Inquiry Search
Rec-ID | Code | Recommendation |
---|---|---|
REC263-1091 | 36 - Volunteers | CFA and VICSES should: develop recruitment and retention strategies to guide these activities centrally, regionally and at the district, brigade and unit level, so that approaches are consistent with the organisations’ strategic goals |
REC263-1090 | 36 - Volunteers | CFA and VICSES should: improve their central and regional oversight of volunteer workforce management by strategically using the available information, such as volunteer demographic data, Brigade Operational Skills Profiles and ERAS-e profiles, and developing new information, such as risk assessment, to increase their awareness of: x x actual and required volunteer numbers the gaps and risks around volunteer capability and capacity |
REC263-1098 | 36 - Volunteers | VicSES should: improve ERAS-e profiles to reflect volunteer activity and availability |
REC263-1096 | 36 - Volunteers | CFA should: develop exit surveys and associated management reports based on meaningful analysis as a way to better inform it about the reasons that volunteers leave |
REC263-1094 | 36 - Volunteers | CFA and VICSES should: evaluate volunteer support systems and processes |
REC263-1093 | 36 - Volunteers | VICSES should: review and improve data quality around volunteer numbers and skills |
Rec-ID | Code | Recommendation |
---|---|---|
REC258-2549 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority provides full disclosure of audit findings at audit exit briefings in accordance with international best practice. |
REC258-2557 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reassesses the penalties in the Civil Aviation Safety Regulations. |
REC258-2544 | 6 - Insurance and legal liability | The Australian Transport Safety Bureau transfers information from Mandatory Occurrence Reports to the Civil Aviation Safety Authority, without redaction or de-identification. |
REC258-2556 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority structures all regulations not yet made with the three-tier approach, and subsequently reviews all other Civil Aviation Safety Regulation Parts (in consultation with industry) to determine if they should be remade using the three-tier structure. |
REC258-2543 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority reintroduces a ‘use of discretion’ procedure that gives operators or individuals the opportunity to discuss and, if necessary, remedy a perceived breach prior to CASA taking any formal action. This procedure is to be followed in all cases, except where CASA identifies a Serious and Imminent Risk to Air Safety. |
REC258-2552 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority implements a system of using third-party commercial audits as a supplementary tool to its surveillance system. |
REC258-2540 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority continues to provide appropriate indemnity to all industry personnel with delegations of authority. |
REC258-2551 | 25 - Inquiry, audit, lessons management and after action review | The Civil Aviation Safety Authority assures consistency of audits across all regions, and delivers audit reports within an agreed timeframe. |
REC258-2528 | 25 - Inquiry, audit, lessons management and after action review | The Australian Transport Safety Bureau investigates as many fatal accidents in the sport and recreational aviation sector as its resources will allow. |
REC258-2550 | 6 - Insurance and legal liability | The Civil Aviation Safety Authority introduces grading of Non-Compliance Notices on a scale of seriousness. |
Rec-ID | Code | Recommendation |
---|---|---|
REC256-1564 | 6 - Insurance and legal liability | State and territory governments, local governments and insurers should explore opportunities for collaboration and partnerships. Partnerships, for example, could be formed through the Insurance Council of Australia and state-based local government associations (or regional organisations of councils). Consideration could be given to the Trusted Information Sharing Network model. Partnerships could involve: |
REC256-1573 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should schedule an independent and public review of the progress of reforms to natural disaster funding arrangements five years after implementation has commenced. This review should examine the operation and efficacy of the arrangements, including the: |
REC256-1572 | 6 - Insurance and legal liability | Insurers should provide additional standardised information to households regarding their insurance policies, the natural hazards they face and indicative costs of rebuilding after a natural disaster. This work should be led by the Insurance Council of Australia developing guidelines, within one year, to ensure consistency in the provision and presentation of this information across insurers. |
Rec-ID | Code | Recommendation |
---|---|---|
REC236-2805 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies review whether any equipment or other changes can be made to improve the weather forecasting at Norfolk Island. The review would include whether the Unicom operator should be an approved meteorological observer. |
REC236-2801 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the ATSB review its process to track the implementation of recommendations or safety actions to ensure it is an effective closed loop system. This should be made public, and provided to the Senate Regional and Rural Affairs and Transport Committee prior to each Budget Estimates. |
