtained before a back-burn is lit. |
REC181-0160 | 20 - Role of police | The State clarify whether, during major fires, Victoria Police should discharge its coordination functions from the State Emergency Response Coordination Centre or from the State Control Centre. |
REC181-0180 | 10 - Infrastructure | The State amend the regulatory framework for electricity safety to require that distribution businesses adopt, as part of their management plans, measures to reduce the risks posed by hazard trees—that is, trees that are outside the clearance zone but that could come into contact with an electric power line having regard to foreseeable local conditions. |
Rec-ID | Code | Recommendation |
---|---|---|
REC019-4148 | 10 - Infrastructure | The Commonwealth Government be asked to complete as far as practicable, the connection of telephones to outlying country centres before the end of 1961. |
REC019-4144 | 16 - Training and behaviour | No opportunity be lost of encouraging the formation of bush fire brigades and the maintenance of enthusiasm and that the Bush Fires Board assist the brigades in any way possible to obtain adequate training and equipment. |
REC019-4158 | 16 - Training and behaviour | That needs in the direction of a fire emergency service be met as far as practicable by the Bush Fires Board in its training programme and in the tactical organisation of existing brigades for use as reserves in districts other than their own. |
REC019-4157 | 18 - Access to fire ground | Local authorities and if necessary the Minister take active steps to enforce the removal of fire hazards from the vicinity of buildings in rural areas and that special attention be given to the removal of dead trees on the edges of pasture land and on firebreaks in timbered country. |
REC019-4136 | 34 - Local knowledge | The Bush Fires Board appoint a Regional Committee of Board members co-opt local members for each climatic region of the State to study the bush fire control problems of the region and advise the Board so that inter alia adequate attention may be given by the Board to co-ordinating the beginning and termination of the prohibited burning times in adjoining districts and to any advisable variations of these duties according to seasonal conditions each year. |
REC019-4149 | 10 - Infrastructure | A sub-committee of telecommunication officers and representatives of the Bush Fires Board be appointed to investigate and encourage the development of a modern system of radio equipment for bush fire brigades. |
Rec-ID | Code | Recommendation |
---|---|---|
REC016_3947 | 15 - Inter-service cooperation | It is recommended that the services of this body [Air Raids Precautions Body] be used in future if to do so be thought desirable. |
REC016_3945 | 16 - Training and behaviour | It is recommended that a large proportion of men employed in and about the open-cut be systematically trained in the use of equipment and in the tactical disposition of it. |
REC016_3944 | 10 - Infrastructure | It is recommended that the water pressure be improved so that a greater volume and jet may be available for the suppression of fires on the faces and also for the purpose of wetting the berms more widely and thoroughly when necessary. It is suggested that there should be variable control of the pressure so that production need not be adversely affected in times of normal danger. |
REC016_3953 | 15 - Inter-service cooperation | It is therefore recommended that the State Electricity Commission should be advised by someone whose profession it is to consider and devise methods of forest fire protection and suppression; that he should collaborate with others to devise a general scheme of organized protection of the undertaking and township of Yallourn; and that above all, he should have direct access to the Commissioners themselves, lest his advice should lose something of its strength and reality in its journey through the “proper channels” of the Commission’s organization. |
REC016_3943 | 10 - Infrastructure | It is recommended that a more constant, running revision of the main and sprinkler system be maintained in future so that the service which it is intended to convey shall be closely and efficiently available to all parts of the berms and faces. It is emphasized that the reticulation system in the berms is fixed and stationary, whereas the faces are continually receding as their surfaces are scraped away by the dredges. |
REC016_3951 | 10 - Infrastructure | It is recommended that the State Electricity Commission adopt a policy of conciliation and good will towards its closer neighbours. It is not suggested that its policy has been essentially otherwise. In future that policy can best be assured of success by time conferring of material benefit upon its neighbours at some monetary cost to the Commission. It is suggested, with conviction, that it would prove to be of great advantage to time Commission if it were to take an active part in the clearing and bettering of its neighbours’ scrub and timber country at time cost of the Commission. The settler whose land is fully cleared and in production, or who knows that his land will be cleared for him, has no incentive to burn illegally or carelessly. If this suggestion should he adopted, it would be necessary that it should be carried out in all cases in accordance with the settler’s convenience, that he himself should take an active part in the operations, and that he should be left, not with a financial obligation, but with a definite material advantage. |
REC016_3948 | 16 - Training and behaviour | It is recommended that workers and volunteers generally be instructed in accordance with a pre-arranged plan, as to what they should do in future times of emergency. Since the fighting of fires is for the greater part a matter of voluntary action, some estimate could perhaps be made, after investigation, of the numbers of men in each department who would be willing to volunteer. It would be necessary that each department should become a component part of an over-riding scheme and that it and its members should be fully instructed in the matter of whistle or siren warnings, places of assembly, reception of messages from the director of proceedings, use of equipment, and the various details which would necessarily be parts of an effective scheme. The training need not be onerous. If given once or twice at the beginning of possible danger periods, it would make for some degree of order and efficiency instead of a probable state of confusion. |
Rec-ID | Code | Recommendation |
---|---|---|
REC013_3977 | 8 - Communications and warnings | To arrange with settlers who live on hills or have a clear view, and are connected by telephone, to act as " look-outs ", and to communicate with the brigade in the case of fire. |
Rec-ID | Code | Recommendation |
---|---|---|
REC008-3990 | 16 - Training and behaviour | The Commission recommends that more than one means of exit should be provided in every mine from every level of it to the surface; and that the miners should be kept informed where they are situated. |
REC008-3984 | 16 - Training and behaviour | The Commission recommends that the live parts of resistances should be fixed so that no unprotected combustible material is within 6ins of the frames or cases containing them or within 24ins measured vertically above. |
Rec-ID | Code | Recommendation |
---|---|---|
REC004-3999 | 10 - Infrastructure | That, in view of the fact that along many of the lines, between the road-bed and the fences, there are numbers of dry inflammable stumps, which, when they catch fire, are very difficult to extinguish, and that the surface of the ground surrounding these stumps is usually chipped by the permanent-way men every summer, thus causing considerable expense without removing the risk of fire, the Railway Department should remove this source of danger, by grabbing them out and burning them as early as may be found practicable. |