REC236-2795 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that a short inquiry be conducted by the Senate Standing Committee on Rural and Regional Affairs and Transport into the current status of aviation regulatory reform to assess the direction, progress and resources expended to date to ensure greater visibility of the processes. |
REC236-2793 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that CASA processes in relation to matters highlighted by this investigation be reviewed. This could involve an evaluation benchmarked against a credible peer (such as FAA or CAA) of regulation and audits with respect to: non-RPT passenger carrying operations; approach to audits; and training and standardisation of FOI across regional offices. |
REC236-2792 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the investigation be re-opened by the ATSB with a focus on organisational, oversight and broader systemic issues. |
REC236-2806 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the relevant agencies investigate appropriate methods to ensure that information about the incidence of, and variable weather conditions at, Norfolk Island is available to assist flight crews and operators managing risk that may result from unforseen weather events. |
Rec-ID | Code | Recommendation |
---|---|---|
REC229-2840 | 39 - Disaster Risk Management | The committee recommends relevant authorities work with community service organisations in both planning responses to and responding to extreme weather events, in particular those organisations that provide vital services to vulnerable groups. |
Rec-ID | Code | Recommendation |
---|---|---|
REC207-2882 | 39 - Disaster Risk Management | Review disaster recovery and business continuity plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC205-1906 | 6 - Insurance and legal liability | Governments should not subsidise household or business property insurance, whether directly or by underwriting risks. |
REC205-1905 | 6 - Insurance and legal liability | The Australian Government should only proceed with reforms that require all household insurers to offer flood cover if it can be demonstrated that the benefits to the wider community would exceed the costs. |
REC205-1903 | 25 - Inquiry, audit, lessons management and after action review | The Australian Government should commission an independent public review of disaster prevention and recovery arrangements. This should be broader than the review currently being conducted by the Attorney-General’s Department. The review should cover the Natural Disaster Relief and Recovery Arrangements, as well as the funding mechanisms for disaster mitigation, including the National Partnership Agreement on Natural Disaster Resilience. This review should: |
REC205-1902 | 25 - Inquiry, audit, lessons management and after action review | The Council of Australian Governments should commission an independent public inquiry to develop an appropriate response to managing the risks of climate change to existing settlements. The inquiry should: |
Rec-ID | Code | Recommendation |
---|---|---|
REC188-2917 | 33 - Relief and recovery | The committee recommends that relevant Commonwealth agencies continue to monitor the wellbeing of their personnel and that counselling and support services should be provided for as long as necessary. |
REC188-2916 | 33 - Relief and recovery | The committee recommends that the Department of Regional Australia and DIAC liaise with the Christmas Island community to explore options for a permanent memorial to be erected on the island, at a site of the residents' choosing, for the victims of the tragedy. |
REC188-2915 | 33 - Relief and recovery | The committee recommends that Department of Immigration and Citizenship (DIAC) and its relevant contractors continue to monitor the wellbeing of the survivors and that counselling and support services should be provided for as long as is necessary. |
Rec-ID | Code | Recommendation |
---|---|---|
REC185-1933 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Treasury clarify what is meant by the term 'cost-effective' as it relates to the 2011 NDRRA Determination and the scrutiny of the states' and territories' insurance arrangements. |
REC185-1932 | 6 - Insurance and legal liability | The committee recommends that a particular focus of the Natural Disasters Insurance Review into the adequacy of current insurance arrangements should be on whether the international insurance market offers reinsurance for the states' and territories' road networks. |
REC185-1930 | 6 - Insurance and legal liability | The committee recommends that the Commonwealth Government consult with state and territory governments to ensure that the states' and territories' captive insurance and reinsurance arrangements are reported transparently and on a comparable basis. |
Rec-ID | Code | Recommendation |
---|---|---|
REC177-3310 | 6 - Insurance and legal liability | Consideration should be given to ways to ensure that contractors who are involved in barrier installation (such as cementing companies) have a direct interest in the performance of works to a proper standard. In particular, consideration should be given to (i) preventing contractors from avoiding the economic consequences of negligent installation of barriers; and/or (ii) imposing specific legislative standards of workmanship on contractors with respect to well control (similar to those which presently apply to licensees). |
REC177-3369 | 6 - Insurance and legal liability | The obligation of companies involved in an incident to meet the full costs of monitoring and remediation should be made a condition of approval of proposals under the EPBC Act and OPGGS Act. Suitable arrangements (insurance or otherwise) need to be in place to ensure that companies have this capacity. |
REC177-3291 | 39 - Disaster Risk Management | Removal of a barrier must be the subject of consultation between licensees and rig operators prior to removal. A proper risk assessment should be carried out and agreed upon, and documented in writing before removal. Joint written certification as to the appropriateness of removal should take place before removal. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3365 | 6 - Insurance and legal liability | The National Plan should specify that the cost of responding to an oil spill, or other damage to the offshore marine environment, will be totally met by the owner/operator. This would be consistent with the Inquiry’s recommendation for legislative changes to the regulatory framework concerning owner/operators meeting the cost of monitoring and remediation of environmental damage. |
REC177-3289 | 39 - Disaster Risk Management | The use/type of barriers (including any change requests relating thereto) must be the subject of consultation between licensees and rig operators prior to installation. A proper risk assessment should be carried out, agreed upon, and documented in writing before installation. Joint written certification as to the appropriateness of the use of particular barriers should take place before installation. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3356 | 39 - Disaster Risk Management | The regulator should pre‐assess and review in a generic sense, and in conjunction with the offshore petroleum industry, available options for well control in the event of a blowout. Being ‘match fit’ in this sense will enable a quicker and more effective response in terms of safety assessment, and will ensure that expectations of both operator and regulator are more readily aligned. |
REC144-3387 | 25 - Inquiry, audit, lessons management and after action review | In order that the ACT public can be reassured about the project management and financial planning in relation to the Fairbairn site as a proposed centralised accommodation facility for emergency services, the Auditor-General undertake a review of the project from a financial probity and project management perspective. |
REC177-3286 | 39 - Disaster Risk Management | Problems which arise in the course of installing barriers must be the subject of consultation between licensees, rig operators, and contractors (if used). A proper risk assessment should then be carried out and remedial steps (including further testing/verification) should be agreed upon, and documented in writing before the performance of remedial work whenever practicable. Joint written certification as to resolution of the problem should take place before resumption of drilling operations. Senior onshore representatives of stakeholder entities should be involved in that certification process. |
REC177-3344 | 25 - Inquiry, audit, lessons management and after action review | There should be a review to determine whether it is appropriate to introduce a rigorous civil penalty regime and/or substantially increase some or all of the penalties that can be imposed for breaches of legislative requirements relating to well integrity and safety. |
REC177-3378 | 25 - Inquiry, audit, lessons management and after action review | In view of the numerous well integrity problems in all of the Montara Oilfield wells, the Minister should commission a detailed audit of all the other offshore wells operated by PTTEPAA to determine whether they too may suffer from well integrity problems. |
REC177-3285 | 39 - Disaster Risk Management | Pre‐drilling assessments should include a risk assessment of the worst‐case blowout scenario. |
REC177-3330 | 39 - Disaster Risk Management | Decision‐making about well control issues should be professionalised. Industry participants must recognise that decision‐makers owe independent duties to the public, not just their employer or principal, in relation to well control. Risk management in the context of well control needs to be understood as an ethical/professional duty. Self‐regulation contemplates self‐regulation by the industry, not just by individual licensees and operators. |
REC177-3374 | 25 - Inquiry, audit, lessons management and after action review | The Minister should, as the JA for the offshore area of the Territory of Ashmore and Cartier Islands, undertake a review of PTTEPAA’s permit and licence to operate at the Montara Oilfield. |
Rec-ID | Code | Recommendation |
---|---|---|
REC174-2985 | 25 - Inquiry, audit, lessons management and after action review | To provide adequate assurance on the validity of claims paid for disaster recovery assistance, the ANAO recommends that Centrelink: |
REC174-2984 | 39 - Disaster Risk Management | To improve Centrelink’s preparedness for responding to future disasters, the ANAO recommends that Centrelink include disasters that impact on multiple Areas in its emergency and business continuity test exercise program. |
Rec-ID | Code | Recommendation |
---|---|---|
REC161-3030 | 25 - Inquiry, audit, lessons management and after action review | That National Offshore Petroleum Safety Authority review the risk assessment of pipelines. National Offshore Petroleum Safety Authority should focus, in particular, on the efficacy of anti-corrosion systems, and recognise potential interference effects and MAE escalation risks associated with adjacent pipelines and unlicenced pipes even if they fall outside its direct regulatory responsibilities. |
Rec-ID | Code | Recommendation |
---|---|---|
REC158-3452 | 25 - Inquiry, audit, lessons management and after action review | That the nominated marine safety authority undertakes a further assessment to determine the recommendations from this Review that may also be applicable to State waters outside commercial port waters. |
Rec-ID | Code | Recommendation |
---|---|---|
REC149-3145 | 25 - Inquiry, audit, lessons management and after action review | NOPSA should consider an audit regime that targets Greenfields operations at commencement of operations. |
REC149-3139 | 39 - Disaster Risk Management | The industry should develop in conjunction with the Regulator a process for addressing the need to maintain the risk profile of a facility moving into extended life operation at the same risk profile as when it was within design life. |
Rec-ID | Code | Recommendation |
---|---|---|
REC146-3193 | 25 - Inquiry, audit, lessons management and after action review | The committee recommends that the Australian National Audit Office audit CASA's implementation and administration of its Safety Management Systems approach. |
Rec-ID | Code | Recommendation |
---|---|---|
REC145-3212 | 6 - Insurance and legal liability | The Committee recommends that the Australian Government request the Productivity Commission to undertake an inquiry into the projected impacts of climate change and related insurance matters, with a particular focus on: |
REC145-3210 | 39 - Disaster Risk Management | The Committee recommends that the Department of Climate Change, in collaboration with the Queensland Government, CSIRO and Indigenous communities in the Torres Strait, undertake a major study into the vulnerability of the Torres Strait to the impacts of climate change and provide assistance in the development of an adaptation plan. |
REC145-3209 | 39 - Disaster Risk Management | The Committee notes that major initiatives relating to climate change adaptation risk assessment and infrastructure are currently in progress. Given that much of Australia’s infrastructure is in the coastal zone and the particular threats facing the coastal zone from climate change, involving significant socioeconomic costs, the Committee recommends that the Australian Government ensure there is a comprehensive national assessment of coastal infrastructure vulnerability to inundation from sea level rise and extreme sea level events. |
REC145-3203 | 39 - Disaster Risk Management | The Committee recommends that: |
REC145-3227 | 39 - Disaster Risk Management | The Committee recommends that coastal based Natural Resource Management bodies seeking funding under the Caring for our Country program have coastal and marine priorities, as well as coastal zone management principles integrated in their management plans. |
Rec-ID | Code | Recommendation |
---|---|---|
REC123-3877 | 25 - Inquiry, audit, lessons management and after action review | All agencies review formal and informal incident notification processes to ensure they support the earliest possible reporting of emergencies to all stakeholders involved in the Airport Emergency Plan and in so doing, ensure early access to specialist advice and support. |
Rec-ID | Code | Recommendation |
---|---|---|
REC116-2104 | 39 - Disaster Risk Management | The Working Group recommends that in addition to existing disease control and pandemic management plans, States/Territories should consider developing a pandemic emergency management plan that considers the impact of pandemic disease broadly, encompasses all government and private sector agencies and addresses: |
REC116-2122 | 33 - Relief and recovery | The Working Group recommends that States/Territories consider their ability to house large numbers of domestic pets, and where necessary, develop plans and arrangements that facilitate this need. |
REC116-2103 | 33 - Relief and recovery | The Working Group recommends that jurisdictions plan for the logistics of supply and delivery of meals to large numbers of homebound persons in an attempt to identify possible ways of resolving existing shortcomings. |
REC116-2120 | 33 - Relief and recovery | The Working Group recommends that the National Recovery Coordinators Group considers the issue of emergency relief centres in the context of catastrophic disaster with a view to assisting jurisdictions to plan for the need to accommodate thousands of people following a disaster. |
REC116-2119 | 6 - Insurance and legal liability | The Working Group recommends that the National Recovery Coordinators Group approach the Investment and Financial Services Association Limited, with a view to identifying the most appropriate way of engaging the life insurance industry in the recovery process. |
REC116-2117 | 33 - Relief and recovery | The Working Group recommends that potential shortfalls in the capacity to deal with large numbers of unprotected children and other special needs groups in a catastrophic event be referred to the Disaster Recovery Sub Committee of Community Services Ministers’ Advisory Council (CSMAC) for consideration and report back. |
REC116-2116 | 39 - Disaster Risk Management | The working group recommends that a similar project to the Review of Australia's Ability to Respond to and Recover from Catastrophic Disasters be established to consider the longer term consequences of catastrophic disasters and their resulting recovery implications. Key aspects of such a review would include: |
REC116-2127 | 39 - Disaster Risk Management | The Working Group recommends that the Australian Government and the States/Territories use the survey templates compiled in each of their jurisdictions during the capability review workshops, and the scenarios to consider their current and future capabilities, to respond to and recover from large scale disasters. |